laminar below Re ≈ 2000, turbulent above Re ≈ 4000
Mean velocity
V = Q/A, A = π·D²/4
Darcy–Weisbach
hf = f·(L/D)·V²/(2g)
Minor losses
hm = ΣK·V²/(2g)
Typical K values
entrance 0.5, exit 1.0, 90° bend ≈ 0.3
Pressure drop
Δp = ρ·g·hf
Two open reservoirs
Δz = (f·L/D + ΣK)·V²/(2g)
Free outlet
H = (1 + f·L/D + ΣK)·V²/(2g)
Open-channel flow (Manning)
Manning equation
V = (1/n)·R2/3·S1/2
Flow rate
Q = A·V
Hydraulic radius
R = A/P (P = wetted perimeter, free surface excluded)
Rectangle
A = b·y, P = b + 2y
Trapezoid (side slope z:1)
A = (b + z·y)·y, P = b + 2y·√(1 + z²)
Circular pipe, full or half full
R = D/4
Required slope
S = (n·Q/(A·R2/3))²
Pumps & pump power
Hydraulic power
Ph = ρ·g·Q·H = Q·Δp
Shaft power
Pshaft = Ph/ηpump
Electrical power
Pel = Pshaft/ηmotor
Pump head
H = Δz + Δp/(ρ·g) + hL
System losses
hL = (f·L/D + ΣK)·V²/(2g)
Time value of money
Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i
Method
Draw a timeline with every cash flow and its timing.
Match the rate to the period: a monthly rate for monthly payments.
Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
Check the sign and the order of magnitude of the answer.
NPV & IRR
Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)
Method
List all cash flows with their year; the investment at year 0 is negative.
Discount each cash flow: CFt/(1 + r)t.
Add them up to get the NPV. Positive means the project earns more than r.
For the IRR, find the rate that makes NPV zero by trial or interpolation.
Normal distribution
z-score
z = (x − μ)/σ
Below x
P(X < x) = Φ(z)
Above x
P(X > x) = 1 − Φ(z)
Between
Φ(z2) − Φ(z1)
Percentile
x = μ + z·σ
Method
Convert the value to a z-score: z = (x − μ)/σ.
Look up Φ(z), the area to the left of z.
For the area to the right use 1 − Φ(z); for an interval subtract the two left areas.
For a percentile, work backwards: find z for the area, then x = μ + z·σ.
2Practice problems
1.Beam support reactionsMedium
The cantilever beam is fixed to the wall at A. It carries a uniformly distributed load w along its whole length and a point load P at 4 m from the wall. Find the magnitude of the reaction moment MA at the wall.
L = 8 mP = 10 kN at 4 mw = 12 kN/m from 0 to 8 m
MA = kN·m
2.Beam support reactionsHard
The simply supported beam has a pin at A and a roller at B. A load P acts at 1 m from A, inclined at 45° to the horizontal, and a vertical load Q acts at 3.5 m from A. Find the magnitude of the total reaction force RA at the pin A.
L = 4 mP = 15 kN at 1 m, θ = 45°Q = 50 kN at 3.5 m
RA = kN
3.Truss: method of jointsMedium
Exactly one member of this truss carries no force under these loads. Which is the zero-force member? Click it in the diagram.
F: 10 kN ↓
1member AB
2member BC
3member CD
4member DE
5member FG
6member GH
7member AF
8member HE
9member BF
10member CG
11member DH
12member BG
13member DG
4.Truss: method of jointsHard
Exactly one member of this truss carries no force under these loads. Which is the zero-force member? Click it in the diagram.
B: 30 kN ↓F: 15 kN ↓F: 10 kN →H: 15 kN ↓
1member AB
2member BC
3member CD
4member DE
5member FG
6member GH
7member AF
8member HE
9member BF
10member CG
11member DH
12member BG
13member DG
5.Shear force & bending momentMedium
The marks A to G split the beam into six equal parts. At which mark is the bending moment largest in size, sagging or hogging? Click it in the diagram.
