laminar below Re ≈ 2000, turbulent above Re ≈ 4000
Mean velocity
V = Q/A, A = π·D²/4
Darcy–Weisbach
hf = f·(L/D)·V²/(2g)
Minor losses
hm = ΣK·V²/(2g)
Typical K values
entrance 0.5, exit 1.0, 90° bend ≈ 0.3
Pressure drop
Δp = ρ·g·hf
Two open reservoirs
Δz = (f·L/D + ΣK)·V²/(2g)
Free outlet
H = (1 + f·L/D + ΣK)·V²/(2g)
Open-channel flow (Manning)
Manning equation
V = (1/n)·R2/3·S1/2
Flow rate
Q = A·V
Hydraulic radius
R = A/P (P = wetted perimeter, free surface excluded)
Rectangle
A = b·y, P = b + 2y
Trapezoid (side slope z:1)
A = (b + z·y)·y, P = b + 2y·√(1 + z²)
Circular pipe, full or half full
R = D/4
Required slope
S = (n·Q/(A·R2/3))²
Pumps & pump power
Hydraulic power
Ph = ρ·g·Q·H = Q·Δp
Shaft power
Pshaft = Ph/ηpump
Electrical power
Pel = Pshaft/ηmotor
Pump head
H = Δz + Δp/(ρ·g) + hL
System losses
hL = (f·L/D + ΣK)·V²/(2g)
Time value of money
Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i
Method
Draw a timeline with every cash flow and its timing.
Match the rate to the period: a monthly rate for monthly payments.
Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
Check the sign and the order of magnitude of the answer.
NPV & IRR
Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)
Method
List all cash flows with their year; the investment at year 0 is negative.
Discount each cash flow: CFt/(1 + r)t.
Add them up to get the NPV. Positive means the project earns more than r.
For the IRR, find the rate that makes NPV zero by trial or interpolation.
Normal distribution
z-score
z = (x − μ)/σ
Below x
P(X < x) = Φ(z)
Above x
P(X > x) = 1 − Φ(z)
Between
Φ(z2) − Φ(z1)
Percentile
x = μ + z·σ
Method
Convert the value to a z-score: z = (x − μ)/σ.
Look up Φ(z), the area to the left of z.
For the area to the right use 1 − Φ(z); for an interval subtract the two left areas.
For a percentile, work backwards: find z for the area, then x = μ + z·σ.
2Practice problems
1.Beam support reactionsMedium
The beam has a pin at A and a roller at B, 6 m from A, and overhangs B to the free end C. Find the vertical reaction RB, taking upward as positive.
AB = 6 mAC = 8 mP1 = 80 kN at 1 mP2 = 65 kN at 8 m
RB = kN
2.Beam support reactionsHard
The simply supported beam has a pin at A and a roller at B. Find the vertical support reaction RB.
L = 8 mP = 40 kN at 2 mw = 6 kN/m from 5 to 8 m
RB = kN
3.Truss: method of jointsMedium
Use the method of joints to find the force FAC in member AC. Give tension as positive and compression as negative.
span = 6 mheight = 3 mB is 4 m from Avertical load = 10 kN
FAC = kN
4.Truss: method of jointsHard
Use the method of joints to find the force FBC in member BC. Give tension as positive and compression as negative.
span = 5 mheight = 2 mB is 2 m from Avertical load = 45 kNhorizontal load = 15 kN →
FBC = kN
5.Shear force & bending momentMedium
The marks A to G split the beam into six equal parts. At which mark is the bending moment largest in size, sagging or hogging? Click it in the diagram.
60 kN @ 4 m6 kN/m, 0–6 m
1A (x = 0 m)
2B (x = 1 m)
3C (x = 2 m)
4D (x = 3 m)
5E (x = 4 m)
6F (x = 5 m)
7G (x = 6 m)
6.Shear force & bending momentHard
Find the bending moment Mx at the section x = 2 m from support A. Use sagging moments positive and upward shear on the left face positive.
