1Formulas and methods

Beam support reactions

Equilibrium
ΣFx = 0, ΣFy = 0, ΣM = 0
Uniform load
resultant w·L at the middle of the load
Moment
M = F·d

Method

  1. Draw a free-body diagram and replace each support by its reactions.
  2. Replace every distributed load by a single force at its centroid.
  3. Take moments about one support to find the reaction at the other.
  4. Use ΣFy = 0 to find the remaining reaction, and check with a second moment equation.

Truss: method of joints

Method of joints
ΣFx = 0, ΣFy = 0 at each joint
Method of sections
ΣM = 0 about a cut point
Member force
positive = tension, negative = compression

Method

  1. Find the support reactions for the whole truss.
  2. Method of joints: start at a joint with at most two unknown member forces and use ΣFx = 0 and ΣFy = 0.
  3. Method of sections: cut through the member you need and take moments about a point where the other unknown members meet.
  4. Assume tension; a negative answer means compression.

Shear force & bending moment

Shear and moment
V = ΣF on one side, M = ΣF·d on one side
Bending stress
σ = M·y/I
Rectangle
I = bh³/12
Section modulus
W = I/ymax
Simply supported, uniform load
Mmax = wL²/8

Method

  1. Find the support reactions from equilibrium of the whole beam.
  2. Cut the beam at the section you need and keep one side.
  3. Shear force: sum of the vertical forces on that side. Bending moment: sum of their moments about the cut.
  4. For the maximum moment, find where the shear force is zero.

Beam deflection

Point load at midspan
δ = PL³/(48EI)
Uniform load, simply supported
δ = 5wL⁴/(384EI)
Cantilever, end load
δ = PL³/(3EI)
Cantilever, uniform load
δ = wL⁴/(8EI)
Superposition
δ = δ1 + δ2

Column buckling

Euler load
Pcr = π²EI/(KL)²
Effective length factor
K = 1 pinned–pinned, 0.5 fixed–fixed, 0.7 fixed–pinned, 2 fixed–free
Critical stress
σcr = Pcr/A
Slenderness
λ = KL/r, r = √(I/A)

Centroid & second moment of area

Centroid
ȳ = ΣAiyi/ΣAi
Rectangle
I = bh³/12
Parallel-axis theorem
I = Ic + A·d²
Composite section
I = Σ(Ic,i + Aidi²)

Effective stress in soil

Total stress
σ = Σγi·hi
Pore water pressure
u = γw·(z − zw)
Effective stress
σ′ = σ − u
Water
γw = 9.81 kN/m³

Consolidation settlement

Normally consolidated
S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0)
Final stress
σ′f = σ′0 + Δσ (at mid-depth of the layer)
Overconsolidated, σ′f ≤ σ′p
S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0)
Overconsolidated, σ′f > σ′p
S = H/(1 + e0)·[Cr·log₁₀(σ′p/σ′0) + Cc·log₁₀(σ′f/σ′p)]
Overconsolidation ratio
OCR = σ′p/σ′0
Time for consolidation
t = Tv·Hdr²/cv
Drainage path
Hdr = H/2 (double drainage), H (single drainage)
Time factors
U 50% → 0.197, 60% → 0.287, 70% → 0.403, 80% → 0.567, 90% → 0.848

Hydrostatic force

Pressure at depth
p = ρgh
Force on a vertical wall
F = ρg·hc·A
Centre of pressure
yp = yc + Ic/(ycA)
Rectangle
Ic = bH³/12

Pipe friction & head loss

Reynolds number
Re = V·D/ν = ρ·V·D/μ
Flow regime
laminar below Re ≈ 2000, turbulent above Re ≈ 4000
Mean velocity
V = Q/A, A = π·D²/4
Darcy–Weisbach
hf = f·(L/D)·V²/(2g)
Minor losses
hm = ΣK·V²/(2g)
Typical K values
entrance 0.5, exit 1.0, 90° bend ≈ 0.3
Pressure drop
Δp = ρ·g·hf
Two open reservoirs
Δz = (f·L/D + ΣK)·V²/(2g)
Free outlet
H = (1 + f·L/D + ΣK)·V²/(2g)

Open-channel flow (Manning)

Manning equation
V = (1/n)·R2/3·S1/2
Flow rate
Q = A·V
Hydraulic radius
R = A/P (P = wetted perimeter, free surface excluded)
Rectangle
A = b·y, P = b + 2y
Trapezoid (side slope z:1)
A = (b + z·y)·y, P = b + 2y·√(1 + z²)
Circular pipe, full or half full
R = D/4
Required slope
S = (n·Q/(A·R2/3))²