50 kN @ 2 m10 kN/m, 0–5 m
1A (x = 0 m)
2B (x = 1 m)
3C (x = 2 m)
4D (x = 3 m)
5E (x = 4 m)
6F (x = 5 m)
7G (x = 6 m)
6.Shear force & bending momentHard
The simply supported beam carries a uniformly distributed load w over its whole span and a point load P. Find the maximum bending moment Mmax in the beam.
L = 5 mP = 60 kN at 4 mw = 8 kN/m from 0 to 5 m
Mmax = kN·m
7.Beam deflectionMedium
A simply supported beam carries a uniformly distributed load w over its whole span. Find the maximum deflection δmax, at midspan.
w = 10 kN/mL = 5 mE = 200 GPa (steel)I = 160 × 10⁶ mm⁴
δmax = mm
8.Beam deflectionHard
A simply supported beam carries a uniformly distributed load w. Its deflection may not exceed span/360. Find the smallest second moment of area Ireq that meets this limit.
w = 5 kN/mL = 3 mE = 11 GPa (timber)
Ireq = × 10⁶ mm⁴
9.Column bucklingMedium
A column of length L made of steel is fixed at the base and free at the top. Using Euler’s formula, find its critical buckling load Pcr.
L = 1.5 mE = 200 GPa (steel)b × h = 30 × 50 mm
Pcr = kN
10.Column bucklingHard
A column of length L made of aluminium is fixed at the base and pinned at the top. Find its slenderness and the critical buckling stress σcr from Euler’s formula.
L = 3 mE = 70 GPa (aluminium)d = 40 mm
σcr = MPa
11.Centroid & second moment of areaMedium
A symmetric I-section has flanges 140 mm wide and 22 mm thick, an overall depth of 320 mm and a web 10 mm thick. Find its second moment of area Ix about the horizontal centroidal axis x.
B = 140 mmH = 320 mmtf = 22 mmtw = 10 mm
Ix = × 10⁶ mm⁴
12.Centroid & second moment of areaHard
The T-section is used as a beam with the flange on top and carries a sagging bending moment of 20 kN·m. Find the bending stress σbottom at the bottom edge.
A 3.5 m thick overconsolidated clay layer has Cc = 0.5, Cr = 0.04 and e₀ = 1. At its mid-depth the effective vertical stress is 55 kPa and the overconsolidation ratio is OCR = 1.5. A new building adds 20 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.
A clay layer 2.5 m thick has a coefficient of consolidation cv = 1 m²/year. It lies on impervious rock, with sand above it, so water drains out only at the top. For 50% average consolidation the time factor is Tv = 0.197. How many years t does the layer take to reach 50% consolidation?
A vertical rectangular gate 1 m wide sits in the wall of a tank of water, with its top edge 1 m below the surface. Find the resultant hydrostatic force F on the gate.
d = 1 mH = 2 mb = 1 mρ = 1000 kg/m³g = 9.81 m/s²
F = kN
18.Hydrostatic forceHard
A vertical rectangular gate 1 m wide sits in the wall of a tank of seawater, with its top edge 3 m below the surface. Find the resultant hydrostatic force F on the gate.
Water flows at 25 L/s through a pipe 400 m long with an inside diameter of 200 mm. Use the Darcy friction factor f = 0.03 and g = 9.81 m/s². Find the friction head loss hf.
Two open reservoirs are joined by a pipe 400 m long with an inside diameter of 300 mm and a Darcy friction factor f = 0.018. The minor losses are a square-edged entrance (K = 0.5), 2 bends (K = 0.3 each), a valve (K = 5) and the exit into the lower reservoir (K = 1.0). Use g = 9.81 m/s². What difference in water level Δz between the reservoirs gives a flow rate of 75 L/s?
A rectangular brickwork channel is 2.5 m wide. Water flows uniformly 1.1 m deep. Manning n = 0.015 and the bed slope is S = 0.0005. Find the flow rate Q in m³/s.
b = 2.5 my = 1.1 mn = 0.015S = 0.0005
Q = m³/s
22.Open-channel flow (Manning)Hard
A concrete sewer with an inside diameter of 450 mm (Manning n = 0.013) must reach a self-cleansing velocity of 1 m/s when flowing just full. Find the minimum slope S (in m/m).
