FE Civil exam practice: cram pack

Formula sheets, the key method steps for every topic and 30 practice problems, with full solutions at the back.

New problemsBack to the course

In the print window, choose “Save as PDF” to keep a copy on your device.

1Formulas and methods

Beam support reactions

Equilibrium
ΣFx = 0, ΣFy = 0, ΣM = 0
Uniform load
resultant w·L at the middle of the load
Moment
M = F·d

Method

  1. Draw a free-body diagram and replace each support by its reactions.
  2. Replace every distributed load by a single force at its centroid.
  3. Take moments about one support to find the reaction at the other.
  4. Use ΣFy = 0 to find the remaining reaction, and check with a second moment equation.

Truss: method of joints

Method of joints
ΣFx = 0, ΣFy = 0 at each joint
Method of sections
ΣM = 0 about a cut point
Member force
positive = tension, negative = compression

Method

  1. Find the support reactions for the whole truss.
  2. Method of joints: start at a joint with at most two unknown member forces and use ΣFx = 0 and ΣFy = 0.
  3. Method of sections: cut through the member you need and take moments about a point where the other unknown members meet.
  4. Assume tension; a negative answer means compression.

Shear force & bending moment

Shear and moment
V = ΣF on one side, M = ΣF·d on one side
Bending stress
σ = M·y/I
Rectangle
I = bh³/12
Section modulus
W = I/ymax
Simply supported, uniform load
Mmax = wL²/8

Method

  1. Find the support reactions from equilibrium of the whole beam.
  2. Cut the beam at the section you need and keep one side.
  3. Shear force: sum of the vertical forces on that side. Bending moment: sum of their moments about the cut.
  4. For the maximum moment, find where the shear force is zero.

Beam deflection

Point load at midspan
δ = PL³/(48EI)
Uniform load, simply supported
δ = 5wL⁴/(384EI)
Cantilever, end load
δ = PL³/(3EI)
Cantilever, uniform load
δ = wL⁴/(8EI)
Superposition
δ = δ1 + δ2

Column buckling

Euler load
Pcr = π²EI/(KL)²
Effective length factor
K = 1 pinned–pinned, 0.5 fixed–fixed, 0.7 fixed–pinned, 2 fixed–free
Critical stress
σcr = Pcr/A
Slenderness
λ = KL/r, r = √(I/A)

Centroid & second moment of area

Centroid
ȳ = ΣAiyi/ΣAi
Rectangle
I = bh³/12
Parallel-axis theorem
I = Ic + A·d²
Composite section
I = Σ(Ic,i + Aidi²)

Effective stress in soil

Total stress
σ = Σγi·hi
Pore water pressure
u = γw·(z − zw)
Effective stress
σ′ = σ − u
Water
γw = 9.81 kN/m³

Consolidation settlement

Normally consolidated
S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0)
Final stress
σ′f = σ′0 + Δσ (at mid-depth of the layer)
Overconsolidated, σ′f ≤ σ′p
S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0)
Overconsolidated, σ′f > σ′p
S = H/(1 + e0)·[Cr·log₁₀(σ′p/σ′0) + Cc·log₁₀(σ′f/σ′p)]
Overconsolidation ratio
OCR = σ′p/σ′0
Time for consolidation
t = Tv·Hdr²/cv
Drainage path
Hdr = H/2 (double drainage), H (single drainage)
Time factors
U 50% → 0.197, 60% → 0.287, 70% → 0.403, 80% → 0.567, 90% → 0.848

Hydrostatic force

Pressure at depth
p = ρgh
Force on a vertical wall
F = ρg·hc·A
Centre of pressure
yp = yc + Ic/(ycA)
Rectangle
Ic = bH³/12

Pipe friction & head loss

Reynolds number
Re = V·D/ν = ρ·V·D/μ
Flow regime
laminar below Re ≈ 2000, turbulent above Re ≈ 4000
Mean velocity
V = Q/A, A = π·D²/4
Darcy–Weisbach
hf = f·(L/D)·V²/(2g)
Minor losses
hm = ΣK·V²/(2g)
Typical K values
entrance 0.5, exit 1.0, 90° bend ≈ 0.3
Pressure drop
Δp = ρ·g·hf
Two open reservoirs
Δz = (f·L/D + ΣK)·V²/(2g)
Free outlet
H = (1 + f·L/D + ΣK)·V²/(2g)

Open-channel flow (Manning)