Pumps & pump power

Hydraulic power
Ph = ρ·g·Q·H = Q·Δp
Shaft power
Pshaft = Ph/ηpump
Electrical power
Pel = Pshaft/ηmotor
Pump head
H = Δz + Δp/(ρ·g) + hL
System losses
hL = (f·L/D + ΣK)·V²/(2g)

Time value of money

Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i

Method

  1. Draw a timeline with every cash flow and its timing.
  2. Match the rate to the period: a monthly rate for monthly payments.
  3. Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
  4. Check the sign and the order of magnitude of the answer.

NPV & IRR

Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)

Method

  1. List all cash flows with their year; the investment at year 0 is negative.
  2. Discount each cash flow: CFt/(1 + r)t.
  3. Add them up to get the NPV. Positive means the project earns more than r.
  4. For the IRR, find the rate that makes NPV zero by trial or interpolation.

Normal distribution

z-score
z = (x − μ)/σ
Below x
P(X < x) = Φ(z)
Above x
P(X > x) = 1 − Φ(z)
Between
Φ(z2) − Φ(z1)
Percentile
x = μ + z·σ

Method

  1. Convert the value to a z-score: z = (x − μ)/σ.
  2. Look up Φ(z), the area to the left of z.
  3. For the area to the right use 1 − Φ(z); for an interval subtract the two left areas.
  4. For a percentile, work backwards: find z for the area, then x = μ + z·σ.

2Practice problems

1.Beam support reactionsMedium
P1​ = 30 kNP2​ = 20 kNABRA​ = ?RB​3 m1 m4 m

The simply supported beam has a pin at A and a roller at B. Find the vertical support reaction RA.

L = 8 mP1 = 30 kN at 3 mP2 = 20 kN at 4 m
RA = kN
2.Beam support reactionsHard
P = 60 kN, 45°Q = 45 kNABRA​ = ?3 m4 m3 m

The simply supported beam has a pin at A and a roller at B. A load P acts at 7 m from A, inclined at 45° to the horizontal, and a vertical load Q acts at 3 m from A. Find the magnitude of the total reaction force RA at the pin A.

L = 10 mP = 60 kN at 7 m, θ = 45°Q = 45 kN at 3 m
RA = kN
3.Truss: method of jointsMedium
ABCDEFGH15 kN10 kN35 kN4 × 4 m4 m

Exactly one member of this truss carries no force under these loads. Which is the zero-force member? Click it in the diagram.

D: 15 kN ↓G: 10 kN ↓H: 35 kN ↓
  1. 1member AB
  2. 2member BC
  3. 3member CD
  4. 4member DE
  5. 5member FG
  6. 6member GH
  7. 7member AF
  8. 8member HE
  9. 9member BF
  10. 10member CG
  11. 11member DH
  12. 12member FC
  13. 13member HC
4.Truss: method of jointsHard
ABCDEFGH25 kN10 kN20 kN4 × 4 m4 m

Exactly one member of this truss carries no force under these loads. Which is the zero-force member? Click it in the diagram.

B: 25 kN ↓D: 10 kN ↓F: 20 kN →
  1. 1member AB
  2. 2member BC
  3. 3member CD
  4. 4member DE
  5. 5member FG
  6. 6member GH
  7. 7member AF
  8. 8member HE
  9. 9member BF
  10. 10member CG
  11. 11member DH
  12. 12member BG
  13. 13member DG
5.Shear force & bending momentMedium
8 kN/m10 kNABCDEFG2 m2 m2 m2 m2 m2 m

The marks A to G split the beam into six equal parts. At which mark is the bending moment largest in size, sagging or hogging? Click it in the diagram.

10 kN @ 4 m8 kN/m, 4–10 m
  1. 1A (x = 0 m)
  2. 2B (x = 2 m)
  3. 3C (x = 4 m)
  4. 4D (x = 6 m)
  5. 5E (x = 8 m)
  6. 6F (x = 10 m)
  7. 7G (x = 12 m)
6.Shear force & bending momentHard
w = 24 kN/mAB5 m2 m1 m

The simply supported beam carries a uniformly distributed load over part of its span. Find the maximum bending moment Mmax in the beam.

