FE Civil exam practice: cram pack

Formula sheets, the key method steps for every topic and 30 practice problems, with full solutions at the back.

New problemsBack to the course

In the print window, choose “Save as PDF” to keep a copy on your device.

1Formulas and methods

Beam support reactions

Equilibrium
ΣFx = 0, ΣFy = 0, ΣM = 0
Uniform load
resultant w·L at the middle of the load
Moment
M = F·d

Method

  1. Draw a free-body diagram and replace each support by its reactions.
  2. Replace every distributed load by a single force at its centroid.
  3. Take moments about one support to find the reaction at the other.
  4. Use ΣFy = 0 to find the remaining reaction, and check with a second moment equation.

Truss: method of joints

Method of joints
ΣFx = 0, ΣFy = 0 at each joint
Method of sections
ΣM = 0 about a cut point
Member force
positive = tension, negative = compression

Method

  1. Find the support reactions for the whole truss.
  2. Method of joints: start at a joint with at most two unknown member forces and use ΣFx = 0 and ΣFy = 0.
  3. Method of sections: cut through the member you need and take moments about a point where the other unknown members meet.
  4. Assume tension; a negative answer means compression.

Shear force & bending moment

Shear and moment
V = ΣF on one side, M = ΣF·d on one side
Bending stress
σ = M·y/I
Rectangle
I = bh³/12
Section modulus
W = I/ymax
Simply supported, uniform load
Mmax = wL²/8

Method

  1. Find the support reactions from equilibrium of the whole beam.
  2. Cut the beam at the section you need and keep one side.
  3. Shear force: sum of the vertical forces on that side. Bending moment: sum of their moments about the cut.
  4. For the maximum moment, find where the shear force is zero.

Beam deflection

Point load at midspan
δ = PL³/(48EI)
Uniform load, simply supported
δ = 5wL⁴/(384EI)
Cantilever, end load
δ = PL³/(3EI)
Cantilever, uniform load
δ = wL⁴/(8EI)
Superposition
δ = δ1 + δ2

Column buckling

Euler load
Pcr = π²EI/(KL)²
Effective length factor
K = 1 pinned–pinned, 0.5 fixed–fixed, 0.7 fixed–pinned, 2 fixed–free
Critical stress
σcr = Pcr/A
Slenderness
λ = KL/r, r = √(I/A)

Centroid & second moment of area

Centroid
ȳ = ΣAiyi/ΣAi
Rectangle
I = bh³/12
Parallel-axis theorem
I = Ic + A·d²
Composite section
I = Σ(Ic,i + Aidi²)

Effective stress in soil

Total stress
σ = Σγi·hi
Pore water pressure
u = γw·(z − zw)
Effective stress
σ′ = σ − u
Water
γw = 9.81 kN/m³

Consolidation settlement

Normally consolidated
S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0)
Final stress
σ′f = σ′0 + Δσ (at mid-depth of the layer)
Overconsolidated, σ′f ≤ σ′p
S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0)
Overconsolidated, σ′f > σ′p
S = H/(1 + e0)·[Cr·log₁₀(σ′p/σ′0) + Cc·log₁₀(σ′f/σ′p)]
Overconsolidation ratio
OCR = σ′p/σ′0
Time for consolidation
t = Tv·Hdr²/cv
Drainage path
Hdr = H/2 (double drainage), H (single drainage)
Time factors
U 50% → 0.197, 60% → 0.287, 70% → 0.403, 80% → 0.567, 90% → 0.848

Hydrostatic force

Pressure at depth
p = ρgh
Force on a vertical wall
F = ρg·hc·A
Centre of pressure
yp = yc + Ic/(ycA)
Rectangle
Ic = bH³/12

Pipe friction & head loss

Reynolds number
Re = V·D/ν = ρ·V·D/μ
Flow regime
laminar below Re ≈ 2000, turbulent above Re ≈ 4000
Mean velocity
V = Q/A, A = π·D²/4
Darcy–Weisbach
hf = f·(L/D)·V²/(2g)
Minor losses
hm = ΣK·V²/(2g)
Typical K values
entrance 0.5, exit 1.0, 90° bend ≈ 0.3
Pressure drop
Δp = ρ·g·hf
Two open reservoirs
Δz = (f·L/D + ΣK)·V²/(2g)
Free outlet
H = (1 + f·L/D + ΣK)·V²/(2g)