L = 10 mP = 60 kN at 2 mw = 10 kN/m from 0 to 10 mx = 2 m
Mx = kN·m
7.Beam deflectionMedium
A simply supported beam carries a uniformly distributed load w over its whole span. Find the maximum deflection δmax, at midspan.
w = 6 kN/mL = 4 mE = 70 GPa (aluminium)I = 57 × 10⁶ mm⁴
δmax = mm
8.Beam deflectionHard
A simply supported timber beam of rectangular section, 100 mm wide, carries a uniformly distributed load w over its whole span. Its midspan deflection may not exceed span/360. Find the smallest depth hreq of the section.
w = 2.5 kN/mL = 3.5 mE = 11 GPa (timber)b = 100 mm
hreq = mm
9.Column bucklingMedium
A column of length L made of steel is fixed at the base and pinned at the top. Using Euler’s formula, find its critical buckling load Pcr.
L = 6 mE = 200 GPa (steel)d = 25 mm
Pcr = kN
10.Column bucklingHard
A column of length L made of steel is pinned at both ends. Find its slenderness and the critical buckling stress σcr from Euler’s formula.
L = 6 mE = 200 GPa (steel)d = 40 mm
σcr = MPa
11.Centroid & second moment of areaMedium
Find the second moment of area Ix of the T-section about the horizontal axis x through its centroid.
bf = 240 mmtf = 15 mmtw = 20 mmhw = 260 mm
Ix = × 10⁶ mm⁴
12.Centroid & second moment of areaHard
A welded I-section has a top flange 190 × 18 mm, a web 280 mm high and 12 mm thick, and a bottom flange 290 × 10 mm (width × thickness). Find its second moment of area Ix about the horizontal axis x through its centroid.
top flange: 190 × 18 mmweb: 12 × 280 mmbottom flange: 290 × 10 mm
Ix = × 10⁶ mm⁴
13.Effective stress in soilMedium
For the soil profile shown, find the pore water pressure u at point X.
A 5.5 m thick overconsolidated clay layer has Cc = 0.3, Cr = 0.03 and e₀ = 1. At its mid-depth the effective vertical stress is 110 kPa and the overconsolidation ratio is OCR = 2. A new building adds 140 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.
A clay layer 2.5 m thick has a coefficient of consolidation cv = 0.8 m²/year. It lies between two sand layers, so water drains out at the top and the bottom. For 90% average consolidation the time factor is Tv = 0.848. How many years t does the layer take to reach 90% consolidation?
A vertical rectangular gate 1 m wide sits in the wall of a tank of water, with its top edge 2 m below the surface. Find the resultant hydrostatic force F on the gate.
d = 2 mH = 1 mb = 1 mρ = 1000 kg/m³g = 9.81 m/s²
F = kN
18.Hydrostatic forceHard
A vertical rectangular gate 1.5 m wide sits in the wall of a tank of oil, with its top edge 1 m below the surface. Find the depth ycp of the centre of pressure below the surface.
d = 1 mH = 3 mb = 1.5 mρ = 880 kg/m³g = 9.81 m/s²
ycp = m
19.Pipe friction & head lossMedium
Water flows at 15 L/s through a pipe 500 m long with an inside diameter of 100 mm. Use the Darcy friction factor f = 0.02 and g = 9.81 m/s². Find the friction head loss hf.
Two open reservoirs are joined by a pipe 100 m long with an inside diameter of 100 mm and a Darcy friction factor f = 0.02. The minor losses are a square-edged entrance (K = 0.5), 2 bends (K = 0.3 each), a valve (K = 5) and the exit into the lower reservoir (K = 1.0). Use g = 9.81 m/s². What difference in water level Δz between the reservoirs gives a flow rate of 10 L/s?
A trapezoidal clean earth channel has a bottom width of 1 m and side slopes of 1.5:1 (horizontal:vertical). Water flows uniformly 2.4 m deep. Manning n = 0.022 and the bed slope is S = 0.004. Find the flow rate Q in m³/s.
b = 1 my = 2.4 mz = 1.5n = 0.022S = 0.004
Q = m³/s
22.Open-channel flow (Manning)Hard
A trapezoidal unfinished concrete channel with a bottom width of 5 m and side slopes of 2:1 (horizontal:vertical) must carry 41 m³/s in uniform flow at a depth of 2.2 m. Manning n = 0.014. Find the required bed slope S (in m/m).