L = 8 mw = 24 kN/m from 5 to 7 m
Mmax = kN·m
7.Beam deflectionMedium
P = 27 kNABδ1.5 m0.5 m

A cantilever of length L is fixed at A and carries a point load P at a distance a = 1.5 m from A. Find the deflection δP under the load.

P = 27 kNa = 1.5 mL = 2 mE = 70 GPa (aluminium)I = 57 × 10⁶ mm⁴
δP = mm
8.Beam deflectionHard
w = 15 kN/mδL = 2.5 m

A simply supported beam carries a uniformly distributed load w. Its deflection may not exceed span/360. Find the smallest second moment of area Ireq that meets this limit.

w = 15 kN/mL = 2.5 mE = 200 GPa (steel)
Ireq = × 10⁶ mm⁴
9.Column bucklingMedium
PL = 5 md = 40 mmcross-section

A column of length L made of steel is pinned at both ends. Using Euler’s formula, find its critical buckling load Pcr.

L = 5 mE = 200 GPa (steel)d = 40 mm
Pcr = kN
10.Column bucklingHard
P = 5 kNL = 4 md = ?cross-section

A solid round column of length L made of aluminium is fixed at the base and pinned at the top. It must carry 5 kN with a factor of safety of 2.5 against buckling. Find the smallest diameter d.

P = 5 kNn = 2.5L = 4 mE = 70 GPa (aluminium)
d = mm
11.Centroid & second moment of areaMedium
2201512012xdimensions in mm

Find the second moment of area Ix of the T-section about the horizontal axis x through its centroid.

bf = 220 mmtf = 15 mmtw = 12 mmhw = 120 mm
Ix = × 10⁶ mm⁴
12.Centroid & second moment of areaHard
1601018012xM = 10 kN·mdimensions in mm

The T-section is used as a beam with the flange on top and carries a sagging bending moment of 10 kN·m. Find the size of the bending stress σtop at the top edge.

bf = 160 mmtf = 10 mmtw = 12 mmhw = 180 mmM = 10 kN·m
σtop = MPa
13.Effective stress in soilMedium
sandγd​ = 15.5 kN/m³γsat​ = 20.5 kN/m³6 mwater tableXz = 5 m

For the soil profile shown, find the total vertical stress σ at point X.

z = 5 mzw = 4 mγw = 9.81 kN/m³sand: γd = 15.5 kN/m³sand: γsat = 20.5 kN/m³
σ = kPa
14.Effective stress in soilHard
sandγd​ = 16.5 kN/m³γsat​ = 20 kN/m³3 mclayγsat​ = 17 kN/m³7 mwater tableXz = 6.5 m

For the soil profile shown, find the pore water pressure u at point X.

z = 6.5 mzw = 1 mγw = 9.81 kN/m³sand: γd = 16.5 kN/m³sand: γsat = 20 kN/m³clay: γsat = 17 kN/m³
u = kPa
15.Consolidation settlementMedium
Δσ = 140 kPasandclayCc​ = 0.25, Cr​ = 0.03e0​ = 0.8σ′0​ = 70 kPaOCR = 24.5 mwater table

A 4.5 m thick overconsolidated clay layer has Cc = 0.25, Cr = 0.03 and e₀ = 0.8. At its mid-depth the effective vertical stress is 70 kPa and the overconsolidation ratio is OCR = 2. A new building adds 140 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.

H = 4.5 mCc = 0.25Cr = 0.03e0 = 0.8σ′0 = 70 kPaOCR = 2Δσ = 140 kPa
S = mm
16.Consolidation settlementHard
sandclayH = 7 mcv​ = 5 m²/year7 mimpervious rockwater table

A clay layer 7 m thick has a coefficient of consolidation cv = 5 m²/year. It lies on impervious rock, with sand above it, so water drains out only at the top. For 50% average consolidation the time factor is Tv = 0.197. How many years t does the layer take to reach 50% consolidation?

H = 7 mcv = 5 m²/yearU = 50%Tv = 0.197single drainage
t = years
17.Hydrostatic forceMedium
gated = 1.5 mH = 1 m

A vertical rectangular gate 2 m wide sits in the wall of a tank of water, with its top edge 1.5 m below the surface. Find the resultant hydrostatic force F on the gate.

d = 1.5 mH = 1 mb = 2 mρ = 1000 kg/m³g = 9.81 m/s²
F = kN
18.Hydrostatic forceHard
gated = 1.5 mH = 1 m

A vertical rectangular gate 1 m wide sits in the wall of a tank of oil, with its top edge 1.5 m below the surface. Find the depth ycp of the centre of pressure below the surface.

d = 1.5 mH = 1 mb = 1 mρ = 880 kg/m³g = 9.81 m/s²
ycp = m
19.Pipe friction & head lossMedium
Q = 30 L/sD = 150 mmL = 500 mf = 0.022

Water flows at 30 L/s through a pipe 500 m long with an inside diameter of 150 mm. Use the Darcy friction factor f = 0.022 and g = 9.81 m/s². Find the friction head loss hf.

