laminar below Re ≈ 2000, turbulent above Re ≈ 4000
Mean velocity
V = Q/A, A = π·D²/4
Darcy–Weisbach
hf = f·(L/D)·V²/(2g)
Minor losses
hm = ΣK·V²/(2g)
Typical K values
entrance 0.5, exit 1.0, 90° bend ≈ 0.3
Pressure drop
Δp = ρ·g·hf
Two open reservoirs
Δz = (f·L/D + ΣK)·V²/(2g)
Free outlet
H = (1 + f·L/D + ΣK)·V²/(2g)
Open-channel flow (Manning)
Manning equation
V = (1/n)·R2/3·S1/2
Flow rate
Q = A·V
Hydraulic radius
R = A/P (P = wetted perimeter, free surface excluded)
Rectangle
A = b·y, P = b + 2y
Trapezoid (side slope z:1)
A = (b + z·y)·y, P = b + 2y·√(1 + z²)
Circular pipe, full or half full
R = D/4
Required slope
S = (n·Q/(A·R2/3))²
Pumps & pump power
Hydraulic power
Ph = ρ·g·Q·H = Q·Δp
Shaft power
Pshaft = Ph/ηpump
Electrical power
Pel = Pshaft/ηmotor
Pump head
H = Δz + Δp/(ρ·g) + hL
System losses
hL = (f·L/D + ΣK)·V²/(2g)
Time value of money
Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i
Method
Draw a timeline with every cash flow and its timing.
Match the rate to the period: a monthly rate for monthly payments.
Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
Check the sign and the order of magnitude of the answer.
NPV & IRR
Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)
Method
List all cash flows with their year; the investment at year 0 is negative.
Discount each cash flow: CFt/(1 + r)t.
Add them up to get the NPV. Positive means the project earns more than r.
For the IRR, find the rate that makes NPV zero by trial or interpolation.
Normal distribution
z-score
z = (x − μ)/σ
Below x
P(X < x) = Φ(z)
Above x
P(X > x) = 1 − Φ(z)
Between
Φ(z2) − Φ(z1)
Percentile
x = μ + z·σ
Method
Convert the value to a z-score: z = (x − μ)/σ.
Look up Φ(z), the area to the left of z.
For the area to the right use 1 − Φ(z); for an interval subtract the two left areas.
For a percentile, work backwards: find z for the area, then x = μ + z·σ.
2Practice problems
1.Beam support reactionsMedium
The simply supported beam has a pin at A and a roller at B. Find the vertical support reaction RB.
L = 6 mP1 = 30 kN at 2 mP2 = 20 kN at 5 m
RB = kN
2.Beam support reactionsHard
A compound beam is fixed to the wall at A, has an internal hinge at C (4 m from A) and rests on a roller at D (10 m from A). It carries a point load P at 7 m from A. Find the magnitude of the reaction moment MA at the wall.
AC = 4 mAD = 10 mP = 65 kN at 7 m
MA = kN·m
3.Truss: method of jointsMedium
Use the method of joints to find the force FAC in member AC. Give tension as positive and compression as negative.
span = 6 mheight = 3 mB is 5 m from Avertical load = 55 kN
FAC = kN
4.Truss: method of jointsHard
Exactly one member of this truss carries no force under these loads. Which is the zero-force member? Click it in the diagram.
The simply supported beam carries a clockwise couple M0 = 55 kN·m at x = 7 m from A, and no other load. Find the bending moment Mx just to the left of the couple. Use sagging moments positive and upward shear on the left face positive.
L = 10 mM0 = 55 kN·m clockwise, at 7 m
Mx = kN·m
6.Shear force & bending momentHard
The simply supported beam carries a uniformly distributed load w over its whole span and a point load P. Find the maximum bending moment Mmax in the beam.
L = 4 mP = 55 kN at 2.5 mw = 2 kN/m from 0 to 4 m
Mmax = kN·m
7.Beam deflectionMedium
A cantilever carries a uniformly distributed load w over its whole length. Find the deflection δ at the free end.
w = 20 kN/mL = 2.5 mE = 200 GPa (steel)I = 12 × 10⁶ mm⁴
δ = mm
8.Beam deflectionHard
A propped cantilever is fixed at A and simply supported (propped) at B. It carries a uniformly distributed load w over its whole length. EI is constant. Find the size of the bending moment MA at the fixed end.
L = 6 mw = 15 kN/m
MA = kN·m
9.Column bucklingMedium
A column of length L made of steel is pinned at both ends. Using Euler’s formula, find its critical buckling load Pcr.