Manning equation
V = (1/n)·R2/3·S1/2
Flow rate
Q = A·V
Hydraulic radius
R = A/P (P = wetted perimeter, free surface excluded)
Rectangle
A = b·y, P = b + 2y
Trapezoid (side slope z:1)
A = (b + z·y)·y, P = b + 2y·√(1 + z²)
Circular pipe, full or half full
R = D/4
Required slope
S = (n·Q/(A·R2/3))²

Pumps & pump power

Hydraulic power
Ph = ρ·g·Q·H = Q·Δp
Shaft power
Pshaft = Ph/ηpump
Electrical power
Pel = Pshaft/ηmotor
Pump head
H = Δz + Δp/(ρ·g) + hL
System losses
hL = (f·L/D + ΣK)·V²/(2g)

Time value of money

Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i

Method

  1. Draw a timeline with every cash flow and its timing.
  2. Match the rate to the period: a monthly rate for monthly payments.
  3. Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
  4. Check the sign and the order of magnitude of the answer.

NPV & IRR

Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)

Method

  1. List all cash flows with their year; the investment at year 0 is negative.
  2. Discount each cash flow: CFt/(1 + r)t.
  3. Add them up to get the NPV. Positive means the project earns more than r.
  4. For the IRR, find the rate that makes NPV zero by trial or interpolation.

Normal distribution

z-score
z = (x − μ)/σ
Below x
P(X < x) = Φ(z)
Above x
P(X > x) = 1 − Φ(z)
Between
Φ(z2) − Φ(z1)
Percentile
x = μ + z·σ

Method

  1. Convert the value to a z-score: z = (x − μ)/σ.
  2. Look up Φ(z), the area to the left of z.
  3. For the area to the right use 1 − Φ(z); for an interval subtract the two left areas.
  4. For a percentile, work backwards: find z for the area, then x = μ + z·σ.

2Practice problems

1.Beam support reactionsMedium
P1​ = 20 kNP2​ = 45 kNABRA​ = ?RB​3 m4 m1 m

The simply supported beam has a pin at A and a roller at B. Find the vertical support reaction RA.

L = 8 mP1 = 20 kN at 3 mP2 = 45 kN at 7 m
RA = kN
2.Beam support reactionsHard
w = 12 kN/mP = 60 kNABRA​RB​ = ?2 m1 m4 m1 m

The simply supported beam has a pin at A and a roller at B. Find the vertical support reaction RB.

L = 8 mP = 60 kN at 7 mw = 12 kN/m from 2 to 3 m
RB = kN
3.Truss: method of jointsMedium
ABBCACACB40 kN5 m3 m3 m

Use the method of joints to find the force FAC in member AC. Give tension as positive and compression as negative.

span = 5 mheight = 3 mB is 3 m from Avertical load = 40 kN
FAC = kN
4.Truss: method of jointsHard
ABBCACACB25 kN10 kN6 m5 m4 m

Use the method of joints to find the force FAC in member AC. Give tension as positive and compression as negative.

span = 6 mheight = 4 mB is 5 m from Avertical load = 25 kNhorizontal load = 10 kN ←
FAC = kN
5.Shear force & bending momentMedium
M0​ = 30 kN·mAB4 m6 m

The simply supported beam carries a clockwise couple M0 = 30 kN·m at x = 4 m from A, and no other load. Find the bending moment Mx just to the left of the couple. Use sagging moments positive and upward shear on the left face positive.

L = 10 mM0 = 30 kN·m clockwise, at 4 m
Mx = kN·m
6.Shear force & bending momentHard
8 kN/m40 kN55 kNABCDEFG1 m1 m1 m1 m1 m1 m

The marks A to G split the beam into six equal parts. At which mark is the bending moment largest in size, sagging or hogging? Click it in the diagram.

40 kN @ 6 m55 kN @ 3 m8 kN/m, 0–4 m
  1. 1A (x = 0 m)
  2. 2B (x = 1 m)
  3. 3C (x = 2 m)
  4. 4D (x = 3 m)
  5. 5E (x = 4 m)
  6. 6F (x = 5 m)
  7. 7G (x = 6 m)
7.Beam deflectionMedium
w = 2 kN/mδL = 6 m

A simply supported beam carries a uniformly distributed load w over its whole span. Find the maximum deflection δmax, at midspan.

w = 2 kN/mL = 6 mE = 70 GPa (aluminium)I = 160 × 10⁶ mm⁴
δmax = mm
8.Beam deflectionHard
P = 21 kNABδ2.5 m1.5 m

A simply supported beam carries a point load P at b = 1.5 m from support B. Find the maximum deflection δmax of the beam.

P = 21 kNb = 1.5 mL = 4 mE = 70 GPa (aluminium)I = 57 × 10⁶ mm⁴
δmax = mm
9.Column bucklingMedium
PL = 6 md = 80 mmcross-section

A column of length L made of steel is pinned at both ends. Using Euler’s formula, find its critical buckling load Pcr.