Q = 30 L/sL = 500 mD = 150 mmf = 0.022g = 9.81 m/s²
hf = m
20.Pipe friction & head lossHard
K = 5Δz = ?L = 300 m, D = 250 mm, f = 0.0223× bend (K = 0.3)

Two open reservoirs are joined by a pipe 300 m long with an inside diameter of 250 mm and a Darcy friction factor f = 0.022. The minor losses are a square-edged entrance (K = 0.5), 3 bends (K = 0.3 each), a valve (K = 5) and the exit into the lower reservoir (K = 1.0). Use g = 9.81 m/s². What difference in water level Δz between the reservoirs gives a flow rate of 75 L/s?

Q = 75 L/sL = 300 mD = 250 mmf = 0.022Kentrance = 0.5Kbend = 0.3 (×3)Kvalve = 5Kexit = 1.0
Δz = m
21.Open-channel flow (Manning)Medium
b = 2.5 my = 2.1 m1.5 : 1n = 0.015, S = 0.0008

A trapezoidal brickwork channel has a bottom width of 2.5 m and side slopes of 1.5:1 (horizontal:vertical). Water flows uniformly 2.1 m deep. Manning n = 0.015 and the bed slope is S = 0.0008. Find the flow rate Q in m³/s.

b = 2.5 my = 2.1 mz = 1.5n = 0.015S = 0.0008
Q = m³/s
22.Open-channel flow (Manning)Hard
D = 200 mmn = 0.013, V = 0.75 m/s

A concrete sewer with an inside diameter of 200 mm (Manning n = 0.013) must reach a self-cleansing velocity of 0.75 m/s when flowing just full. Find the minimum slope S (in m/m).

D = 200 mmn = 0.013V = 0.75 m/s
S = m/m
23.Pumps & pump powerMedium
PQ = 150 L/sH = 72 m

In a test, a pump delivers 150 L/s of water (ρ = 1000 kg/m³) against a head of 72 m while its shaft takes 163 kW. Use g = 9.81 m/s². Find the pump efficiency η in percent.

Q = 150 L/sH = 72 mPshaft = 163 kWg = 9.81 m/s²
η = %
24.Pumps & pump powerHard
PQ = 40 L/sΔz = 12 mL = 100 m, D = 150 mm, f = 0.025, ΣK = 4

A pump moves 40 L/s of water (ρ = 1000 kg/m³) from an open lower reservoir to an upper tank whose water surface is 12 m higher. The pipe is 100 m long with an inside diameter of 150 mm and a Darcy friction factor f = 0.025; the minor-loss coefficients add up to ΣK = 4 (entrance and exit included). Use g = 9.81 m/s². Find the head H the pump must add.

Q = 40 L/sΔz = 12 mL = 100 mD = 150 mmf = 0.025ΣK = 4
H = m
25.Time value of moneyMedium
years0123…9PV = ?€12 000+1.5%+1.5%…r = 6.5%

A property is expected to earn net rent of €12 000 next year. The rent is expected to grow by 1.5% per year forever. The required return is 6.5% per year. Find the value PV of the property today.

C1 = €12 000g = 1.5%r = 6.5%
PV = €
26.Time value of moneyHard
years0123…20€3 000€3 000€3 000FV = ?

You deposit €3 000 at the start of every year for 20 years, the first deposit today. The account pays 3% per year. How much is in the account at the end of year 20? Find FV.

A = €3 000i = 3%n = 20
FV = €
27.NPV & IRRMedium
years0123…9−200 00010 000+4%+4%…r = 8%, NPV = ?

A project costs €200 000 today. It generates €10 000 at the end of the first year, and the cash flow then grows by 4% per year forever. The cost of capital is 8%. Find the net present value NPV.

C0 = €200 000CF1 = €10 000g = 4%r = 8%
NPV = €
28.NPV & IRRHard
years0123−40 00014 50021 00026 500

A project costs €40 000 and returns €14 500, €21 000, €26 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.