L = 6 mE = 200 GPa (steel)b × h = 20 × 80 mm
Pcr = kN
10.Column bucklingHard
A solid round column of length L made of steel is pinned at both ends. It must carry 115 kN with a factor of safety of 2 against buckling. Find the smallest diameter d.
P = 115 kNn = 2L = 3 mE = 200 GPa (steel)
d = mm
11.Centroid & second moment of areaMedium
Find the second moment of area Ix of the T-section about the horizontal axis x through its centroid.
bf = 160 mmtf = 20 mmtw = 14 mmhw = 120 mm
Ix = × 10⁶ mm⁴
12.Centroid & second moment of areaHard
The T-section is used as a beam with the flange on top and carries a sagging bending moment of 40 kN·m. Find the size of the bending stress σtop at the top edge.
A 4 m thick overconsolidated clay layer has Cc = 0.3, Cr = 0.02 and e₀ = 0.85. At its mid-depth the effective vertical stress is 85 kPa and the preconsolidation pressure is 195 kPa. A new building adds 105 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.
A clay layer 9 m thick has a coefficient of consolidation cv = 2 m²/year. It lies between two sand layers, so water drains out at the top and the bottom. For 70% average consolidation the time factor is Tv = 0.403. How many years t does the layer take to reach 70% consolidation?
A vertical rectangular gate 3 m wide sits in the wall of a tank of water, with its top edge 1.5 m below the surface. Find the resultant hydrostatic force F on the gate.
A vertical rectangular gate 1 m wide sits in the wall of a tank of glycerin, with its top edge 2 m below the surface. Find the depth ycp of the centre of pressure below the surface.
d = 2 mH = 1 mb = 1 mρ = 1260 kg/m³g = 9.81 m/s²
ycp = m
19.Pipe friction & head lossMedium
Water (ρ = 1000 kg/m³) flows at 2.3 m/s through a horizontal pipe, 100 m long, with an inside diameter of 300 mm. Use the Darcy friction factor f = 0.03 and g = 9.81 m/s². Find the pressure drop Δp over the pipe in kPa.
Two open reservoirs are joined by a pipe 100 m long with an inside diameter of 200 mm and a Darcy friction factor f = 0.015. The minor losses are a square-edged entrance (K = 0.5), 2 bends (K = 0.3 each), a valve (K = 0.2) and the exit into the lower reservoir (K = 1.0). Use g = 9.81 m/s². What difference in water level Δz between the reservoirs gives a flow rate of 80 L/s?
A trapezoidal brickwork channel has a bottom width of 5 m and side slopes of 3:1 (horizontal:vertical). Water flows uniformly 1.5 m deep. Manning n = 0.015 and the bed slope is S = 0.001. Find the flow rate Q in m³/s.
b = 5 my = 1.5 mz = 3n = 0.015S = 0.001
Q = m³/s
22.Open-channel flow (Manning)Hard
A trapezoidal clean earth channel with a bottom width of 2 m and side slopes of 2:1 (horizontal:vertical) must carry 45 m³/s in uniform flow at a depth of 2.2 m. Manning n = 0.022. Find the required bed slope S (in m/m).
Q = 45 m³/sb = 2 my = 2.2 mz = 2n = 0.022
S = m/m
23.Pumps & pump powerMedium
A pump with an efficiency of 70% delivers 30 L/s of water (ρ = 1000 kg/m³) against a head of 38 m. Use g = 9.81 m/s². Find the shaft power Pshaft needed, in kW.
Q = 30 L/sH = 38 mη = 70%g = 9.81 m/s²
Pshaft = kW
24.Pumps & pump powerHard
A pump moves 60 L/s of water (ρ = 1000 kg/m³) from an open lower reservoir to an upper tank whose water surface is 7 m higher. The pipe is 500 m long with an inside diameter of 200 mm and a Darcy friction factor f = 0.015; the minor-loss coefficients add up to ΣK = 5 (entrance and exit included). Use g = 9.81 m/s². The pump efficiency is 80%. Find the shaft power Pshaft in kW.
A property is expected to earn net rent of €6 000 next year. The rent is expected to grow by 4% per year forever. The required return is 10% per year. Find the value PV of the property today.
C1 = €6 000g = 4%r = 10%
PV = €
26.Time value of moneyHard
You deposit €3 000 at the start of every year for 27 years, the first deposit today. The account pays 4% per year. How much is in the account at the end of year 27? Find FV.