L = 6 mE = 200 GPa (steel)d = 80 mm
Pcr = kN
10.Column bucklingHard
P = 60 kNL = 2.5 md = ?cross-section

A solid round column of length L made of steel is pinned at both ends. It must carry 60 kN with a factor of safety of 2 against buckling. Find the smallest diameter d.

P = 60 kNn = 2L = 2.5 mE = 200 GPa (steel)
d = mm
11.Centroid & second moment of areaMedium
1002516016xdimensions in mm

Find the second moment of area Ix of the T-section about the horizontal axis x through its centroid.

bf = 100 mmtf = 25 mmtw = 16 mmhw = 160 mm
Ix = × 10⁶ mm⁴
12.Centroid & second moment of areaHard
120 mm240 mm144 mm50 × 50xIx​ = ?

A 120 mm × 240 mm plate has a rectangular cut-out 50 mm wide and 50 mm high, centred on the vertical centre line with its centre 144 mm above the bottom. Find the second moment of area Ix about the horizontal axis through the centroid.

b = 120 mmh = 240 mmcut-out: 50 × 50 mmhole centre: y = 144 mm
Ix = × 10⁶ mm⁴
13.Effective stress in soilMedium
sandγd​ = 17 kN/m³γsat​ = 19.5 kN/m³8 mwater tableXz = 6 m

For the soil profile shown, find the total vertical stress σ at point X.

z = 6 mzw = 4 mγw = 9.81 kN/m³sand: γd = 17 kN/m³sand: γsat = 19.5 kN/m³
σ = kPa
14.Effective stress in soilHard
sandγd​ = 15 kN/m³γsat​ = 18.5 kN/m³3 mclayγsat​ = 17 kN/m³4 mwater tableXz = 5 m

For the soil profile shown, find the vertical effective stress σ′ at point X.

z = 5 mzw = 1 mγw = 9.81 kN/m³sand: γd = 15 kN/m³sand: γsat = 18.5 kN/m³clay: γsat = 17 kN/m³
σ′ = kPa
15.Consolidation settlementMedium
Δσ = 20 kPasandclayCc​ = 0.2, Cr​ = 0.03e0​ = 0.6σ′0​ = 50 kPaσ′p​ = 130 kPa4 mwater table

A 4 m thick overconsolidated clay layer has Cc = 0.2, Cr = 0.03 and e₀ = 0.6. At its mid-depth the effective vertical stress is 50 kPa and the preconsolidation pressure is 130 kPa. A new building adds 20 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.

H = 4 mCc = 0.2Cr = 0.03e0 = 0.6σ′0 = 50 kPaσ′p = 130 kPaΔσ = 20 kPa
S = mm
16.Consolidation settlementHard
sandclayH = 9.5 mcv​ = 1.2 m²/year9.5 mimpervious rockwater table

A clay layer 9.5 m thick has a coefficient of consolidation cv = 1.2 m²/year. It lies on impervious rock, with sand above it, so water drains out only at the top. For 60% average consolidation the time factor is Tv = 0.287. How many years t does the layer take to reach 60% consolidation?

H = 9.5 mcv = 1.2 m²/yearU = 60%Tv = 0.287single drainage
t = years
17.Hydrostatic forceMedium
gated = 3 mH = 3 m

A vertical rectangular gate 2 m wide sits in the wall of a tank of water, with its top edge 3 m below the surface. Find the resultant hydrostatic force F on the gate.

d = 3 mH = 3 mb = 2 mρ = 1000 kg/m³g = 9.81 m/s²
F = kN
18.Hydrostatic forceHard
gated = 2.5 mH = 1.5 m

A vertical rectangular gate 1.5 m wide sits in the wall of a tank of glycerin, with its top edge 2.5 m below the surface. Find the depth ycp of the centre of pressure below the surface.

d = 2.5 mH = 1.5 mb = 1.5 mρ = 1260 kg/m³g = 9.81 m/s²
ycp = m
19.Pipe friction & head lossMedium
V = 1.1 m/sD = 200 mmL = 300 mf = 0.015

Water flows at a mean velocity of 1.1 m/s through a pipe 300 m long with an inside diameter of 200 mm. Use the Darcy friction factor f = 0.015 and g = 9.81 m/s². Find the friction head loss hf.