CF0 = −40 000CF1 = 14 500CF2 = 21 000CF3 = 26 500
IRR = %
29.Normal distributionMedium
−3−2−10123zshaded area between −z and z = 0.5587

Drag z so that the shaded area between −z and z under the standard normal curve is 0.5587. Find z to two decimals.

A = 0.5587
z =
30.Normal distributionHard
157164171178185192199cmtop 15%

The heights of adult men are normally distributed with mean 178 cm and standard deviation 7 cm. Drag the cut-off so the shaded top 15% is to the right of it. Find the cut-off x.

μ = 178 cmσ = 7 cm15%
x = cm

3Solutions

1.Beam support reactions

Answer: RA = 28.75 kN

Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Taking moments about one support removes that support’s reaction from the equation.

P1​ = 30 kNP2​ = 20 kNABRA​RB​3 m1 m4 m

Free-body diagram

Replace the supports with reaction forces. A roller gives one vertical reaction; with only vertical loads the pin gives one vertical reaction too.

Equilibrium

Moments about A, counter-clockwise positive. Then vertical force balance.

ΣMA = 0: RB·8 = 30·3 + 20·4
RB = 170/8 = 21.25 kN
ΣFy = 0: RA = 50 − 21.25 = 28.75 kN

Answer

RA = 28.75 kN
2.Beam support reactions

Answer: RA = 61.29 kN

Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Replace each distributed load by its resultant (its area) acting at the centroid of the load diagram, and take moments about a support to remove that support’s reaction from the equation.

Components of P

Pv = 60·sin 45° = 42.43 kN
Ph = 60·cos 45° = 42.43 kN

Reactions

ΣMA = 0: RB·10 = 42.43·7 + 45·3 → RB = 43.2 kN
Ay = 42.43 + 45 − 43.2 = 44.23 kN
Ax = Ph = 42.43 kN

Resultant at A

RA = √(42.43² + 44.23²) = 61.29 kN

Answer

RA = 61.29 kN
3.Truss: method of joints

Answer: member BF

Zero-force members: at a joint, the forces must balance in every direction. If a joint has no load and no support, and two of its three members are in line, then the balance across that line involves only the third member, so its force is zero. If only two members meet at an unloaded joint and they are not in line, both are zero.

Joint B

AB and BC lie on one straight line and the joint carries no load. Balancing forces across that line leaves only BF.

ΣF⊥ = 0 → FBF = 0

Check with the method of joints

Solving all joints gives these member forces (T = tension, C = compression).

AB: 17.5 kN (T), BC: 17.5 kN (T), CD: 42.5 kN (T), DE: 42.5 kN (T), FG: 35 kN (C), GH: 35 kN (C), AF: 24.75 kN (C), HE: 60.1 kN (C), BF: 0, CG: 10 kN (C), DH: 15 kN (T), FC: 24.75 kN (T), HC: 10.61 kN (C)

Answer

Zero-force member: BF
4.Truss: method of joints

Answer: member CG

Zero-force members: at a joint, the forces must balance in every direction. If a joint has no load and no support, and two of its three members are in line, then the balance across that line involves only the third member, so its force is zero. If only two members meet at an unloaded joint and they are not in line, both are zero.

Joint C

BC and CD lie on one straight line and the joint carries no load. Balancing forces across that line leaves only CG.

ΣF⊥ = 0 → FCG = 0

Check with the method of joints

Solving all joints gives these member forces (T = tension, C = compression).

AB: 36.25 kN (T), BC: 27.5 kN (T), CD: 27.5 kN (T), DE: 18.75 kN (T), FG: 36.25 kN (C), GH: 18.75 kN (C), AF: 22.98 kN (C), HE: 26.52 kN (C), BF: 16.25 kN (T), CG: 0, DH: 18.75 kN (T), BG: 12.37 kN (T), DG: 12.37 kN (C)

Answer

Zero-force member: CG
5.Shear force & bending moment

Answer: D (x = 6 m)

Largest bending moment: M changes slope wherever the shear force changes, so its peaks sit where the shear force crosses zero: under a point load, inside a distributed load, or over a support of an overhang. At a fixed support of a cantilever the moment is largest at the wall. Compare the size of M at those places, sagging or hogging.

Support reactions

Take moments about one support, then use the vertical force balance.

R1 = 26.67 kN, R2 = 31.33 kN

Bending moment at every mark

Sum the moments of all forces on one side of the cut. Sagging is positive, hogging negative.