Q = 41 m³/sb = 5 my = 2.2 mz = 2n = 0.014
S = m/m
23.Pumps & pump powerMedium
A pump delivers 30 L/s of water (ρ = 1000 kg/m³) against a head of 74 m. The pump efficiency is 82% and the electric motor driving it has an efficiency of 95%. Use g = 9.81 m/s². Find the electrical power Pel the motor draws, in kW.
A pump moves 20 L/s of water (ρ = 1000 kg/m³) from an open lower reservoir to an upper tank whose water surface is 17 m higher. The pipe is 400 m long with an inside diameter of 100 mm and a Darcy friction factor f = 0.02; the minor-loss coefficients add up to ΣK = 8 (entrance and exit included). Use g = 9.81 m/s². The upper tank is closed and the air above its water is at a gauge pressure of 250 kPa. Find the head H the pump must add.
A property is expected to earn net rent of €2 000 next year. The rent is expected to grow by 1% per year forever. The required return is 5% per year. Find the value PV of the property today.
C1 = €2 000g = 1%r = 5%
PV = €
26.Time value of moneyHard
A loan of €250 000 is repaid with equal monthly payments over 20 years. The interest rate is 4.8% per year, compounded monthly. Find the monthly payment A.
P = €250 0004.8% / 12N = 240
A = €
27.NPV & IRRMedium
An investment of €75 000 gives these cash flows at the end of years 1 to 3: €20 000, €22 000, €21 000. The cost of capital is 8%. Find the net present value NPV.
A project costs €20 000 and returns €14 500, €9 000, €9 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
CF0 = −20 000CF1 = 14 500CF2 = 9 000CF3 = 9 000
IRR = %
29.Normal distributionMedium
The exam scores are normally distributed with mean 65 points and standard deviation 10 points. What fraction lies between 53.5 and 75 points? Give P as a decimal.
μ = 65σ = 10x1 = 53.5x2 = 75
P =
30.Normal distributionHard
The IQ scores are normally distributed with mean 100 points and standard deviation 15 points. Find the value x below which 10% of them lie (the 10th percentile).
μ = 100σ = 15P = 10%
x = points
3Solutions
1.Beam support reactions
Answer: RB = 100 kN
Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Replace each distributed load by its resultant (its area) acting at the centroid of the load diagram, and take moments about a support to remove that support’s reaction from the equation.
Moments about A
Counter-clockwise positive.
ΣMA = 0: RB·6 = 80·1 + 65·8
RB = 600/6 = 100 kN
Vertical equilibrium
RA = 80 + 65 − 100 = 45 kN
Answer
RB = 100 kN
2.Beam support reactions
Answer: RB = 24.63 kN
Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Taking moments about one support removes that support’s reaction from the equation.
Free-body diagram
Replace the supports with reaction forces. A roller gives one vertical reaction; with only vertical loads the pin gives one vertical reaction too.
Equilibrium
Moments about A, counter-clockwise positive. Then vertical force balance.
UDL resultant: W = w·ℓ = 6·3 = 18 kN, acting at x̄ = 6.5 m
ΣMA = 0: RB·8 = 40·2 + 6·3·6.5
RB = 197/8 = 24.63 kN
ΣFy = 0: RA = 58 − 24.63 = 33.38 kN
Answer
RB = 24.63 kN
3.Truss: method of joints
Answer: FAC = 4.444 kN
Method of joints: every pin of a truss is in equilibrium, so ΣFx = 0 and ΣFy = 0 at each joint. Start at a joint with at most two unknown member forces. A negative result means the member is in compression.
Support reactions
Equilibrium of the whole truss. Moments about A, counter-clockwise positive.