V = 1.1 m/sL = 300 mD = 200 mmf = 0.015g = 9.81 m/s²
hf = m
20.Pipe friction & head lossHard
K = 5free outletH = ?L = 400 m, D = 300 mm, f = 0.0182× bend (K = 0.3)

A pipe 400 m long with an inside diameter of 300 mm (Darcy friction factor f = 0.018) runs from an open reservoir and discharges as a free jet into the air. The minor losses are a square-edged entrance (K = 0.5), 2 bends (K = 0.3 each) and a valve (K = 5). Use g = 9.81 m/s². How far H must the reservoir surface be above the pipe outlet for a flow rate of 75 L/s?

Q = 75 L/sL = 400 mD = 300 mmf = 0.018Kentrance = 0.5Kbend = 0.3 (×2)Kvalve = 5
H = m
21.Open-channel flow (Manning)Medium
b = 3 my = 1.2 m1.5 : 1n = 0.014, S = 0.003

A trapezoidal unfinished concrete channel has a bottom width of 3 m and side slopes of 1.5:1 (horizontal:vertical). Water flows uniformly 1.2 m deep. Manning n = 0.014 and the bed slope is S = 0.003. Find the flow rate Q in m³/s.

b = 3 my = 1.2 mz = 1.5n = 0.014S = 0.003
Q = m³/s
22.Open-channel flow (Manning)Hard
b = 2.5 my = 2.2 m1 : 1n = 0.025, Q = 25 m³/s

A trapezoidal gravel channel with a bottom width of 2.5 m and side slopes of 1:1 (horizontal:vertical) must carry 25 m³/s in uniform flow at a depth of 2.2 m. Manning n = 0.025. Find the required bed slope S (in m/m).

Q = 25 m³/sb = 2.5 my = 2.2 mz = 1n = 0.025
S = m/m
23.Pumps & pump powerMedium
PQ = 15 L/sH = 72 m

In a test, a pump delivers 15 L/s of water (ρ = 1000 kg/m³) against a head of 72 m while its shaft takes 12.9 kW. Use g = 9.81 m/s². Find the pump efficiency η in percent.

Q = 15 L/sH = 72 mPshaft = 12.9 kWg = 9.81 m/s²
η = %
24.Pumps & pump powerHard
PQ = 80 L/sΔz = 19 mL = 600 m, D = 200 mm, f = 0.018, ΣK = 6

A pump moves 80 L/s of water (ρ = 1000 kg/m³) from an open lower reservoir to an upper tank whose water surface is 19 m higher. The pipe is 600 m long with an inside diameter of 200 mm and a Darcy friction factor f = 0.018; the minor-loss coefficients add up to ΣK = 6 (entrance and exit included). Use g = 9.81 m/s². Find the head H the pump must add.

Q = 80 L/sΔz = 19 mL = 600 mD = 200 mmf = 0.018ΣK = 6
H = m
25.Time value of moneyMedium
years012PV = ?€10 000

You need €10 000 in 2 years. An account pays 3.6% per year, compounded monthly. How much must you deposit today? Find the present value PV.

FV = €10 0003.6% / 12n = 2
PV = €
26.Time value of moneyHard
months0123…300€150 000A?AAA

A loan of €150 000 is repaid with equal monthly payments over 25 years. The interest rate is 4.2% per year, compounded monthly. Find the monthly payment A.

P = €150 0004.2% / 12N = 300
A = €
27.NPV & IRRMedium
years0123−45 00022 00017 00011 000

An investment of €45 000 gives these cash flows at the end of years 1 to 3: €22 000, €17 000, €11 000. The cost of capital is 7.000000000000001%. Find the net present value NPV.

r = 7.000000000000001%CF0 = −45 000CF1 = 22 000CF2 = 17 000CF3 = 11 000
NPV = €
28.NPV & IRRHard
r (%)NPVABr* = ?0

Project A costs €20 000 and returns €11 000, €8 000, €4 500 at the end of years 1 to 3. Project B costs €22 000 and returns €5 500, €8 500, €12 000. Find the crossover rate r* at which both projects have the same NPV, in percent.

A: −20 000, 11 000, 8 000, 4 500B: −22 000, 5 500, 8 500, 12 000
r* = %
29.Normal distributionMedium
300 kg303.5 kgT = X₁ + … + X₁₂?

The masses of bags of cement are independent and normal with mean 25 kg and standard deviation 0.5 kg. Find the probability P that the total mass of 12 of them exceeds 303.5 kg. Round z to two decimals.

μ = 25 kgσ = 0.5 kgn = 12> 303.5 kg
P =
30.Normal distributionHard
0.04 mm0D − d?

