1Formulas and methods
Time value of money
Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i
Method
Draw a timeline with every cash flow and its timing.
Match the rate to the period: a monthly rate for monthly payments.
Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
Check the sign and the order of magnitude of the answer.
NPV & IRR
Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)
Method
List all cash flows with their year; the investment at year 0 is negative.
Discount each cash flow: CFt/(1 + r)t.
Add them up to get the NPV. Positive means the project earns more than r.
For the IRR, find the rate that makes NPV zero by trial or interpolation.
Bond pricing & yield
Bond price
P = C·(1 − (1 + y)−n)/y + F/(1 + y)n
Semi-annual
C/2, y/2 and 2n periods
Current yield
C/P
Price and yield
yield up → price down
Method
Find the coupon per period and the yield per period.
Price = present value of the coupons (an annuity) + present value of the face value.
For semi-annual coupons use half the coupon, half the yield and twice the periods.
Check: if the yield is above the coupon rate, the price is below face value.
CAPM & WACC
CAPM
re = rf + β·(rm − rf)
WACC
E/V·re + D/V·rd·(1 − T)
Firm value
V = E + D
Break-even analysis
Contribution margin
CM = p − v
Break-even quantity
QBE = FC/(p − v)
Target profit
Q = (FC + profit)/(p − v)
Profit
π = (p − v)·Q − FC
Margin of safety
(Q − QBE)/Q
2Practice problems
1.Time value of moneyMedium
You invest €5 000 at 6% per year with continuous compounding. Find the value FV after 12 years.
PV = €5 000r = 6%t = 12
FV = €
2.Time value of moneyHard
You borrow €12 000 at 5.4% per year, compounded monthly, and repay €375 at the end of every month. How many months does it take until the loan is repaid (the last payment may be smaller)? Give the number of payments N.
P = €12 000A = €3755.4% / 12
N = payments
3.NPV & IRRMedium
An investment of €60 000 gives these cash flows at the end of years 1 to 4: €14 000, €26 000, €17 000, €24 000. The cost of capital is 7.000000000000001%. Find the net present value NPV.
A project costs €10 000 and returns €7 000, €6 500 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
CF0 = −10 000CF1 = 7 000CF2 = 6 500
IRR = %
5.Bond pricing & yieldMedium
You buy a bond with 3 years to maturity (face value €1 000, annual coupon 4%) when its yield to maturity is 2.5%. One year later, just after receiving the first coupon, you sell it when the yield to maturity is 4%. Find your holding period return HPR in percent.
F = €1 000coupon = 4%n = 3y0 = 2.5%y1 = 4%
HPR = %
6.Bond pricing & yieldHard
A bond with a face value of €1 000 and an annual coupon of 6% matures in 5 years and sells for €920. Find its yield to maturity YTM in percent.
F = €1 000coupon = 6%n = 5P = €920
YTM = %
7.CAPM & WACCMedium
A company has equity worth €12 000 000 and debt worth €3 000 000. Its cost of equity is 8%, its pre-tax cost of debt is 5% and the tax rate is 25.8%. Find the WACC.
A company has 1 000 000 shares at €59.50 each and 40 000 bonds trading at €1 050 each. The pre-tax cost of debt is 5% and the tax rate is 20%. The share’s beta is 1.5, the risk-free rate 3.5% and the market return 8%. Find the WACC.
β = 1.5rf = 3.5%rm = 8%rd = 5%T = 20%
WACC = %
9.Break-even analysisMedium
A product sells for €26 per unit with a variable cost of €6 per unit. Fixed costs are €30 000 per month. How many units Q must be sold per month to make a profit of €10 000?
F = €30 000p = €26v = €6profit = €10 000
Q = units
10.Break-even analysisHard
A product sells for €35 per unit, with a variable cost of €30 per unit and fixed costs of €2 500 per year. Budgeted sales are 580 units. Find the margin of safety MS as a percentage of budgeted sales.