ΣMA = 0: Cy·6 = 10·4 → Cy = 6.667 kN
ΣFy = 0: Ay = 10 − 6.667 = 3.333 kN
Joint C
The roller gives only a vertical reaction, so joint C has just two unknown member forces. Assume both in tension.
sin γ = 3/3.606 = 0.8321, cos γ = 2/3.606 = 0.5547
Method of joints: every pin of a truss is in equilibrium, so ΣFx = 0 and ΣFy = 0 at each joint. Start at a joint with at most two unknown member forces. A negative result means the member is in compression.
Support reactions
Equilibrium of the whole truss. Moments about A, counter-clockwise positive.
ΣMA = 0: Cy·5 = 45·2 + 15·2 → Cy = 24 kN
ΣFy = 0: Ay = 45 − 24 = 21 kN
ΣFx = 0: Ax = −15 kN
Joint C
The roller gives only a vertical reaction, so joint C has just two unknown member forces. Assume both in tension.
sin γ = 2/3.606 = 0.5547, cos γ = 3/3.606 = 0.8321
Largest bending moment: M changes slope wherever the shear force changes, so its peaks sit where the shear force crosses zero: under a point load, inside a distributed load, or over a support of an overhang. At a fixed support of a cantilever the moment is largest at the wall. Compare the size of M at those places, sagging or hogging.
Support reactions
Take moments about one support, then use the vertical force balance.
R1 = 38 kN, R2 = 58 kN
Bending moment at every mark
Sum the moments of all forces on one side of the cut. Sagging is positive, hogging negative.
MA = 0, MB = 35, MC = 64, MD = 87, ME = 104 kN·m, MF = 55, MG = 0
Answer
Mark E: ME = 104 kN·m
6.Shear force & bending moment
Answer: Mx = 176 kN·m
Method of sections: cut the beam where you want the internal forces and keep one side. The shear force V balances the vertical forces on that side, and the bending moment M balances their moments about the cut.
Support reactions
Equilibrium of the whole beam.
UDL resultant: W = w·ℓ = 10·10 = 100 kN, acting at x̄ = 5 m
ΣMA = 0: RB·10 = 60·2 + 10·10·5
RB = 620/10 = 62 kN
ΣFy = 0: RA = 160 − 62 = 98 kN
Cut at x = 2 m and keep the left part
Only forces left of the cut appear. A UDL portion acts as one force at the middle of that portion.
M = RA·x − (each load left of the cut × its distance to the cut)
Mx = 98·2 − 10·2·1 = 176 kN·m
Answer
Mx = 176 kN·m
7.Beam deflection
Answer: δmax = 5.013 mm
Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).
Consistent units
Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.
w = 6 N/mm, L = 4000 mm
EI = 3.99 × 10¹² N·mm²
Deflection
δmax = 5wL⁴/(384EI) = 5·6·4000⁴/(384·3.99 × 10¹²) = 5.013 mm
Answer
δmax = 5.013 mm
8.Beam deflection
Answer: hreq = 176.3 mm
Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).
Consistent units
Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.
bh³/12 = Ireq → h = (12·4.568 × 10⁷/100)1/3 = 176.3 mm
Answer
hreq = 176.3 mm
In practice, choose the next standard depth above this value.
9.Column buckling
Answer: Pcr = 2.146 kN
Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.
Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.
Smallest second moment of area
A round section has the same I about every axis.
I = πd⁴/64 = π·40⁴/64 = 125664 mm⁴
Radius of gyration and slenderness
A = 1257 mm²
r = √(I/A) = √(125664/1257) = 10 mm
KL = 1·6000 = 6000 mm
KL/r = 6000/10 = 600
Critical stress
σcr = π²E/(KL/r)² = π²·200000/600² = 5.483 MPa
Answer
σcr = 5.483 MPa
11.Centroid & second moment of area
Answer: Ix = 69.58 × 10⁶ mm⁴
Composite areas: split the section into rectangles. The centroid is the area-weighted average ȳ = ΣAᵢyᵢ/ΣAᵢ. The second moment of area about the centroidal axis adds each part’s own bh³/12 and its parallel-axis term A·d², where d is the distance from the part’s centroid to the overall centroid. Bending stress is σ = M·y/I.