A = €3 000i = 4%n = 27
FV = €
27.NPV & IRRMedium
A project costs €20 000 today and returns €5 500, €8 000, €8 500, €5 000, €9 000 at the end of years 1 to 5. The cost of capital is 8%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
A project costs €50 000 and returns €29 000, €22 000, €36 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
CF0 = −50 000CF1 = 29 000CF2 = 22 000CF3 = 36 000
IRR = %
29.Normal distributionMedium
Drag z so that the shaded area between −z and z under the standard normal curve is 0.5527. Find z to two decimals.
A = 0.5527
z =
30.Normal distributionHard
The exam scores are normally distributed with mean 65 points and standard deviation 10 points. Find the value x below which 20% of them lie (the 20th percentile).
μ = 65σ = 10P = 20%
x = points
3Solutions
1.Beam support reactions
Answer: RB = 26.67 kN
Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Taking moments about one support removes that support’s reaction from the equation.
Free-body diagram
Replace the supports with reaction forces. A roller gives one vertical reaction; with only vertical loads the pin gives one vertical reaction too.
Equilibrium
Moments about A, counter-clockwise positive. Then vertical force balance.
ΣMA = 0: RB·6 = 30·2 + 20·5
RB = 160/6 = 26.67 kN
ΣFy = 0: RA = 50 − 26.67 = 23.33 kN
Answer
RB = 26.67 kN
2.Beam support reactions
Answer: MA = 130 kN·m
Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Replace each distributed load by its resultant (its area) acting at the centroid of the load diagram, and take moments about a support to remove that support’s reaction from the equation. An internal hinge cannot carry a bending moment, which gives one extra equation: the moment about the hinge of the forces on either side is zero.
Part CD
The hinge has no moment, so moments about C on CD alone must balance.
ΣMC = 0: RD·6 = 65·3
RD = 32.5 kN
VC = 65 − 32.5 = 32.5 kN
Part AC
The hinge force VC acts downward on AC (equal and opposite to its action on CD).
RA = 32.5 = 32.5 kN
MA = 32.5·4 = 130 kN·m
Answer
MA = 130 kN·m
3.Truss: method of joints
Answer: FAC = 15.28 kN
Method of joints: every pin of a truss is in equilibrium, so ΣFx = 0 and ΣFy = 0 at each joint. Start at a joint with at most two unknown member forces. A negative result means the member is in compression.
Support reactions
Equilibrium of the whole truss. Moments about A, counter-clockwise positive.
ΣMA = 0: Cy·6 = 55·5 → Cy = 45.83 kN
ΣFy = 0: Ay = 55 − 45.83 = 9.167 kN
Joint C
The roller gives only a vertical reaction, so joint C has just two unknown member forces. Assume both in tension.
sin γ = 3/3.162 = 0.9487, cos γ = 1/3.162 = 0.3162
Zero-force members: at a joint, the forces must balance in every direction. If a joint has no load and no support, and two of its three members are in line, then the balance across that line involves only the third member, so its force is zero. If only two members meet at an unloaded joint and they are not in line, both are zero.
Joint D
CD and DE lie on one straight line and the joint carries no load. Balancing forces across that line leaves only DH.
ΣF⊥ = 0 → FDH = 0
Check with the method of joints
Solving all joints gives these member forces (T = tension, C = compression).
Method of sections: cut the beam where you want the internal forces and keep one side. The shear force V balances the vertical forces on that side, and the bending moment M balances their moments about the cut. An applied couple makes the bending moment diagram jump by the size of the couple.
Support reactions
Moments about A, counter-clockwise positive: RB·L − M0 = 0. Vertical balance: RA + RB = 0.
RB = M0/L = 55/10 = 5.5 kN (upward)
RA = −RB = −5.5 kN (downward)
Cut just left of the couple
The left part contains only RA.
Mx = RA·a = −5.5·7 = −38.5 kN·m
Answer
Mx = −38.5 kN·m
6.Shear force & bending moment
Answer: Mmax = 55.31 kN·m
Method of sections: cut the beam where you want the internal forces and keep one side. The shear force V balances the vertical forces on that side, and the bending moment M balances their moments about the cut. Maximum moment: since dM/dx = V, the bending moment has its peak where the shear force passes through zero, either at a point load or inside a distributed load.
Support reactions
Equilibrium of the whole beam.
UDL resultant: W = w·ℓ = 2·4 = 8 kN, acting at x̄ = 2 m
ΣMA = 0: RB·4 = 55·2.5 + 2·4·2
RB = 153.5/4 = 38.38 kN
ΣFy = 0: RA = 63 − 38.38 = 24.63 kN
Where is V = 0?
V(2.5⁻) = RA − w·2.5 = 19.63 kN
V(2.5⁺) = 19.63 − 55 = −35.38 kN
The shear changes sign at the load, so the maximum is under the load.
Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).
Consistent units
Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.
w = 20 N/mm, L = 2500 mm
EI = 2.4 × 10¹² N·mm²
Deflection
δ = wL⁴/(8EI) = 20·2500⁴/(8·2.4 × 10¹²) = 40.69 mm
Answer
δ = 40.69 mm
8.Beam deflection
Answer: MA = 67.5 kN·m
Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition). For a statically indeterminate beam, remove a redundant support and require the deflection there to be zero (compatibility).
Remove the prop
Without the prop the beam is a cantilever. Its free end would deflect under the load.
δload = wL⁴/(8EI)
Compatibility at the prop
The prop force RB alone lifts the free end by RBL³/(3EI). The prop holds B at zero deflection, so the two must cancel. EI cancels out.
Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.
Smallest second moment of area
A rectangle buckles about its weak axis, using the smaller dimension cubed.
Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.
Required critical load
Pcr = n·P = 2·115000 = 230000 N
KL = 1·3000 = 3000 mm
Solve for the diameter
d = (64·n·P·(KL)²/(π³E))^(1/4) = (64·230000·3000²/(π³·200000))^(1/4) = 67.99 mm
Answer
d = 67.99 mm
Check: the slenderness KL/r is 176.5, so the column is slender and Euler applies.
11.Centroid & second moment of area
Answer: Ix = 7.521 × 10⁶ mm⁴
Composite areas: split the section into rectangles. The centroid is the area-weighted average ȳ = ΣAᵢyᵢ/ΣAᵢ. The second moment of area about the centroidal axis adds each part’s own bh³/12 and its parallel-axis term A·d², where d is the distance from the part’s centroid to the overall centroid. Bending stress is σ = M·y/I.
Split into two rectangles
Measure every y from the bottom edge.
flange: Af = 160·20 = 3200 mm², yf = 120 + 20/2 = 130 mm
Composite areas: split the section into rectangles. The centroid is the area-weighted average ȳ = ΣAᵢyᵢ/ΣAᵢ. The second moment of area about the centroidal axis adds each part’s own bh³/12 and its parallel-axis term A·d², where d is the distance from the part’s centroid to the overall centroid. Bending stress is σ = M·y/I.
Split into two rectangles
Measure every y from the bottom edge.
flange: Af = 300·20 = 6000 mm², yf = 160 + 20/2 = 170 mm
Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).
Total stress
Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.
Water pressure grows with depth below the water table.
u = γw·(z − zw) = 9.81·1 = 9.81 kPa
Effective stress
σ′ = σ − u = 36.5 − 9.81 = 26.69 kPa
Answer
σ′ = 26.69 kPa
14.Effective stress in soil
Answer: σ′ = 93.71 kPa
Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).
Total stress
Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.
σ = γd·1 + γsat,sand·5 + γsat,clay·4
σ = 15.5·1 + 18.5·5 + 18.5·4 = 182 kPa
Pore water pressure
Water pressure grows with depth below the water table.
u = γw·(z − zw) = 9.81·9 = 88.29 kPa
Effective stress
σ′ = σ − u = 182 − 88.29 = 93.71 kPa
Answer
σ′ = 93.71 kPa
15.Consolidation settlement
Answer: S = 15.11 mm
Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.
Compare with the preconsolidation pressure
σ′f = 85 + 105 = 190 kPa ≤ 195 kPa
Settlement
The clay stays on its recompression line.
S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0) = 0.02·4/(1 + 0.85)·log₁₀(190/85) = 15.11 mm
Answer
S = 15.11 mm
16.Consolidation settlement
Answer: t = 4.08 years
Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.
Drainage path
Hdr = H/2 = 9/2 = 4.5 m
Time
t = Tv·Hdr²/cv = 0.403·4.5²/2 = 4.08 years
Answer
t = 4.08 years
17.Hydrostatic force
Answer: F = 58.86 kN
Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.
Centroid depth and area
yc = d + H/2 = 1.5 + 1/2 = 2 m
A = H·b = 1·3 = 3 m²
Resultant force
F = ρ·g·yc·A = 1000·9.81·2·3 = 58.86 kN
Answer
F = 58.86 kN
18.Hydrostatic force
Answer: ycp = 2.533 m
Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.
Centroid depth and area
yc = d + H/2 = 2 + 1/2 = 2.5 m
A = H·b = 1·1 = 1 m²
Resultant force
F = ρ·g·yc·A = 1260·9.81·2.5·1 = 30.9 kN
Centre of pressure
Pressure grows with depth, so the resultant acts below the centroid.
Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.