Hole diameters D are normal with mean 25.04 mm and standard deviation 0.01 mm. Shaft diameters d are independent and normal with mean 25 mm and standard deviation 0.015 mm. A randomly chosen shaft fits when D − d > 0. Find the probability P that it fits. Round z to two decimals.

hole: μ = 25.04 mm, σ = 0.01 mmshaft: μ = 25 mm, σ = 0.015 mm
P =

3Solutions

1.Beam support reactions

Answer: RA = 18.13 kN

Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Taking moments about one support removes that support’s reaction from the equation.

P1​ = 20 kNP2​ = 45 kNABRA​RB​3 m4 m1 m

Free-body diagram

Replace the supports with reaction forces. A roller gives one vertical reaction; with only vertical loads the pin gives one vertical reaction too.

Equilibrium

Moments about A, counter-clockwise positive. Then vertical force balance.

ΣMA = 0: RB·8 = 20·3 + 45·7
RB = 375/8 = 46.88 kN
ΣFy = 0: RA = 65 − 46.88 = 18.13 kN

Answer

RA = 18.13 kN
2.Beam support reactions

Answer: RB = 56.25 kN

Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Taking moments about one support removes that support’s reaction from the equation.

w = 12 kN/mP = 60 kNABRA​RB​2 m1 m4 m1 m

Free-body diagram

Replace the supports with reaction forces. A roller gives one vertical reaction; with only vertical loads the pin gives one vertical reaction too.

Equilibrium

Moments about A, counter-clockwise positive. Then vertical force balance.

UDL resultant: W = w·ℓ = 12·1 = 12 kN, acting at x̄ = 2.5 m
ΣMA = 0: RB·8 = 60·7 + 12·1·2.5
RB = 450/8 = 56.25 kN
ΣFy = 0: RA = 72 − 56.25 = 15.75 kN

Answer

RB = 56.25 kN
3.Truss: method of joints

Answer: FAC = 16 kN

Method of joints: every pin of a truss is in equilibrium, so ΣFx = 0 and ΣFy = 0 at each joint. Start at a joint with at most two unknown member forces. A negative result means the member is in compression.

ABBCACACB40 kNAy​Cy​

Support reactions

Equilibrium of the whole truss. Moments about A, counter-clockwise positive.

ΣMA = 0: Cy·5 = 40·3 → Cy = 24 kN
ΣFy = 0: Ay = 40 − 24 = 16 kN

Joint C

The roller gives only a vertical reaction, so joint C has just two unknown member forces. Assume both in tension.

sin γ = 3/3.606 = 0.8321, cos γ = 2/3.606 = 0.5547
ΣFy = 0: Cy + FBC·sin γ = 0 → FBC = −24/0.8321 = −28.84 kN
ΣFx = 0: −FAC − FBC·cos γ = 0 → FAC = −(−28.84)·0.5547 = 16 kN

Answer

FAC = 16 kN (tension)
4.Truss: method of joints

Answer: FAC = 3.542 kN

Method of joints: every pin of a truss is in equilibrium, so ΣFx = 0 and ΣFy = 0 at each joint. Start at a joint with at most two unknown member forces. A negative result means the member is in compression.

ABBCACACB25 kN10 kNAy​Cy​Ax​

Support reactions

Equilibrium of the whole truss. Moments about A, counter-clockwise positive.

ΣMA = 0: Cy·6 = 25·5 − 10·4 → Cy = 14.17 kN
ΣFy = 0: Ay = 25 − 14.17 = 10.83 kN
ΣFx = 0: Ax = 10 kN

Joint C

The roller gives only a vertical reaction, so joint C has just two unknown member forces. Assume both in tension.

sin γ = 4/4.123 = 0.9701, cos γ = 1/4.123 = 0.2425
ΣFy = 0: Cy + FBC·sin γ = 0 → FBC = −14.17/0.9701 = −14.6 kN
ΣFx = 0: −FAC − FBC·cos γ = 0 → FAC = −(−14.6)·0.2425 = 3.542 kN

Answer

FAC = 3.542 kN (tension)
5.Shear force & bending moment

Answer: Mx = −12 kN·m

Method of sections: cut the beam where you want the internal forces and keep one side. The shear force V balances the vertical forces on that side, and the bending moment M balances their moments about the cut. An applied couple makes the bending moment diagram jump by the size of the couple.

Support reactions

Moments about A, counter-clockwise positive: RB·L − M0 = 0. Vertical balance: RA + RB = 0.

RB = M0/L = 30/10 = 3 kN (upward)
RA = −RB = −3 kN (downward)

Cut just left of the couple

The left part contains only RA.