Split into two rectangles
Measure every y from the bottom edge.
flange: Af = 240·15 = 3600 mm², yf = 260 + 15/2 = 267.5 mm
Composite areas: split the section into rectangles. The centroid is the area-weighted average ȳ = ΣAᵢyᵢ/ΣAᵢ. The second moment of area about the centroidal axis adds each part’s own bh³/12 and its parallel-axis term A·d², where d is the distance from the part’s centroid to the overall centroid. Bending stress is σ = M·y/I.
Split into three rectangles
Measure every y from the bottom edge.
top flange: A = 3420 mm², y = 299 mm
web: A = 3360 mm², y = 150 mm
bottom flange: A = 2900 mm², y = 5 mm
Centroid
ȳ = (3420·299 + 3360·150 + 2900·5)/9680 = 159.2 mm
Parallel-axis theorem
top flange: 190·18³/12 + 3420·139.8² = 6.693 × 10⁷ mm⁴
Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).
Pore water pressure
Water pressure grows with depth below the water table.
u = γw·(z − zw) = 9.81·1 = 9.81 kPa
Answer
u = 9.81 kPa
14.Effective stress in soil
Answer: σ′ = 80.85 kPa
Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).
Total stress
Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.
σ = γd·3 + γsat,sand·1 + γsat,clay·3.5
σ = 15.5·3 + 19·1 + 17·3.5 = 125 kPa
Pore water pressure
Water pressure grows with depth below the water table.
u = γw·(z − zw) = 9.81·4.5 = 44.15 kPa
Effective stress
σ′ = σ − u = 125 − 44.15 = 80.85 kPa
Answer
σ′ = 80.85 kPa
15.Consolidation settlement
Answer: S = 70.64 mm
Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.
Preconsolidation pressure
σ′p = OCR·σ′0 = 2·110 = 220 kPa
Compare with the preconsolidation pressure
σ′f = 110 + 140 = 250 kPa > 220 kPa
Settlement
Recompression up to σ′p, virgin compression beyond it.
S = 0.03·5.5/(1 + 1)·log₁₀(220/110) + 0.3·5.5/(1 + 1)·log₁₀(250/220)
S = 24.83 + 45.8 = 70.64 mm
Answer
S = 70.64 mm
16.Consolidation settlement
Answer: t = 1.656 years
Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.
Drainage path
Hdr = H/2 = 2.5/2 = 1.25 m
Time
t = Tv·Hdr²/cv = 0.848·1.25²/0.8 = 1.656 years
Answer
t = 1.656 years
17.Hydrostatic force
Answer: F = 24.52 kN
Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.
Centroid depth and area
yc = d + H/2 = 2 + 1/2 = 2.5 m
A = H·b = 1·1 = 1 m²
Resultant force
F = ρ·g·yc·A = 1000·9.81·2.5·1 = 24.52 kN
Answer
F = 24.52 kN
18.Hydrostatic force
Answer: ycp = 2.8 m
Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.
Centroid depth and area
yc = d + H/2 = 1 + 3/2 = 2.5 m
A = H·b = 3·1.5 = 4.5 m²
Resultant force
F = ρ·g·yc·A = 880·9.81·2.5·4.5 = 97.12 kN
Centre of pressure
Pressure grows with depth, so the resultant acts below the centroid.
Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.
Mean velocity
A = π·0.1²/4 = 0.007854 m²
V = Q/A = 0.015/0.007854 = 1.91 m/s
Velocity head
V²/(2g) = 1.91²/(2·9.81) = 0.1859 m
Darcy–Weisbach
hf = f·(L/D)·V²/(2g) = 0.02·(500/0.1)·1.91²/(2·9.81) = 18.59 m
Answer
hf = 18.59 m
20.Pipe friction & head loss
Answer: Δz = 2.239 m
Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.
Velocity
V = Q/A = 0.01/0.007854 = 1.273 m/s
V²/(2g) = 0.08263 m
Loss coefficients
f·L/D = 0.02·100/0.1 = 20
ΣK = 0.5 + 2·0.3 + 5 + 1.0 = 7.1
Total head loss
hf = 20·0.08263 = 1.653 m
hm = 7.1·0.08263 = 0.5867 m
Δz = hf + hm = 2.239 m
Answer
Δz = 2.239 m
21.Open-channel flow (Manning)
Answer: Q = 34.71 m³/s
Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.