D = 450 mmn = 0.013V = 1 m/s
S = m/m
23.Pumps & pump powerMedium
In a test, a pump delivers 15 L/s of water (ρ = 1000 kg/m³) against a head of 66 m while its shaft takes 16.2 kW. Use g = 9.81 m/s². Find the pump efficiency η in percent.
Q = 15 L/sH = 66 mPshaft = 16.2 kWg = 9.81 m/s²
η = %
24.Pumps & pump powerHard
A pump moves 75 L/s of water (ρ = 1000 kg/m³) from an open lower reservoir to an upper tank whose water surface is 11 m higher. The pipe is 600 m long with an inside diameter of 200 mm and a Darcy friction factor f = 0.015; the minor-loss coefficients add up to ΣK = 6 (entrance and exit included). Use g = 9.81 m/s². The upper tank is closed and the air above its water is at a gauge pressure of 150 kPa. Find the head H the pump must add.
A credit card charges a nominal interest rate of 15% per year, compounded monthly. Find the effective annual rate EAR in percent.
r = 15%m = 12
EAR = %
26.Time value of moneyHard
You borrow €12 000 at 4.8% per year, compounded monthly, and repay €200 at the end of every month. How many months does it take until the loan is repaid (the last payment may be smaller)? Give the number of payments N.
P = €12 000A = €2004.8% / 12
N = payments
27.NPV & IRRMedium
A project costs €400 000 today. It generates €29 000 at the end of the first year, and the cash flow then grows by 3% per year forever. The cost of capital is 12%. Find the net present value NPV.
C0 = €400 000CF1 = €29 000g = 3%r = 12%
NPV = €
28.NPV & IRRHard
A project costs €25 000 and returns €8 500, €14 000, €13 000, €10 000 at the end of years 1 to 4. Cash flows can be reinvested at the cost of capital of 8%. Find the modified internal rate of return MIRR in percent.
Drag z so that the shaded area under the standard normal curve, to the right of z, is 0.9279. Find z to two decimals.
A = 0.9279
z =
30.Normal distributionHard
The heights of adult men are normally distributed with mean 178 cm and standard deviation 7 cm. Find the value x below which 90% of them lie (the 90th percentile).
μ = 178σ = 7P = 90%
x = cm
3Solutions
1.Beam support reactions
Answer: MA = 424 kN·m
Cantilever equilibrium: a fixed support can push up and also resist rotation, so it gives a vertical reaction RA and a reaction moment MA. ΣFy = 0 gives RA, and moments about the wall give MA = Σ(load × distance from the wall). A distributed load acts as its resultant at the centroid of the load diagram.
Resultant of the distributed load
W = 12·8 = 96 kN, x̄ = 4 m
Moment about the wall
MA = P·a + W·x̄ = 10·4 + 96·4 = 424 kN·m
Answer
MA = 424 kN·m
2.Beam support reactions
Answer: RA = 17.73 kN
Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Replace each distributed load by its resultant (its area) acting at the centroid of the load diagram, and take moments about a support to remove that support’s reaction from the equation.
Components of P
Pv = 15·sin 45° = 10.61 kN
Ph = 15·cos 45° = 10.61 kN
Reactions
ΣMA = 0: RB·4 = 10.61·1 + 50·3.5 → RB = 46.4 kN
Ay = 10.61 + 50 − 46.4 = 14.2 kN
Ax = Ph = 10.61 kN
Resultant at A
RA = √(10.61² + 14.2²) = 17.73 kN
Answer
RA = 17.73 kN
3.Truss: method of joints
Answer: member CG
Zero-force members: at a joint, the forces must balance in every direction. If a joint has no load and no support, and two of its three members are in line, then the balance across that line involves only the third member, so its force is zero. If only two members meet at an unloaded joint and they are not in line, both are zero.
Joint C
BC and CD lie on one straight line and the joint carries no load. Balancing forces across that line leaves only CG.