Mx = RA·a = −3·4 = −12 kN·m

Answer

Mx = −12 kN·m
6.Shear force & bending moment

Answer: E (x = 4 m)

Largest bending moment: M changes slope wherever the shear force changes, so its peaks sit where the shear force crosses zero: under a point load, inside a distributed load, or over a support of an overhang. At a fixed support of a cantilever the moment is largest at the wall. Compare the size of M at those places, sagging or hogging.

Support reactions

Take moments about one support, then use the vertical force balance.

R1 = 9.75 kN, R2 = 117.3 kN

Bending moment at every mark

Sum the moments of all forces on one side of the cut. Sagging is positive, hogging negative.

MA = 0, MB = 5.75, MC = 3.5, MD = −6.75, ME = −80 kN·m, MF = −40, MG = 0

Answer

Mark E: ME = −80 kN·m
7.Beam deflection

Answer: δmax = 3.013 mm

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).

Consistent units

Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.

w = 2 N/mm, L = 6000 mm
EI = 1.12 × 10¹³ N·mm²

Deflection

δmax = 5wL⁴/(384EI) = 5·2·6000⁴/(384·1.12 × 10¹³) = 3.013 mm

Answer

δmax = 3.013 mm
8.Beam deflection

Answer: δmax = 6.455 mm

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).

Consistent units

Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.

P = 21000 N, b = 1500 mm, L = 4000 mm
EI = 3.99 × 10¹² N·mm²

Position of the maximum

Setting the slope in the longer segment to zero gives the position.

x = √((L² − b²)/3) = √((4000² − 1500²)/3) = 2141 mm

Maximum deflection

δmax = Pb(L² − b²)3/2/(9√3·EIL) = 6.455 mm

Answer

δmax = 6.455 mm
9.Column buckling

Answer: Pcr = 110.2 kN

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Smallest second moment of area

A round section has the same I about every axis.

I = πd⁴/64 = π·80⁴/64 = 2.011 × 10⁶ mm⁴

Effective length

KL = 1·6000 = 6000 mm

Critical load

Pcr = π²EI/(KL)² = π²·200000·2.011 × 10⁶/6000² = 110245 N = 110.2 kN

Answer

Pcr = 110.2 kN
10.Column buckling

Answer: d = 52.75 mm

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Required critical load

Pcr = n·P = 2·60000 = 120000 N
KL = 1·2500 = 2500 mm

Solve for the diameter

d = (64·n·P·(KL)²/(π³E))^(1/4) = (64·120000·2500²/(π³·200000))^(1/4) = 52.75 mm

Answer

d = 52.75 mm

Check: the slenderness KL/r is 189.6, so the column is slender and Euler applies.

11.Centroid & second moment of area

Answer: Ix = 16.41 × 10⁶ mm⁴

Composite areas: split the section into rectangles. The centroid is the area-weighted average ȳ = ΣAᵢyᵢ/ΣAᵢ. The second moment of area about the centroidal axis adds each part’s own bh³/12 and its parallel-axis term A·d², where d is the distance from the part’s centroid to the overall centroid. Bending stress is σ = M·y/I.

Split into two rectangles

Measure every y from the bottom edge.

flange: Af = 100·25 = 2500 mm², yf = 160 + 25/2 = 172.5 mm
web: Aw = 16·160 = 2560 mm², yw = 160/2 = 80 mm

Centroid

ȳ = (Afyf + Awyw)/(Af + Aw) = (2500·172.5 + 2560·80)/5060 = 125.7 mm

Parallel-axis theorem

flange: 100·25³/12 + 2500·(172.5 − 125.7)² = 5.605 × 10⁶ mm⁴
web: 16·160³/12 + 2560·(80 − 125.7)² = 1.081 × 10⁷ mm⁴
Ix = 5.605 × 10⁶ + 1.081 × 10⁷ = 1.641 × 10⁷ mm⁴ = 16.41 × 10⁶ mm⁴

Answer

Ix = 16.41 × 10⁶ mm⁴
12.Centroid & second moment of area

Answer: Ix = 136.1 × 10⁶ mm⁴

Sections with holes: treat a hole as a negative area. The centroid is ȳ = (A₁y₁ − A₂y₂)/(A₁ − A₂), with A₁, y₁ for the full plate and A₂, y₂ for the hole. For the second moment of area about the centroidal axis, use the parallel-axis theorem for each part and subtract the hole: I = (Ic1 + A₁d₁²) − (Ic2 + A₂d₂²), where d is the distance from each part's own centroid to the axis through ȳ. A rectangle has Ic = bh³/12 and a circle Ic = πd⁴/64.