Open-channel flow (Manning)

Manning equation
V = (1/n)·R2/3·S1/2
Flow rate
Q = A·V
Hydraulic radius
R = A/P (P = wetted perimeter, free surface excluded)
Rectangle
A = b·y, P = b + 2y
Trapezoid (side slope z:1)
A = (b + z·y)·y, P = b + 2y·√(1 + z²)
Circular pipe, full or half full
R = D/4
Required slope
S = (n·Q/(A·R2/3))²

Pumps & pump power

Hydraulic power
Ph = ρ·g·Q·H = Q·Δp
Shaft power
Pshaft = Ph/ηpump
Electrical power
Pel = Pshaft/ηmotor
Pump head
H = Δz + Δp/(ρ·g) + hL
System losses
hL = (f·L/D + ΣK)·V²/(2g)

Time value of money

Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i

Method

  1. Draw a timeline with every cash flow and its timing.
  2. Match the rate to the period: a monthly rate for monthly payments.
  3. Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
  4. Check the sign and the order of magnitude of the answer.

NPV & IRR

Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)

Method

  1. List all cash flows with their year; the investment at year 0 is negative.
  2. Discount each cash flow: CFt/(1 + r)t.
  3. Add them up to get the NPV. Positive means the project earns more than r.
  4. For the IRR, find the rate that makes NPV zero by trial or interpolation.

Normal distribution

z-score
z = (x − μ)/σ
Below x
P(X < x) = Φ(z)
Above x
P(X > x) = 1 − Φ(z)
Between
Φ(z2) − Φ(z1)
Percentile
x = μ + z·σ

Method

  1. Convert the value to a z-score: z = (x − μ)/σ.
  2. Look up Φ(z), the area to the left of z.
  3. For the area to the right use 1 − Φ(z); for an interval subtract the two left areas.
  4. For a percentile, work backwards: find z for the area, then x = μ + z·σ.

2Practice problems

1.Beam support reactionsMedium
P1​ = 50 kNP2​ = 80 kNABCRB​ = ?0.5 m3 m1.5 m

The beam has a pin at A and a roller at B, 3.5 m from A, and overhangs B to the free end C. Find the vertical reaction RB, taking upward as positive.

AB = 3.5 mAC = 5 mP1 = 50 kN at 0.5 mP2 = 80 kN at 5 m
RB = kN
2.Beam support reactionsHard
w = 12 kN/mP = 15 kNABRA​RB​ = ?2 m2 m2 m

The simply supported beam has a pin at A and a roller at B. Find the vertical support reaction RB.

L = 6 mP = 15 kN at 4 mw = 12 kN/m from 0 to 2 m
RB = kN
3.Truss: method of jointsMedium
ABBCACACB10 kN5 m2 m3 m

Use the method of joints to find the force FAB in member AB. Give tension as positive and compression as negative.

span = 5 mheight = 3 mB is 2 m from Avertical load = 10 kN
FAB = kN
4.Truss: method of jointsHard
ABCDEFGH25 kN15 kN30 kN30 kN4 × 3 m4 m

Exactly one member of this truss carries no force under these loads. Which is the zero-force member? Click it in the diagram.

D: 25 kN ↓F: 15 kN ↓H: 30 kN ↓H: 30 kN ←
  1. 1member AB
  2. 2member BC
  3. 3member CD
  4. 4member DE
  5. 5member FG
  6. 6member GH
  7. 7member AF
  8. 8member HE
  9. 9member BF
  10. 10member CG
  11. 11member DH
  12. 12member BG
  13. 13member DG
5.Shear force & bending momentMedium
M0​ = 35 kN·mAB1.5 m2.5 m

The simply supported beam carries a clockwise couple M0 = 35 kN·m at x = 1.5 m from A, and no other load. Find the bending moment Mx just to the right of the couple. Use sagging moments positive and upward shear on the left face positive.