ΣF⊥ = 0 → FCG = 0
Check with the method of joints
Solving all joints gives these member forces (T = tension, C = compression).
Zero-force members: at a joint, the forces must balance in every direction. If a joint has no load and no support, and two of its three members are in line, then the balance across that line involves only the third member, so its force is zero. If only two members meet at an unloaded joint and they are not in line, both are zero.
Joint C
BC and CD lie on one straight line and the joint carries no load. Balancing forces across that line leaves only CG.
ΣF⊥ = 0 → FCG = 0
Check with the method of joints
Solving all joints gives these member forces (T = tension, C = compression).
Largest bending moment: M changes slope wherever the shear force changes, so its peaks sit where the shear force crosses zero: under a point load, inside a distributed load, or over a support of an overhang. At a fixed support of a cantilever the moment is largest at the wall. Compare the size of M at those places, sagging or hogging.
Support reactions
Take moments about one support, then use the vertical force balance.
R1 = 62.5 kN, R2 = 37.5 kN
Bending moment at every mark
Sum the moments of all forces on one side of the cut. Sagging is positive, hogging negative.
MA = 0, MB = 57.5, MC = 105 kN·m, MD = 92.5, ME = 70, MF = 37.5, MG = 0
Answer
Mark C: MC = 105 kN·m
6.Shear force & bending moment
Answer: Mmax = 64 kN·m
Method of sections: cut the beam where you want the internal forces and keep one side. The shear force V balances the vertical forces on that side, and the bending moment M balances their moments about the cut. Maximum moment: since dM/dx = V, the bending moment has its peak where the shear force passes through zero, either at a point load or inside a distributed load.
Support reactions
Equilibrium of the whole beam.
UDL resultant: W = w·ℓ = 8·5 = 40 kN, acting at x̄ = 2.5 m
ΣMA = 0: RB·5 = 60·4 + 8·5·2.5
RB = 340/5 = 68 kN
ΣFy = 0: RA = 100 − 68 = 32 kN
Where is V = 0?
V(4⁻) = RA − w·4 = 0 kN
V(4⁺) = 0 − 60 = −60 kN
The shear changes sign at the load, so the maximum is under the load.
Maximum moment
Mmax = RA·4 − w·4²/2 = 32·4 − 8·4²/2 = 64 kN·m
Answer
Mmax = 64 kN·m
It occurs at x = 4 m from A.
7.Beam deflection
Answer: δmax = 2.543 mm
Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).
Consistent units
Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.
w = 10 N/mm, L = 5000 mm
EI = 3.2 × 10¹³ N·mm²
Deflection
δmax = 5wL⁴/(384EI) = 5·10·5000⁴/(384·3.2 × 10¹³) = 2.543 mm
Answer
δmax = 2.543 mm
8.Beam deflection
Answer: Ireq = 57.53 × 10⁶ mm⁴
Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).
Deflection limit
δallow = L/360 = 3000/360 = 8.333 mm
Required second moment of area
I = 5wL⁴/(384·E·δallow) = 5·5·3000⁴/(384·11000·8.333) = 5.753 × 10⁷ mm⁴
Ireq = 57.53 × 10⁶ mm⁴
Answer
Ireq = 57.53 × 10⁶ mm⁴
9.Column buckling
Answer: Pcr = 24.67 kN
Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.
Smallest second moment of area
A rectangle buckles about its weak axis, using the smaller dimension cubed.
Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.
Smallest second moment of area
A round section has the same I about every axis.
I = πd⁴/64 = π·40⁴/64 = 125664 mm⁴
Radius of gyration and slenderness
A = 1257 mm²
r = √(I/A) = √(125664/1257) = 10 mm
KL = 0.7·3000 = 2100 mm
KL/r = 2100/10 = 210
Critical stress
σcr = π²E/(KL/r)² = π²·70000/210² = 15.67 MPa
Answer
σcr = 15.67 MPa
11.Centroid & second moment of area
Answer: Ix = 154.5 × 10⁶ mm⁴
Second moment of area: for a rectangle about its own centroidal axis I = bh³/12, and about its base bh³/3 (parallel-axis theorem I = Ic + A·d²). A hole is handled by subtracting its I, as long as both parts share the same axis. The elastic section modulus is S = I/c, where c is the distance to the extreme fibre.