Centroid

ȳ = (28800·120 − 2500·144)/(28800 − 2500) = 117.7 mm

Full plate about ȳ

120·240³/12 + 28800·2.281² = 138.4 × 10⁶ mm⁴

Hole about ȳ

50·50³/12 + 2500·26.28² = 2.248 × 10⁶ mm⁴

Subtract

Ix = 136.1 × 10⁶ mm⁴

Answer

Ix = 136.1 × 10⁶ mm⁴
13.Effective stress in soil

Answer: σ = 107 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Total stress

Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.

σ = γd·zw + γsat·(z − zw) = 17·4 + 19.5·2 = 107 kPa

Answer

σ = 107 kPa
14.Effective stress in soil

Answer: σ′ = 46.76 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Total stress

Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.

σ = γd·1 + γsat,sand·2 + γsat,clay·2
σ = 15·1 + 18.5·2 + 17·2 = 86 kPa

Pore water pressure

Water pressure grows with depth below the water table.

u = γw·(z − zw) = 9.81·4 = 39.24 kPa

Effective stress

σ′ = σ − u = 86 − 39.24 = 46.76 kPa

Answer

σ′ = 46.76 kPa
15.Consolidation settlement

Answer: S = 10.96 mm

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Compare with the preconsolidation pressure

σ′f = 50 + 20 = 70 kPa ≤ 130 kPa

Settlement

The clay stays on its recompression line.

S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0) = 0.03·4/(1 + 0.6)·log₁₀(70/50) = 10.96 mm

Answer

S = 10.96 mm
16.Consolidation settlement

Answer: t = 21.58 years

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Drainage path

Hdr = H = 9.5 m

Time

t = Tv·Hdr²/cv = 0.287·9.5²/1.2 = 21.58 years

Answer

t = 21.58 years
17.Hydrostatic force

Answer: F = 264.9 kN

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 3 + 3/2 = 4.5 m
A = H·b = 3·2 = 6 m²
gated = 3 mH = 3 mF

Resultant force

F = ρ·g·yc·A = 1000·9.81·4.5·6 = 264.9 kN

Answer

F = 264.9 kN
18.Hydrostatic force

Answer: ycp = 3.308 m

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 2.5 + 1.5/2 = 3.25 m
A = H·b = 1.5·1.5 = 2.25 m²
gated = 2.5 mH = 1.5 mF

Resultant force

F = ρ·g·yc·A = 1260·9.81·3.25·2.25 = 90.39 kN

Centre of pressure

Pressure grows with depth, so the resultant acts below the centroid.

Ic = b·H³/12 = 1.5·1.5³/12 = 0.4219 m⁴
ycp = yc + Ic/(yc·A) = 3.25 + 0.4219/(3.25·2.25) = 3.308 m

Answer

ycp = 3.308 m
19.Pipe friction & head loss

Answer: hf = 1.388 m

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Velocity head

V²/(2g) = 1.1²/(2·9.81) = 0.06167 m

Darcy–Weisbach

hf = f·(L/D)·V²/(2g) = 0.015·(300/0.2)·1.1²/(2·9.81) = 1.388 m

Answer

hf = 1.388 m
20.Pipe friction & head loss

Answer: H = 1.785 m

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Velocity

V = Q/A = 0.075/0.07069 = 1.061 m/s
V²/(2g) = 0.05738 m

Loss coefficients

f·L/D = 0.018·400/0.3 = 24
ΣK = 0.5 + 2·0.3 + 5 = 6.1

Energy equation

The outlet jet still carries its velocity head; it is not a loss but it has to be supplied.

H = (1 + 24 + 6.1)·0.05738 = 1.785 m

Answer

H = 1.785 m
21.Open-channel flow (Manning)

Answer: Q = 19.2 m³/s

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Geometry

A = (b + z·y)·y = (3 + 1.5·1.2)·1.2 = 5.76 m²
P = b + 2y·√(1 + z²) = 3 + 2·1.2·√(1 + 1.5²) = 7.327 m
R = A/P = 0.7862 m

Velocity

V = (1/0.014)·0.78622/3·0.0031/2 = 3.333 m/s

Flow rate

Q = A·V = 5.76·3.333 = 19.2 m³/s

Answer

Q = 19.2 m³/s
22.Open-channel flow (Manning)

Answer: S = 0.002912 m/m

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Geometry

A = (b + z·y)·y = (2.5 + 1·2.2)·2.2 = 10.34 m²
P = b + 2y·√(1 + z²) = 2.5 + 2·2.2·√(1 + 1²) = 8.723 m
R = A/P = 1.185 m

Solve Manning for S

S1/2 = n·Q/(A·R2/3) = 0.025·25/(10.34·1.12) = 0.05396
S = 0.05396² = 0.002912

Answer

S = 0.002912

That is a fall of 2.912 m per kilometre.