L = 4 mM0 = 35 kN·m clockwise, at 1.5 m
Mx = kN·m
6.Shear force & bending momentHard
w = 4 kN/mAB3 m5 m

The simply supported beam carries a uniformly distributed load over part of its span. Find the maximum bending moment Mmax in the beam.

L = 8 mw = 4 kN/m from 0 to 3 m
Mmax = kN·m
7.Beam deflectionMedium
w = 20 kN/mABθ5 m

A simply supported beam carries a uniformly distributed load w over its whole span. Find the slope θA of the beam at support A, in radians.

w = 20 kN/mL = 5 mE = 70 GPa (aluminium)I = 84 × 10⁶ mm⁴
θA = rad
8.Beam deflectionHard
w = 4 kN/mABδ6 m

A simply supported timber beam of rectangular section, 150 mm wide, carries a uniformly distributed load w over its whole span. Its midspan deflection may not exceed span/360. Find the smallest depth hreq of the section.

w = 4 kN/mL = 6 mE = 11 GPa (timber)b = 150 mm
hreq = mm
9.Column bucklingMedium
PL = 1 md = 20 mmcross-section

A column of length L made of aluminium is pinned at both ends. Using Euler’s formula, find its critical buckling load Pcr.

L = 1 mE = 70 GPa (aluminium)d = 20 mm
Pcr = kN
10.Column bucklingHard
P = 65 kNL = 1.5 md = ?cross-section

A solid round column of length L made of steel is fixed at the base and pinned at the top. It must carry 65 kN with a factor of safety of 2.5 against buckling. Find the smallest diameter d.

P = 65 kNn = 2.5L = 1.5 mE = 200 GPa (steel)
d = mm
11.Centroid & second moment of areaMedium
150 mm150 mm97.5 mmØ30xIx​ = ?

A 150 mm × 150 mm plate has a circular hole of diameter 30 mm on its vertical centre line, with its centre 97.5 mm above the bottom. Find the second moment of area Ix about the horizontal axis through the centroid.

b = 150 mmh = 150 mmd = 30 mmhole centre: y = 97.5 mm
Ix = × 10⁶ mm⁴
12.Centroid & second moment of areaHard
120 mm150 mm52.5 mm80 × 20xIx​ = ?

A 120 mm × 150 mm plate has a rectangular cut-out 80 mm wide and 20 mm high, centred on the vertical centre line with its centre 52.5 mm above the bottom. Find the second moment of area Ix about the horizontal axis through the centroid.

b = 120 mmh = 150 mmcut-out: 80 × 20 mmhole centre: y = 52.5 mm
Ix = × 10⁶ mm⁴
13.Effective stress in soilMedium
sandγd​ = 15 kN/m³γsat​ = 19.5 kN/m³10 mwater tableXz = 5 m

For the soil profile shown, find the vertical effective stress σ′ at point X.

z = 5 mzw = 1 mγw = 9.81 kN/m³sand: γd = 15 kN/m³sand: γsat = 19.5 kN/m³
σ′ = kPa
14.Effective stress in soilHard
sandγd​ = 15 kN/m³γsat​ = 19 kN/m³3 mclayγsat​ = 17 kN/m³6 mwater tableXz = 6 m

For the soil profile shown, find the pore water pressure u at point X.

z = 6 mzw = 1 mγw = 9.81 kN/m³sand: γd = 15 kN/m³sand: γsat = 19 kN/m³clay: γsat = 17 kN/m³
u = kPa
15.Consolidation settlementMedium
Δσ = 50 kPasandclayCc​ = 0.25, Cr​ = 0.02e0​ = 0.7σ′0​ = 45 kPaOCR = 1.54 mwater table

A 4 m thick overconsolidated clay layer has Cc = 0.25, Cr = 0.02 and e₀ = 0.7. At its mid-depth the effective vertical stress is 45 kPa and the overconsolidation ratio is OCR = 1.5. A new building adds 50 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.