Head loss
hf = f·(L/D)·V²/(2g) = 0.03·(100/0.3)·2.3²/(2·9.81) = 2.696 m
Pressure drop
The pipe is horizontal and the velocity does not change, so the energy equation reduces to Δp = ρ·g·hf.
Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.
Velocity
V = Q/A = 0.08/0.03142 = 2.546 m/s
V²/(2g) = 0.3305 m
Loss coefficients
f·L/D = 0.015·100/0.2 = 7.5
ΣK = 0.5 + 2·0.3 + 0.2 + 1.0 = 2.3
Total head loss
hf = 7.5·0.3305 = 2.479 m
hm = 2.3·0.3305 = 0.7602 m
Δz = hf + hm = 3.239 m
Answer
Δz = 3.239 m
21.Open-channel flow (Manning)
Answer: Q = 29.71 m³/s
Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.
Geometry
A = (b + z·y)·y = (5 + 3·1.5)·1.5 = 14.25 m²
P = b + 2y·√(1 + z²) = 5 + 2·1.5·√(1 + 3²) = 14.49 m
R = A/P = 0.9837 m
Velocity
V = (1/0.015)·0.98372/3·0.0011/2 = 2.085 m/s
Flow rate
Q = A·V = 14.25·2.085 = 29.71 m³/s
Answer
Q = 29.71 m³/s
22.Open-channel flow (Manning)
Answer: S = 0.003923 m/m
Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.
Geometry
A = (b + z·y)·y = (2 + 2·2.2)·2.2 = 14.08 m²
P = b + 2y·√(1 + z²) = 2 + 2·2.2·√(1 + 2²) = 11.84 m
Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.
Hydraulic power
Ph = ρ·g·Q·H = 1000·9.81·0.03·38 = 11.18 kW
Shaft power
Pshaft = Ph/η = 11.18/0.7 = 15.98 kW
Answer
Pshaft = 15.98 kW
24.Pumps & pump power
Answer: Pshaft = 10.96 kW
Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Ordinary annuity factor
((1 + 0.04)27 − 1)/0.04 = 47.08
Annuity due
Each deposit is invested one year longer.
FV = 3 000·47.08·1.04 = €146 902.75
Answer
FV = €146 902.75
27.NPV & IRR
Answer: DPB = 3.354 years
Payback period: the time until the cumulative cash flows repay the initial investment. Cash is assumed to come in evenly during each year, so the last part is a fraction of a year. The simple payback ignores the time value of money; the discounted payback period uses the discounted cash flows instead.
Discounted and cumulative cash flows
year 1: 5 500/1.08 = 5 092.59 → Σ = 5 092.59
year 2: 8 000/1.166 = 6 858.71 → Σ = 11 951.30
year 3: 8 500/1.26 = 6 747.57 → Σ = 18 698.88
year 4: 5 000/1.36 = 3 675.15 → Σ = 22 374.03
Fraction of the last year
DPB = 3 + 1 301.12/3 675.15 = 3.354
Answer
DPB = 3.354 years
The discounted payback is always longer than the simple payback (2.765 years).
28.NPV & IRR
Answer: IRR = 32.35 %
Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.
Bracket the IRR
NPV falls as the rate rises, so the IRR lies between a rate with positive NPV and one with negative NPV.
NPV(30%) = 1 711.42
NPV(35%) = −1 815.27
Narrow down
Linear interpolation gives a first estimate; repeating it (or a calculator's IRR function) gives the exact rate.
From an area back to z: Φ(z) is the area to the left of z. For a left-tail area A, find z with Φ(z) = A in the table. A right-tail area A means Φ(z) = 1 − A. A central area A between −z and z leaves (1 − A)/2 in each tail, so Φ(z) = (1 + A)/2. For a value x, use x = μ + zσ.
Area to the left of z
Φ(z) = (1 + 0.5527)/2 = 0.7764
Read the z-table backwards
Find 0.7764 inside the table and read off z.
z = 0.76
Answer
z = 0.76
30.Normal distribution
Answer: x = 56.58 points
Normal distribution: convert a value x to a z-score, z = (x − μ)/σ, which counts standard deviations from the mean. A z-table (or Φ(z)) gives the area to the left of z, which is P(X < x). The area to the right is 1 − Φ(z), and the area between two values is the difference of their two areas.
z for the percentile
Φ(z) = 0.2 → z = −0.8416
Back to x
x = 65 + −0.8416·10 = 56.58 points
Answer
x = 56.58 points
This is independent practice material. ExamProblems is not affiliated with or endorsed by the organisation that runs this exam, and the exam name is used only to describe the content. The FE exam is run by NCEES, which is not affiliated with ExamProblems and does not endorse it.