23.Pumps & pump power

Answer: η = 82.13 %

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Hydraulic power

Ph = ρ·g·Q·H = 1000·9.81·0.015·72 = 10.59 kW

Efficiency

η = Ph/Pshaft = 10.59/12.9 = 82.13%

Answer

η = 82.13%
24.Pumps & pump power

Answer: H = 38.83 m

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Velocity

V = Q/A = 0.08/0.03142 = 2.546 m/s
V²/(2g) = 0.3305 m

Head losses

hL = (f·L/D + ΣK)·V²/(2g) = (54 + 6)·0.3305 = 19.83 m

Pump head

Both surfaces are open and practically at rest, so pressure and velocity terms drop out.

H = Δz + hL = 19 + 19.83 = 38.83 m

Answer

H = 38.83 m
25.Time value of money

Answer: PV = 9306 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Rate and number of periods

i = 0.036000000000000004/12 = 0.003
N = 12·2 = 24

Present value

PV = FV/(1 + i)N = 10 000/1.075 = €9 306.31

Answer

PV = €9 306.31
26.Time value of money

Answer: A = 808.4 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Monthly rate and number of payments

i = 0.042/12 = 0.0035
N = 12·25 = 300

Payment

The present value of N equal payments A is A·(1 − (1 + i)⁻ᴺ)/i. Set it equal to the loan and solve for A.

(1 + i)−N = 0.3506
A = 150 000·0.0035/(1 − 0.3506) = €808.41

Answer

A = €808.41
27.NPV & IRR

Answer: NPV = −611.5 €

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Present value of each cash flow

CF0 = −45 000
CF1/(1 + 0.07)1 = 22 000/1.07 = 20 560.75
CF2/(1 + 0.07)2 = 17 000/1.145 = 14 848.46
CF3/(1 + 0.07)3 = 11 000/1.225 = 8 979.28

Add them up

NPV = €−611.52

Answer

NPV = €−611.52

NPV is negative, so the project earns less than the required return.

28.NPV & IRR

Answer: r* = 2.969 %

Crossover rate: the discount rate at which two projects have the same NPV. It is the IRR of the difference in their cash flows (B − A). Below it the project with the later, larger cash flows has the higher NPV; above it the other one wins.

Difference in cash flows

ΔCF0 = −22 000 − (−20 000) = −2 000
ΔCF1 = 5 500 − 11 000 = −5 500
ΔCF2 = 8 500 − 8 000 = 500
ΔCF3 = 12 000 − 4 500 = 7 500

IRR of the difference

NPVΔ(2%) = 155.85
NPVΔ(3%) = −4.95
r* = 2.969%

Answer

r* = 2.969%

Check: at 2.969% both NPVs are €2 350.15.

29.Normal distribution

Answer: P = 0.02169

Sums and differences of normal variables: if X and Y are independent and normal, X + Y and X − Y are normal too. Means add or subtract: E(X ± Y) = μX ± μY. Variances always add, also for a difference: Var(X ± Y) = σX² + σY², so σ = √(σX² + σY²). Standard deviations never add directly. The total of n independent items with the same distribution has mean n·μ and standard deviation σ·√n. Then standardise as usual: z = (x − mean)/σ and read Φ(z).

Distribution of the total

μT = 300 kg, σT = 0.5·√12 = 1.732 kg

Standardise

z = (303.5 − 300)/1.732 = 2.02

Probability

P = 1 − Φ(2.02) = 0.02169

Answer

P = 0.02169
30.Normal distribution

Answer: P = 0.9868

Sums and differences of normal variables: if X and Y are independent and normal, X + Y and X − Y are normal too. Means add or subtract: E(X ± Y) = μX ± μY. Variances always add, also for a difference: Var(X ± Y) = σX² + σY², so σ = √(σX² + σY²). Standard deviations never add directly. The total of n independent items with the same distribution has mean n·μ and standard deviation σ·√n. Then standardise as usual: z = (x − mean)/σ and read Φ(z).

Distribution of the difference

μ = 25.04 − 25 = 0.04 mm, σ = 0.01803 mm

Standardise

z = (0 − 0.04)/0.01803 = −2.22

Probability

P = 1 − Φ(−2.22) = 0.9868

Answer

P = 0.9868

This is independent practice material. ExamProblems is not affiliated with or endorsed by the organisation that runs this exam, and the exam name is used only to describe the content. The FE exam is run by NCEES, which is not affiliated with ExamProblems and does not endorse it.