H = 4 mCc = 0.25Cr = 0.02e0 = 0.7σ′0 = 45 kPaOCR = 1.5Δσ = 50 kPa
S = mm
16.Consolidation settlementHard
sandclayH = 6.5 mcv​ = 1.5 m²/year6.5 mimpervious rockwater table

A clay layer 6.5 m thick has a coefficient of consolidation cv = 1.5 m²/year. It lies on impervious rock, with sand above it, so water drains out only at the top. For 90% average consolidation the time factor is Tv = 0.848. How many years t does the layer take to reach 90% consolidation?

H = 6.5 mcv = 1.5 m²/yearU = 90%Tv = 0.848single drainage
t = years
17.Hydrostatic forceMedium
gated = 0.5 mH = 1.5 m

A vertical rectangular gate 2 m wide sits in the wall of a tank of water, with its top edge 0.5 m below the surface. Find the resultant hydrostatic force F on the gate.

d = 0.5 mH = 1.5 mb = 2 mρ = 1000 kg/m³g = 9.81 m/s²
F = kN
18.Hydrostatic forceHard
gated = 1 mH = 3 m

A vertical rectangular gate 3 m wide sits in the wall of a tank of glycerin, with its top edge 1 m below the surface. Find the depth ycp of the centre of pressure below the surface.

d = 1 mH = 3 mb = 3 mρ = 1260 kg/m³g = 9.81 m/s²
ycp = m
19.Pipe friction & head lossMedium
Q = 4 L/sD = 75 mmL = 500 mf = 0.028

Water flows at 4 L/s through a pipe 500 m long with an inside diameter of 75 mm. Use the Darcy friction factor f = 0.028 and g = 9.81 m/s². Find the friction head loss hf.

Q = 4 L/sL = 500 mD = 75 mmf = 0.028g = 9.81 m/s²
hf = m
20.Pipe friction & head lossHard
K = 2Δz = 12 mL = 150 m, D = 200 mm, f = 0.0224× bend (K = 0.3)

Two open reservoirs are joined by a pipe 150 m long with an inside diameter of 200 mm and a Darcy friction factor f = 0.022. The water surface of the upper reservoir is 12 m above that of the lower one. The minor losses are a square-edged entrance (K = 0.5), 4 bends (K = 0.3 each), a valve (K = 2) and the exit into the lower reservoir (K = 1.0). Use g = 9.81 m/s². Find the flow rate Q in L/s.

Δz = 12 mL = 150 mD = 200 mmf = 0.022Kentrance = 0.5Kbend = 0.3 (×4)Kvalve = 2Kexit = 1.0
Q = L/s
21.Open-channel flow (Manning)Medium
b = 2.5 my = 0.8 m3 : 1n = 0.025, S = 0.005

A trapezoidal gravel channel has a bottom width of 2.5 m and side slopes of 3:1 (horizontal:vertical). Water flows uniformly 0.8 m deep. Manning n = 0.025 and the bed slope is S = 0.005. Find the flow rate Q in m³/s.

b = 2.5 my = 0.8 mz = 3n = 0.025S = 0.005
Q = m³/s
22.Open-channel flow (Manning)Hard
b = 3.5 my = 2.3 m1 : 1n = 0.025, Q = 14 m³/s

A trapezoidal gravel channel with a bottom width of 3.5 m and side slopes of 1:1 (horizontal:vertical) must carry 14 m³/s in uniform flow at a depth of 2.3 m. Manning n = 0.025. Find the required bed slope S (in m/m).

Q = 14 m³/sb = 3.5 my = 2.3 mz = 1n = 0.025
S = m/m
23.Pumps & pump powerMedium
PQ = 25 L/sH = 28 m

In a test, a pump delivers 25 L/s of water (ρ = 1000 kg/m³) against a head of 28 m while its shaft takes 8.4 kW. Use g = 9.81 m/s². Find the pump efficiency η in percent.

Q = 25 L/sH = 28 mPshaft = 8.4 kWg = 9.81 m/s²
η = %
24.Pumps & pump powerHard
PQ = 75 L/sΔz = 17 mL = 200 m, D = 200 mm, f = 0.018, ΣK = 8

A pump moves 75 L/s of water (ρ = 1000 kg/m³) from an open lower reservoir to an upper tank whose water surface is 17 m higher. The pipe is 200 m long with an inside diameter of 200 mm and a Darcy friction factor f = 0.018; the minor-loss coefficients add up to ΣK = 8 (entrance and exit included). Use g = 9.81 m/s². Find the head H the pump must add.