Outer rectangle minus the two side cut-outs
Both cut-outs together are (B − tw) wide and hw = H − 2tf high, and share the axis x.
Composite areas: split the section into rectangles. The centroid is the area-weighted average ȳ = ΣAᵢyᵢ/ΣAᵢ. The second moment of area about the centroidal axis adds each part’s own bh³/12 and its parallel-axis term A·d², where d is the distance from the part’s centroid to the overall centroid. Bending stress is σ = M·y/I.
Split into two rectangles
Measure every y from the bottom edge.
flange: Af = 200·10 = 2000 mm², yf = 280 + 10/2 = 285 mm
Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).
Total stress
Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.
Water pressure grows with depth below the water table.
u = γw·(z − zw) = 9.81·3 = 29.43 kPa
Effective stress
σ′ = σ − u = 108 − 29.43 = 78.57 kPa
Answer
σ′ = 78.57 kPa
14.Effective stress in soil
Answer: u = 29.43 kPa
Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).
Pore water pressure
Water pressure grows with depth below the water table.
u = γw·(z − zw) = 9.81·3 = 29.43 kPa
Answer
u = 29.43 kPa
15.Consolidation settlement
Answer: S = 9.429 mm
Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.
Preconsolidation pressure
σ′p = OCR·σ′0 = 1.5·55 = 82.5 kPa
Compare with the preconsolidation pressure
σ′f = 55 + 20 = 75 kPa ≤ 82.5 kPa
Settlement
The clay stays on its recompression line.
S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0) = 0.04·3.5/(1 + 1)·log₁₀(75/55) = 9.429 mm
Answer
S = 9.429 mm
16.Consolidation settlement
Answer: t = 1.231 years
Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.
Drainage path
Hdr = H = 2.5 m
Time
t = Tv·Hdr²/cv = 0.197·2.5²/1 = 1.231 years
Answer
t = 1.231 years
17.Hydrostatic force
Answer: F = 39.24 kN
Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.
Centroid depth and area
yc = d + H/2 = 1 + 2/2 = 2 m
A = H·b = 2·1 = 2 m²
Resultant force
F = ρ·g·yc·A = 1000·9.81·2·2 = 39.24 kN
Answer
F = 39.24 kN
18.Hydrostatic force
Answer: F = 56.56 kN
Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.
Centroid depth and area
yc = d + H/2 = 3 + 1.5/2 = 3.75 m
A = H·b = 1.5·1 = 1.5 m²
Resultant force
F = ρ·g·yc·A = 1025·9.81·3.75·1.5 = 56.56 kN
Answer
F = 56.56 kN
19.Pipe friction & head loss
Answer: hf = 1.937 m
Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.
Mean velocity
A = π·0.2²/4 = 0.03142 m²
V = Q/A = 0.025/0.03142 = 0.7958 m/s
Velocity head
V²/(2g) = 0.7958²/(2·9.81) = 0.03228 m
Darcy–Weisbach
hf = f·(L/D)·V²/(2g) = 0.03·(400/0.2)·0.7958²/(2·9.81) = 1.937 m
Answer
hf = 1.937 m
20.Pipe friction & head loss
Answer: Δz = 1.785 m
Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.
Velocity
V = Q/A = 0.075/0.07069 = 1.061 m/s
V²/(2g) = 0.05738 m
Loss coefficients
f·L/D = 0.018·400/0.3 = 24
ΣK = 0.5 + 2·0.3 + 5 + 1.0 = 7.1
Total head loss
hf = 24·0.05738 = 1.377 m
hm = 7.1·0.05738 = 0.4074 m
Δz = hf + hm = 1.785 m
Answer
Δz = 1.785 m
21.Open-channel flow (Manning)
Answer: Q = 2.868 m³/s
Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.