F = €2 500p = €35v = €30budget = 580
MS = %
3Solutions
1.Time value of money
Answer: FV = 10272 €
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Exponent
r·t = 0.06·12 = 0.72
e0.72 = 2.054
Future value
FV = 5 000·2.054 = €10 272.17
Answer
FV = €10 272.17
2.Time value of money
Answer: N = 35 payments
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Rearrange the annuity formula
i = 0.0045
(1 + i)−N = 1 − 12 000·0.0045/375 = 0.856
Solve with logarithms
N = −ln(0.856)/ln(1.004) = 34.63
Round up to whole payments
34 full payments leave a small balance, which the last, smaller payment clears.
N = 35
Answer
N = 35 payments
3.NPV & IRR
Answer: NPV = 7980 €
Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.
Present value of each cash flow
CF0 = −60 000
CF1/(1 + 0.07)1 = 14 000/1.07 = 13 084.11
CF2/(1 + 0.07)2 = 26 000/1.145 = 22 709.41
CF3/(1 + 0.07)3 = 17 000/1.225 = 13 877.06
CF4/(1 + 0.07)4 = 24 000/1.311 = 18 309.49
Add them up
NPV = €7 980.07
Answer
NPV = €7 980.07
NPV is positive, so the project earns more than the required return.
4.NPV & IRR
Answer: IRR = 22.89 %
Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.
Bracket the IRR
NPV falls as the rate rises, so the IRR lies between a rate with positive NPV and one with negative NPV.
NPV(20%) = 347.22
NPV(25%) = −240.00
Narrow down
Linear interpolation gives a first estimate; repeating it (or a calculator's IRR function) gives the exact rate.
IRR ≈ 20 + 5·347.22/(347.22 − (−240.00)) = 22.96%
exact: NPV(22.89%) = 0 → IRR = 22.89%
Answer
IRR = 22.89%
5.Bond pricing & yield
Answer: HPR = −0.2724 %
Bond pricing: a bond’s price is the present value of its cash flows, discounted at the yield to maturity (YTM): the coupons form an annuity and the face value is paid back at maturity. P = C·(1 − (1 + y)⁻ⁿ)/y + F/(1 + y)ⁿ. When the yield is above the coupon rate the bond trades below face value, and the other way round.
Bond pricing: a bond’s price is the present value of its cash flows, discounted at the yield to maturity (YTM): the coupons form an annuity and the face value is paid back at maturity. P = C·(1 − (1 + y)⁻ⁿ)/y + F/(1 + y)ⁿ. When the yield is above the coupon rate the bond trades below face value, and the other way round.
Equation for the yield
€920 = €60·(1 − (1 + y)⁻⁵)/y + €1 000/(1 + y)⁵
Solve numerically
P(8%) = €920.15, P(9%) = €883.31
YTM = 8.004%
Answer
YTM = 8.004%
7.CAPM & WACC
Answer: WACC = 7.142 %
Cost of capital: CAPM gives the return shareholders require: re = rf + β·(rm − rf). The weighted average cost of capital mixes equity and debt by their market values: WACC = E/V·re + D/V·rd·(1 − T), with V = E + D. Interest is tax-deductible, hence the (1 − T).
Weights
V = €15 000 000, E/V = 0.8, D/V = 0.2
WACC
WACC = 0.8·8% + 0.2·5%·(1 − 0.258) = 7.142%
Answer
WACC = 7.142%
8.CAPM & WACC
Answer: WACC = 7.664 %
Cost of capital: CAPM gives the return shareholders require: re = rf + β·(rm − rf). The weighted average cost of capital mixes equity and debt by their market values: WACC = E/V·re + D/V·rd·(1 − T), with V = E + D. Interest is tax-deductible, hence the (1 − T).
Cost-volume-profit: each unit sold earns a contribution margin, price minus variable cost per unit. Profit = Q·(p − v) − F, where F is the fixed cost. At the break-even point profit is zero, so Q = F/(p − v).
Cost-volume-profit: each unit sold earns a contribution margin, price minus variable cost per unit. Profit = Q·(p − v) − F, where F is the fixed cost. At the break-even point profit is zero, so Q = F/(p − v).