Q = 75 L/sΔz = 17 mL = 200 mD = 200 mmf = 0.018ΣK = 8
H = m
25.Time value of moneyMedium
years0123…9PV = ?€2 000+1.5%+1.5%…r = 7.5%

A property is expected to earn net rent of €2 000 next year. The rent is expected to grow by 1.5% per year forever. The required return is 7.5% per year. Find the value PV of the property today.

C1 = €2 000g = 1.5%r = 7.5%
PV = €
26.Time value of moneyHard
years0123…13€1 000€1 000€1 000FV = ?

You deposit €1 000 at the start of every year for 13 years, the first deposit today. The account pays 8% per year. How much is in the account at the end of year 13? Find FV.

A = €1 000i = 8%n = 13
FV = €
27.NPV & IRRMedium
years0123456−40 00017 00016 00016 5008 00013 00010 500

A project costs €40 000 today and returns €17 000, €16 000, €16 500, €8 000, €13 000, €10 500 at the end of years 1 to 6. The cost of capital is 10%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.

r = 10%CF0 = −40 000CF1 = 17 000CF2 = 16 000CF3 = 16 500CF4 = 8 000CF5 = 13 000CF6 = 10 500
DPB = years
28.NPV & IRRHard
years0123−20 00012 5008 50013 500

A project costs €20 000 and returns €12 500, €8 500, €13 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.

CF0 = −20 000CF1 = 12 500CF2 = 8 500CF3 = 13 500
IRR = %
29.Normal distributionMedium
225 kg223.5 kgT = X₁ + … + X₉?

The masses of bags of cement are independent and normal with mean 25 kg and standard deviation 0.5 kg. Find the probability P that the total mass of 9 of them is below 223.5 kg. Round z to two decimals.

μ = 25 kgσ = 0.5 kgn = 9< 223.5 kg
P =
30.Normal distributionHard
4 s0X − Y?

Runner A's lap time X and runner B's lap time Y are independent and normal: X has mean 52 s and standard deviation 4 s, Y has mean 48 s and standard deviation 3 s. Find the probability P that X is greater than Y. Round z to two decimals.

μX = 52 s, σX = 4 sμY = 48 s, σY = 3 s
P =

3Solutions

1.Beam support reactions

Answer: RB = 121.4 kN

Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Replace each distributed load by its resultant (its area) acting at the centroid of the load diagram, and take moments about a support to remove that support’s reaction from the equation.

Moments about A

Counter-clockwise positive.

ΣMA = 0: RB·3.5 = 50·0.5 + 80·5
RB = 425/3.5 = 121.4 kN

Vertical equilibrium

RA = 50 + 80 − 121.4 = 8.571 kN

Answer

RB = 121.4 kN
2.Beam support reactions

Answer: RB = 14 kN

Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Taking moments about one support removes that support’s reaction from the equation.

w = 12 kN/mP = 15 kNABRA​RB​2 m2 m2 m

Free-body diagram

Replace the supports with reaction forces. A roller gives one vertical reaction; with only vertical loads the pin gives one vertical reaction too.

Equilibrium

Moments about A, counter-clockwise positive. Then vertical force balance.

UDL resultant: W = w·ℓ = 12·2 = 24 kN, acting at x̄ = 1 m
ΣMA = 0: RB·6 = 15·4 + 12·2·1
RB = 84/6 = 14 kN
ΣFy = 0: RA = 39 − 14 = 25 kN

Answer

RB = 14 kN
3.Truss: method of joints

Answer: FAB = −7.211 kN

Method of joints: every pin of a truss is in equilibrium, so ΣFx = 0 and ΣFy = 0 at each joint. Start at a joint with at most two unknown member forces. A negative result means the member is in compression.

ABBCACACB10 kNAy​Cy​

Support reactions

Equilibrium of the whole truss. Moments about A, counter-clockwise positive.