Geometry
A = (b + z·y)·y = (1 + 1.5·2.4)·2.4 = 11.04 m²
P = b + 2y·√(1 + z²) = 1 + 2·2.4·√(1 + 1.5²) = 9.653 m
R = A/P = 1.144 m
Velocity
V = (1/0.022)·1.1442/3·0.0041/2 = 3.144 m/s
Flow rate
Q = A·V = 11.04·3.144 = 34.71 m³/s
Answer
Q = 34.71 m³/s
22.Open-channel flow (Manning)
Answer: S = 0.0004949 m/m
Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.
Geometry
A = (b + z·y)·y = (5 + 2·2.2)·2.2 = 20.68 m²
P = b + 2y·√(1 + z²) = 5 + 2·2.2·√(1 + 2²) = 14.84 m
Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.
Hydraulic power
Ph = ρ·g·Q·H = 1000·9.81·0.03·74 = 21.78 kW
Shaft power
Pshaft = 21.78/0.82 = 26.56 kW
Electrical power
Pel = 26.56/0.95 = 27.96 kW
Answer
Pel = 27.96 kW
24.Pumps & pump power
Answer: H = 71.57 m
Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.
Both surfaces are practically at rest, so there is no velocity head term.
H = Δz + p/(ρ·g) + hL = 17 + 25.48 + 29.08 = 71.57 m
Answer
H = 71.57 m
25.Time value of money
Answer: PV = 50000 €
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Monthly rate and number of payments
i = 0.048/12 = 0.004
N = 12·20 = 240
Payment
The present value of N equal payments A is A·(1 − (1 + i)⁻ᴺ)/i. Set it equal to the loan and solve for A.
(1 + i)−N = 0.3836
A = 250 000·0.004/(1 − 0.3836) = €1 622.39
Answer
A = €1 622.39
27.NPV & IRR
Answer: NPV = −20950 €
Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.
Present value of each cash flow
CF0 = −75 000
CF1/(1 + 0.08)1 = 20 000/1.08 = 18 518.52
CF2/(1 + 0.08)2 = 22 000/1.166 = 18 861.45
CF3/(1 + 0.08)3 = 21 000/1.26 = 16 670.48
Add them up
NPV = €−20 949.55
Answer
NPV = €−20 949.55
NPV is negative, so the project earns less than the required return.
28.NPV & IRR
Answer: IRR = 32.25 %
Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.
Bracket the IRR
NPV falls as the rate rises, so the IRR lies between a rate with positive NPV and one with negative NPV.
NPV(30%) = 575.79
NPV(35%) = −663.01
Narrow down
Linear interpolation gives a first estimate; repeating it (or a calculator's IRR function) gives the exact rate.
IRR ≈ 30 + 5·575.79/(575.79 − (−663.01)) = 32.32%
exact: NPV(32.25%) = 0 → IRR = 32.25%
Answer
IRR = 32.25%
29.Normal distribution
Answer: P = 0.7163
Normal distribution: convert a value x to a z-score, z = (x − μ)/σ, which counts standard deviations from the mean. A z-table (or Φ(z)) gives the area to the left of z, which is P(X < x). The area to the right is 1 − Φ(z), and the area between two values is the difference of their two areas.
z-scores
z₁ = (53.5 − 65)/10 = −1.15
z₂ = (75 − 65)/10 = 1
Area between
P = Φ(1) − Φ(−1.15) = 0.8413 − 0.1251 = 0.7163
Answer
P = 0.7163
30.Normal distribution
Answer: x = 80.78 points
Normal distribution: convert a value x to a z-score, z = (x − μ)/σ, which counts standard deviations from the mean. A z-table (or Φ(z)) gives the area to the left of z, which is P(X < x). The area to the right is 1 − Φ(z), and the area between two values is the difference of their two areas.
z for the percentile
Φ(z) = 0.1 → z = −1.282
Back to x
x = 100 + −1.282·15 = 80.78 points
Answer
x = 80.78 points