MA = 0, MB = 53.33, MC = 106.7, MD = 124 kN·m, ME = 109.3, MF = 62.67, MG = 0

Answer

Mark D: MD = 124 kN·m
6.Shear force & bending moment

Answer: Mmax = 63 kN·m

Method of sections: cut the beam where you want the internal forces and keep one side. The shear force V balances the vertical forces on that side, and the bending moment M balances their moments about the cut. Maximum moment: since dM/dx = V, the bending moment has its peak where the shear force passes through zero, either at a point load or inside a distributed load.

Support reactions

Equilibrium of the whole beam.

UDL resultant: W = w·ℓ = 24·2 = 48 kN, acting at x̄ = 6 m
ΣMA = 0: RB·8 = 24·2·6
RB = 288/8 = 36 kN
ΣFy = 0: RA = 48 − 36 = 12 kN

Zero shear

The shear force starts at RA, stays constant over any unloaded part and falls with slope w inside the load.

RA − w·(x0 − 5) = 0
x0 = 5 + 12/24 = 5.5 m

Maximum moment

Mmax = RA·x0 − w·(x0 − 5)²/2 = 12·5.5 − 24·0.5²/2 = 63 kN·m

Answer

Mmax = 63 kN·m
7.Beam deflection

Answer: δP = 7.613 mm

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).

Consistent units

Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.

P = 27000 N, a = 1500 mm, L = 2000 mm
EI = 3.99 × 10¹² N·mm²

Deflection under the load

δP = Pa³/(3EI) = 27000·1500³/(3·3.99 × 10¹²) = 7.613 mm

Answer

δP = 7.613 mm
8.Beam deflection

Answer: Ireq = 5.493 × 10⁶ mm⁴

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).

Deflection limit

δallow = L/360 = 2500/360 = 6.944 mm

Required second moment of area

I = 5wL⁴/(384·E·δallow) = 5·15·2500⁴/(384·200000·6.944) = 5.493 × 10⁶ mm⁴
Ireq = 5.493 × 10⁶ mm⁴

Answer

Ireq = 5.493 × 10⁶ mm⁴
9.Column buckling

Answer: Pcr = 9.922 kN

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Smallest second moment of area

A round section has the same I about every axis.

I = πd⁴/64 = π·40⁴/64 = 125664 mm⁴

Effective length

KL = 1·5000 = 5000 mm

Critical load

Pcr = π²EI/(KL)² = π²·200000·125664/5000² = 9922 N = 9.922 kN

Answer

Pcr = 9.922 kN
10.Column buckling

Answer: d = 41.23 mm

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Required critical load

Pcr = n·P = 2.5·5000 = 12500 N
KL = 0.7·4000 = 2800 mm

Solve for the diameter

d = (64·n·P·(KL)²/(π³E))^(1/4) = (64·12500·2800²/(π³·70000))^(1/4) = 41.23 mm

Answer

d = 41.23 mm

Check: the slenderness KL/r is 271.6, so the column is slender and Euler applies.

11.Centroid & second moment of area

Answer: Ix = 6.358 × 10⁶ mm⁴

Composite areas: split the section into rectangles. The centroid is the area-weighted average ȳ = ΣAᵢyᵢ/ΣAᵢ. The second moment of area about the centroidal axis adds each part’s own bh³/12 and its parallel-axis term A·d², where d is the distance from the part’s centroid to the overall centroid. Bending stress is σ = M·y/I.

Split into two rectangles

Measure every y from the bottom edge.

flange: Af = 220·15 = 3300 mm², yf = 120 + 15/2 = 127.5 mm
web: Aw = 12·120 = 1440 mm², yw = 120/2 = 60 mm

Centroid

ȳ = (Afyf + Awyw)/(Af + Aw) = (3300·127.5 + 1440·60)/4740 = 107 mm

Parallel-axis theorem

flange: 220·15³/12 + 3300·(127.5 − 107)² = 1.45 × 10⁶ mm⁴
web: 12·120³/12 + 1440·(60 − 107)² = 4.908 × 10⁶ mm⁴
Ix = 1.45 × 10⁶ + 4.908 × 10⁶ = 6.358 × 10⁶ mm⁴ = 6.358 × 10⁶ mm⁴

Answer

Ix = 6.358 × 10⁶ mm⁴
12.Centroid & second moment of area

Answer: σtop = 42.13 MPa

Composite areas: split the section into rectangles. The centroid is the area-weighted average ȳ = ΣAᵢyᵢ/ΣAᵢ. The second moment of area about the centroidal axis adds each part’s own bh³/12 and its parallel-axis term A·d², where d is the distance from the part’s centroid to the overall centroid. Bending stress is σ = M·y/I.