ΣMA = 0: Cy·5 = 10·2 → Cy = 4 kN
ΣFy = 0: Ay = 10 − 4 = 6 kN

Joint A

Assume every member is in tension (pulling away from the joint). Only AB has a vertical component at A.

sin α = 3/3.606 = 0.8321
ΣFy = 0: Ay + FAB·sin α = 0
FAB = −6/0.8321 = −7.211 kN

Answer

FAB = −7.211 kN (compression)
4.Truss: method of joints

Answer: member CG

Zero-force members: at a joint, the forces must balance in every direction. If a joint has no load and no support, and two of its three members are in line, then the balance across that line involves only the third member, so its force is zero. If only two members meet at an unloaded joint and they are not in line, both are zero.

Joint C

BC and CD lie on one straight line and the joint carries no load. Balancing forces across that line leaves only CG.

ΣF⊥ = 0 → FCG = 0

Check with the method of joints

Solving all joints gives these member forces (T = tension, C = compression).

AB: 3.75 kN (C), BC: 11.25 kN (T), CD: 11.25 kN (T), DE: 26.25 kN (T), FG: 26.25 kN (C), GH: 56.25 kN (C), AF: 43.75 kN (C), HE: 43.75 kN (C), BF: 20 kN (T), CG: 0, DH: 5 kN (T), BG: 25 kN (C), DG: 25 kN (T)

Answer

Zero-force member: CG
5.Shear force & bending moment

Answer: Mx = 21.88 kN·m

Method of sections: cut the beam where you want the internal forces and keep one side. The shear force V balances the vertical forces on that side, and the bending moment M balances their moments about the cut. An applied couple makes the bending moment diagram jump by the size of the couple.

Support reactions

Moments about A, counter-clockwise positive: RB·L − M0 = 0. Vertical balance: RA + RB = 0.

RB = M0/L = 35/4 = 8.75 kN (upward)
RA = −RB = −8.75 kN (downward)

Cut just right of the couple

The left part now contains RA and the couple.

Mx = RA·a + M0 = −8.75·1.5 + 35 = 21.88 kN·m

Answer

Mx = 21.88 kN·m
6.Shear force & bending moment

Answer: Mmax = 11.88 kN·m

Method of sections: cut the beam where you want the internal forces and keep one side. The shear force V balances the vertical forces on that side, and the bending moment M balances their moments about the cut. Maximum moment: since dM/dx = V, the bending moment has its peak where the shear force passes through zero, either at a point load or inside a distributed load.

Support reactions

Equilibrium of the whole beam.

UDL resultant: W = w·ℓ = 4·3 = 12 kN, acting at x̄ = 1.5 m
ΣMA = 0: RB·8 = 4·3·1.5
RB = 18/8 = 2.25 kN
ΣFy = 0: RA = 12 − 2.25 = 9.75 kN

Zero shear

The shear force starts at RA, stays constant over any unloaded part and falls with slope w inside the load.

RA − w·(x0 − 0) = 0
x0 = 0 + 9.75/4 = 2.438 m

Maximum moment

Mmax = RA·x0 − w·(x0 − 0)²/2 = 9.75·2.438 − 4·2.438²/2 = 11.88 kN·m

Answer

Mmax = 11.88 kN·m
7.Beam deflection

Answer: θA = 0.01772 rad

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition). The slope θ = dv/dx is the first integral of M/(EI); in consistent units it comes out in radians.

Consistent units

Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.

w = 20 N/mm, L = 5000 mm
EI = 5.88 × 10¹² N·mm²

End slope

θA = wL³/(24EI) = 20·5000³/(24·5.88 × 10¹²) = 0.01772 rad

Answer

θA = 0.01772 rad

That is 1.015°.

8.Beam deflection

Answer: hreq = 308.8 mm

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).

Consistent units

Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.

w = 4 N/mm, L = 6000 mm, E = 11000 N/mm²

Deflection limit

δallow = L/360 = 6000/360 = 16.67 mm

Required second moment of area

Ireq = 5wL⁴/(384·E·δallow) = 5·4·6000⁴/(384·11000·16.67) = 3.682 × 10⁸ mm⁴

Required depth

bh³/12 = Ireq → h = (12·3.682 × 10⁸/150)1/3 = 308.8 mm

Answer

hreq = 308.8 mm

In practice, choose the next standard depth above this value.