Geometry
A = b·y = 2.5·1.1 = 2.75 m²
P = b + 2y = 2.5 + 2·1.1 = 4.7 m
R = A/P = 0.5851 m
Velocity
V = (1/0.015)·0.58512/3·0.00051/2 = 1.043 m/s
Flow rate
Q = A·V = 2.75·1.043 = 2.868 m³/s
Answer
Q = 2.868 m³/s
22.Open-channel flow (Manning)
Answer: S = 0.003112 m/m
Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.
Hydraulic radius
R = D/4 = 0.45/4 = 0.1125 m
Solve Manning for S
S = (n·V/R2/3)² = (0.013·1/0.233)² = 0.003112
Answer
S = 0.003112
That is a fall of 3.112 m per kilometre.
23.Pumps & pump power
Answer: η = 59.95 %
Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.
Hydraulic power
Ph = ρ·g·Q·H = 1000·9.81·0.015·66 = 9.712 kW
Efficiency
η = Ph/Pshaft = 9.712/16.2 = 59.95%
Answer
η = 59.95%
24.Pumps & pump power
Answer: H = 41.11 m
Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.
Both surfaces are practically at rest, so there is no velocity head term.
H = Δz + p/(ρ·g) + hL = 11 + 15.29 + 14.81 = 41.11 m
Answer
H = 41.11 m
25.Time value of money
Answer: EAR = 16.08 %
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Rate per period
r/m = 0.15/12 = 0.0125
Compound over one year
EAR = (1 + 0.0125)12 − 1 = 1.161 − 1 = 16.08%
Answer
EAR = 16.08%
The EAR is always above the nominal rate when interest compounds more than once a year.
26.Time value of money
Answer: N = 69 payments
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Rearrange the annuity formula
i = 0.004
(1 + i)−N = 1 − 12 000·0.004/200 = 0.76
Solve with logarithms
N = −ln(0.76)/ln(1.004) = 68.75
Round up to whole payments
68 full payments leave a small balance, which the last, smaller payment clears.
N = 69
Answer
N = 69 payments
27.NPV & IRR
Answer: NPV = −77778 €
Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.
Value of the cash flows
PV = 29 000/(0.12 − 0.03) = 322 222.22
NPV
NPV = 322 222.22 − 400 000 = −€77 777.78
Answer
NPV = −€77 777.78
NPV is negative, so the project earns less than the required return.
28.NPV & IRR
Answer: MIRR = 19.56 %
Modified IRR: compound every inflow forward to the end of the project at the reinvestment rate (usually the cost of capital) to get the terminal value TV. MIRR is the rate that turns the initial investment into TV: MIRR = (TV/C₀)^(1/n) − 1.
Terminal value of the inflows
8 500·1.083 = 10 707.55
14 000·1.082 = 16 329.60
13 000·1.081 = 14 040.00
10 000·1.080 = 10 000.00
TV = 51 077.15
MIRR
MIRR = (51 077.15/25 000)1/4 − 1 = 19.56%
Answer
MIRR = 19.56%
29.Normal distribution
Answer: z = −1.46
From an area back to z: Φ(z) is the area to the left of z. For a left-tail area A, find z with Φ(z) = A in the table. A right-tail area A means Φ(z) = 1 − A. A central area A between −z and z leaves (1 − A)/2 in each tail, so Φ(z) = (1 + A)/2. For a value x, use x = μ + zσ.
Area to the left of z
Φ(z) = 1 − 0.9279 = 0.0721
Read the z-table backwards
Find 0.0721 inside the table and read off z.
z = −1.46
Answer
z = −1.46
30.Normal distribution
Answer: x = 187 cm
Normal distribution: convert a value x to a z-score, z = (x − μ)/σ, which counts standard deviations from the mean. A z-table (or Φ(z)) gives the area to the left of z, which is P(X < x). The area to the right is 1 − Φ(z), and the area between two values is the difference of their two areas.
z for the percentile
Φ(z) = 0.9 → z = 1.282
Back to x
x = 178 + 1.282·7 = 186.97 cm
Answer
x = 186.97 cm