Split into two rectangles

Measure every y from the bottom edge.

flange: Af = 160·10 = 1600 mm², yf = 180 + 10/2 = 185 mm
web: Aw = 12·180 = 2160 mm², yw = 180/2 = 90 mm

Centroid

ȳ = (Afyf + Awyw)/(Af + Aw) = (1600·185 + 2160·90)/3760 = 130.4 mm

Parallel-axis theorem

flange: 160·10³/12 + 1600·(185 − 130.4)² = 4.779 × 10⁶ mm⁴
web: 12·180³/12 + 2160·(90 − 130.4)² = 9.362 × 10⁶ mm⁴
Ix = 4.779 × 10⁶ + 9.362 × 10⁶ = 1.414 × 10⁷ mm⁴

Bending stress

The top edge is h − ȳ from the axis.

y = 190 − 130.4 = 59.57 mm
σ = M·y/I = 1 × 10⁷·59.57/1.414 × 10⁷ = 42.13 MPa

Answer

σtop = 42.13 MPa
13.Effective stress in soil

Answer: σ = 82.5 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Total stress

Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.

σ = γd·zw + γsat·(z − zw) = 15.5·4 + 20.5·1 = 82.5 kPa

Answer

σ = 82.5 kPa
14.Effective stress in soil

Answer: u = 53.96 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Pore water pressure

Water pressure grows with depth below the water table.

u = γw·(z − zw) = 9.81·5.5 = 53.96 kPa

Answer

u = 53.96 kPa
15.Consolidation settlement

Answer: S = 132.6 mm

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Preconsolidation pressure

σ′p = OCR·σ′0 = 2·70 = 140 kPa

Compare with the preconsolidation pressure

σ′f = 70 + 140 = 210 kPa > 140 kPa

Settlement

Recompression up to σ′p, virgin compression beyond it.

S = 0.03·4.5/(1 + 0.8)·log₁₀(140/70) + 0.25·4.5/(1 + 0.8)·log₁₀(210/140)
S = 22.58 + 110.1 = 132.6 mm

Answer

S = 132.6 mm
16.Consolidation settlement

Answer: t = 1.931 years

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Drainage path

Hdr = H = 7 m

Time

t = Tv·Hdr²/cv = 0.197·7²/5 = 1.931 years

Answer

t = 1.931 years
17.Hydrostatic force

Answer: F = 39.24 kN

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 1.5 + 1/2 = 2 m
A = H·b = 1·2 = 2 m²
gated = 1.5 mH = 1 mF

Resultant force

F = ρ·g·yc·A = 1000·9.81·2·2 = 39.24 kN

Answer

F = 39.24 kN
18.Hydrostatic force

Answer: ycp = 2.042 m

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 1.5 + 1/2 = 2 m
A = H·b = 1·1 = 1 m²
gated = 1.5 mH = 1 mF

Resultant force

F = ρ·g·yc·A = 880·9.81·2·1 = 17.27 kN

Centre of pressure

Pressure grows with depth, so the resultant acts below the centroid.

Ic = b·H³/12 = 1·1³/12 = 0.08333 m⁴
ycp = yc + Ic/(yc·A) = 2 + 0.08333/(2·1) = 2.042 m

Answer

ycp = 2.042 m
19.Pipe friction & head loss

Answer: hf = 10.77 m

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Mean velocity

A = π·0.15²/4 = 0.01767 m²
V = Q/A = 0.03/0.01767 = 1.698 m/s

Velocity head

V²/(2g) = 1.698²/(2·9.81) = 0.1469 m

Darcy–Weisbach

hf = f·(L/D)·V²/(2g) = 0.022·(500/0.15)·1.698²/(2·9.81) = 10.77 m

Answer

hf = 10.77 m
20.Pipe friction & head loss

Answer: Δz = 4.022 m

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Velocity

V = Q/A = 0.075/0.04909 = 1.528 m/s
V²/(2g) = 0.119 m

Loss coefficients

f·L/D = 0.022·300/0.25 = 26.4
ΣK = 0.5 + 3·0.3 + 5 + 1.0 = 7.4

Total head loss

hf = 26.4·0.119 = 3.141 m
hm = 7.4·0.119 = 0.8805 m
Δz = hf + hm = 4.022 m

Answer

Δz = 4.022 m
21.Open-channel flow (Manning)