9.Column buckling

Answer: Pcr = 5.426 kN

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Smallest second moment of area

A round section has the same I about every axis.

I = πd⁴/64 = π·20⁴/64 = 7854 mm⁴

Effective length

KL = 1·1000 = 1000 mm

Critical load

Pcr = π²EI/(KL)² = π²·70000·7854/1000² = 5426 N = 5.426 kN

Answer

Pcr = 5.426 kN
10.Column buckling

Answer: d = 36.88 mm

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Required critical load

Pcr = n·P = 2.5·65000 = 162500 N
KL = 0.7·1500 = 1050 mm

Solve for the diameter

d = (64·n·P·(KL)²/(π³E))^(1/4) = (64·162500·1050²/(π³·200000))^(1/4) = 36.88 mm

Answer

d = 36.88 mm

Check: the slenderness KL/r is 113.9, so the column is slender and Euler applies.

11.Centroid & second moment of area

Answer: Ix = 41.78 × 10⁶ mm⁴

Sections with holes: treat a hole as a negative area. The centroid is ȳ = (A₁y₁ − A₂y₂)/(A₁ − A₂), with A₁, y₁ for the full plate and A₂, y₂ for the hole. For the second moment of area about the centroidal axis, use the parallel-axis theorem for each part and subtract the hole: I = (Ic1 + A₁d₁²) − (Ic2 + A₂d₂²), where d is the distance from each part's own centroid to the axis through ȳ. A rectangle has Ic = bh³/12 and a circle Ic = πd⁴/64.

Centroid

ȳ = (22500·75 − 706.9·97.5)/(22500 − 706.9) = 74.27 mm

Full plate about ȳ

150·150³/12 + 22500·0.7298² = 42.2 × 10⁶ mm⁴

Hole about ȳ

π·30⁴/64 + 706.9·23.23² = 0.4212 × 10⁶ mm⁴

Subtract

Ix = 41.78 × 10⁶ mm⁴

Answer

Ix = 41.78 × 10⁶ mm⁴
12.Centroid & second moment of area

Answer: Ix = 32.81 × 10⁶ mm⁴

Sections with holes: treat a hole as a negative area. The centroid is ȳ = (A₁y₁ − A₂y₂)/(A₁ − A₂), with A₁, y₁ for the full plate and A₂, y₂ for the hole. For the second moment of area about the centroidal axis, use the parallel-axis theorem for each part and subtract the hole: I = (Ic1 + A₁d₁²) − (Ic2 + A₂d₂²), where d is the distance from each part's own centroid to the axis through ȳ. A rectangle has Ic = bh³/12 and a circle Ic = πd⁴/64.

Centroid

ȳ = (18000·75 − 1600·52.5)/(18000 − 1600) = 77.2 mm

Full plate about ȳ

120·150³/12 + 18000·−2.195² = 33.84 × 10⁶ mm⁴

Hole about ȳ

80·20³/12 + 1600·−24.7² = 1.029 × 10⁶ mm⁴

Subtract

Ix = 32.81 × 10⁶ mm⁴

Answer

Ix = 32.81 × 10⁶ mm⁴
13.Effective stress in soil

Answer: σ′ = 53.76 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Total stress

Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.

σ = γd·zw + γsat·(z − zw) = 15·1 + 19.5·4 = 93 kPa

Pore water pressure

Water pressure grows with depth below the water table.

u = γw·(z − zw) = 9.81·4 = 39.24 kPa

Effective stress

σ′ = σ − u = 93 − 39.24 = 53.76 kPa

Answer

σ′ = 53.76 kPa
14.Effective stress in soil

Answer: u = 49.05 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Pore water pressure

Water pressure grows with depth below the water table.

u = γw·(z − zw) = 9.81·5 = 49.05 kPa

Answer

u = 49.05 kPa
15.Consolidation settlement

Answer: S = 95.59 mm

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Preconsolidation pressure

σ′p = OCR·σ′0 = 1.5·45 = 67.5 kPa

Compare with the preconsolidation pressure

σ′f = 45 + 50 = 95 kPa > 67.5 kPa

Settlement

Recompression up to σ′p, virgin compression beyond it.

