1Formulas and methods

Graph theory

Handshake lemma
Σ deg(v) = 2|E|
Complete graphs
|E(Kn)| = n(n − 1)/2, |E(Km,n)| = m·n
Regular graph
|E| = n·k/2
Tree and forest
|E| = n − 1, |E| = n − c
Leaves of a tree
L = 2 + Σ (deg(v) − 2) over deg(v) ≥ 3
Euler
circuit: all degrees even; path: exactly 2 odd degrees
Hamilton circuits in Kn
(n − 1)!/2
Dijkstra update
d(v) = min(d(v), d(u) + w(u, v))
Walks of length L
(Mᴸ)ij

Method

  1. Write down the degree of every vertex; the degrees add up to twice the number of edges.
  2. For Euler questions, check that the graph is connected and count the vertices with odd degree.
  3. For trees, use n − 1 edges and the handshake lemma.
  4. For Dijkstra, keep a table of tentative distances and settle the smallest unsettled vertex each round.
  5. For a minimum spanning tree, sort the edges by weight and skip every edge that closes a cycle (Kruskal), or grow one tree from a start vertex (Prim).

2Practice problems

1.Algorithms & complexityMedium

What is the time complexity of the standard dynamic programming algorithm for the longest common subsequence of strings of lengths m and n?

  1. AO(mn)
  2. BO(mn log n)
  3. CO(m + n)
  4. DO(2m+n)
2.Algorithms & complexityHard

What did the Cook–Levin theorem establish?

  1. AThe Boolean satisfiability problem (SAT) is NP-complete
  2. BP is not equal to NP
  3. CEvery NP problem can be solved in exponential time
  4. DThe halting problem is undecidable
3.Data structuresMedium

Which abstract data type does Dijkstra's algorithm use to choose the next vertex to process?

  1. AA FIFO queue
  2. BA min-priority queue
  3. CA set with no ordering
  4. DA stack
4.Data structuresHard

What guarantee do the red-black tree rules give about the height of a tree with n keys?

  1. AThe height is exactly log2 n
  2. BThe height is at most log2 n + 1
  3. CThe height is at most 2 log2(n + 1)
  4. DThe height is at most n / 2
5.Graph theoryMedium
ABCDEFEuler circuitEuler path, no circuitneither

Does the connected graph have an Euler circuit, an Euler path that is not a circuit, or neither? Click your answer.

|V| = 6|E| = 7
  1. 1Euler circuit
  2. 2Euler path, no circuit
  3. 3neither
6.Graph theoryHard
12616101552ABCDE

Kruskal’s algorithm builds a minimum spanning tree. Click the edge it adds as edge number 4; skipped edges do not count.

k = 4
  1. 1edge AB
  2. 2edge AC
  3. 3edge BC
  4. 4edge BD
  5. 5edge CE
  6. 6edge DE
  7. 7edge BE

3Solutions

1.Algorithms & complexity

Answer: A · O(mn)

Why this is the answer

The table has (m + 1)(n + 1) cells and each is computed in O(1) from its neighbours.

Answer

A · O(mn)
2.Algorithms & complexity

Answer: A · The Boolean satisfiability problem (SAT) is NP-complete

Why this is the answer

Cook and Levin showed independently that every problem in NP reduces to SAT in polynomial time, so SAT was the first known NP-complete problem.

Answer

A · The Boolean satisfiability problem (SAT) is NP-complete
3.Data structures

Answer: B · A min-priority queue

Why this is the answer

A min-priority queue, usually a binary heap, returns the unvisited vertex with the smallest distance efficiently.

Answer

B · A min-priority queue
4.Data structures

Answer: C · The height is at most 2 log2(n + 1)

Why this is the answer

Every path has the same number of black nodes and red nodes cannot be adjacent, so the longest path is at most twice the shortest, giving height O(log n).

Answer

C · The height is at most 2 log2(n + 1)
5.Graph theory

Answer: Euler path, no circuit

Euler, Hamilton and trees: a connected graph has an Euler circuit (every edge once, back to the start) when every vertex has even degree, and an Euler path that is not a circuit when exactly two vertices have odd degree; the path then runs from one odd vertex to the other. A Hamilton circuit visits every vertex once; Kn has (n − 1)!/2 of them. A tree on n vertices has n − 1 edges, and a connected graph with m edges keeps a spanning tree after removing m − n + 1 edges.

Degrees

deg(A) = 2, deg(B) = 4, deg(C) = 3, deg(D) = 2, deg(E) = 2, deg(F) = 1

Odd vertices

C, F → 2
Euler path, no circuit

Answer

Euler path, no circuit

The Euler path starts at one odd vertex and ends at the other.

6.Graph theory

Answer: edge AB

Shortest paths and spanning trees: Dijkstra’s algorithm settles one vertex per round: the unsettled vertex with the smallest tentative distance. Its distance is then final, and every neighbour v gets d(v) = min(d(v), d(u) + w(u, v)). Kruskal’s algorithm builds a minimum spanning tree by taking the edges from light to heavy and skipping any edge that would close a cycle; Prim’s algorithm grows one tree from a start vertex by always adding the lightest edge that leaves it. A spanning tree of n vertices has n − 1 edges.

Kruskal’s algorithm

1. BE (2)
2. DE (5)
3. AC (6)
4. AB (12)

edge number 4

AB

Answer

edge AB