Answer: Q = 24.96 m³/s

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Geometry

A = (b + z·y)·y = (2.5 + 1.5·2.1)·2.1 = 11.87 m²
P = b + 2y·√(1 + z²) = 2.5 + 2·2.1·√(1 + 1.5²) = 10.07 m
R = A/P = 1.178 m

Velocity

V = (1/0.015)·1.1782/3·0.00081/2 = 2.103 m/s

Flow rate

Q = A·V = 11.87·2.103 = 24.96 m³/s

Answer

Q = 24.96 m³/s
22.Open-channel flow (Manning)

Answer: S = 0.005161 m/m

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Hydraulic radius

R = D/4 = 0.2/4 = 0.05 m

Solve Manning for S

S = (n·V/R2/3)² = (0.013·0.75/0.1357)² = 0.005161

Answer

S = 0.005161

That is a fall of 5.161 m per kilometre.

23.Pumps & pump power

Answer: η = 65 %

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Hydraulic power

Ph = ρ·g·Q·H = 1000·9.81·0.15·72 = 105.9 kW

Efficiency

η = Ph/Pshaft = 105.9/163 = 65%

Answer

η = 65%
24.Pumps & pump power

Answer: H = 17.4 m

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Velocity

V = Q/A = 0.04/0.01767 = 2.264 m/s
V²/(2g) = 0.2611 m

Head losses

hL = (f·L/D + ΣK)·V²/(2g) = (16.67 + 4)·0.2611 = 5.397 m

Pump head

Both surfaces are open and practically at rest, so pressure and velocity terms drop out.

H = Δz + hL = 12 + 5.397 = 17.4 m

Answer

H = 17.4 m
25.Time value of money

Answer: PV = 240000 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Growing perpetuity

PV = C1/(r − g) = 12 000/(0.065 − 0.015) = 12 000/0.05 = €240 000.00

Answer

PV = €240 000.00
26.Time value of money

Answer: FV = 83029 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Ordinary annuity factor

((1 + 0.03)20 − 1)/0.03 = 26.87

Annuity due

Each deposit is invested one year longer.

FV = 3 000·26.87·1.03 = €83 029.46

Answer

FV = €83 029.46
27.NPV & IRR

Answer: NPV = 50000 €

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Value of the cash flows

PV = 10 000/(0.08 − 0.04) = 250 000.00

NPV

NPV = 250 000.00 − 200 000 = €50 000.00

Answer

NPV = €50 000.00

NPV is positive, so the project earns more than the required return.

28.NPV & IRR

Answer: IRR = 22.87 %

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Bracket the IRR

NPV falls as the rate rises, so the IRR lies between a rate with positive NPV and one with negative NPV.

NPV(20%) = 2 002.31
NPV(25%) = −1 392.00

Narrow down

Linear interpolation gives a first estimate; repeating it (or a calculator's IRR function) gives the exact rate.

IRR ≈ 20 + 5·2 002.31/(2 002.31 − (−1 392.00)) = 22.95%
exact: NPV(22.87%) = 0 → IRR = 22.87%

Answer

IRR = 22.87%
29.Normal distribution

Answer: z = 0.77

From an area back to z: Φ(z) is the area to the left of z. For a left-tail area A, find z with Φ(z) = A in the table. A right-tail area A means Φ(z) = 1 − A. A central area A between −z and z leaves (1 − A)/2 in each tail, so Φ(z) = (1 + A)/2. For a value x, use x = μ + zσ.

Area to the left of z

Φ(z) = (1 + 0.5587)/2 = 0.7794

Read the z-table backwards

Find 0.7794 inside the table and read off z.

z = 0.77

Answer

z = 0.77
30.Normal distribution

Answer: x = 185.3 cm

From an area back to z: Φ(z) is the area to the left of z. For a left-tail area A, find z with Φ(z) = A in the table. A right-tail area A means Φ(z) = 1 − A. A central area A between −z and z leaves (1 − A)/2 in each tail, so Φ(z) = (1 + A)/2. For a value x, use x = μ + zσ.

Area to the left

Φ(z) = 0.85

z from the table

z ≈ 1.04

Back to the original units

x = 178 + 1.04·7 = 185.3 cm

Answer

x = 185.3 cm