S = 0.02·4/(1 + 0.7)·log₁₀(67.5/45) + 0.25·4/(1 + 0.7)·log₁₀(95/67.5)
S = 8.287 + 87.31 = 95.59 mm

Answer

S = 95.59 mm
16.Consolidation settlement

Answer: t = 23.89 years

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Drainage path

Hdr = H = 6.5 m

Time

t = Tv·Hdr²/cv = 0.848·6.5²/1.5 = 23.89 years

Answer

t = 23.89 years
17.Hydrostatic force

Answer: F = 36.79 kN

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 0.5 + 1.5/2 = 1.25 m
A = H·b = 1.5·2 = 3 m²
gated = 0.5 mH = 1.5 mF

Resultant force

F = ρ·g·yc·A = 1000·9.81·1.25·3 = 36.79 kN

Answer

F = 36.79 kN
18.Hydrostatic force

Answer: ycp = 2.8 m

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 1 + 3/2 = 2.5 m
A = H·b = 3·3 = 9 m²
gated = 1 mH = 3 mF

Resultant force

F = ρ·g·yc·A = 1260·9.81·2.5·9 = 278.1 kN

Centre of pressure

Pressure grows with depth, so the resultant acts below the centroid.

Ic = b·H³/12 = 3·3³/12 = 6.75 m⁴
ycp = yc + Ic/(yc·A) = 2.5 + 6.75/(2.5·9) = 2.8 m

Answer

ycp = 2.8 m
19.Pipe friction & head loss

Answer: hf = 7.799 m

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Mean velocity

A = π·0.075²/4 = 0.004418 m²
V = Q/A = 0.004/0.004418 = 0.9054 m/s

Velocity head

V²/(2g) = 0.9054²/(2·9.81) = 0.04178 m

Darcy–Weisbach

hf = f·(L/D)·V²/(2g) = 0.028·(500/0.075)·0.9054²/(2·9.81) = 7.799 m

Answer

hf = 7.799 m
20.Pipe friction & head loss

Answer: Q = 104.7 L/s

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Loss coefficients

f·L/D = 0.022·150/0.2 = 16.5
ΣK = 0.5 + 4·0.3 + 2 + 1.0 = 4.7

Energy equation

Both surfaces are open to the air and practically at rest, so all of Δz is lost in the pipe.

12 = (16.5 + 4.7)·V²/(2·9.81)
V = √(2·9.81·12/21.2) = 3.333 m/s

Flow rate

Q = V·π·D²/4 = 3.333·0.03142 = 0.1047 m³/s = 104.7 L/s

Answer

Q = 104.7 L/s
21.Open-channel flow (Manning)

Answer: Q = 7.156 m³/s

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Geometry

A = (b + z·y)·y = (2.5 + 3·0.8)·0.8 = 3.92 m²
P = b + 2y·√(1 + z²) = 2.5 + 2·0.8·√(1 + 3²) = 7.56 m
R = A/P = 0.5185 m

Velocity

V = (1/0.025)·0.51852/3·0.0051/2 = 1.826 m/s

Flow rate

Q = A·V = 3.92·1.826 = 7.156 m³/s

Answer

Q = 7.156 m³/s
22.Open-channel flow (Manning)

Answer: S = 0.0004691 m/m

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Geometry

A = (b + z·y)·y = (3.5 + 1·2.3)·2.3 = 13.34 m²
P = b + 2y·√(1 + z²) = 3.5 + 2·2.3·√(1 + 1²) = 10.01 m
R = A/P = 1.333 m

Solve Manning for S

S1/2 = n·Q/(A·R2/3) = 0.025·14/(13.34·1.211) = 0.02166
S = 0.02166² = 0.0004691

Answer

S = 0.0004691

That is a fall of 0.4691 m per kilometre.

23.Pumps & pump power

Answer: η = 81.75 %

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Hydraulic power

Ph = ρ·g·Q·H = 1000·9.81·0.025·28 = 6.867 kW

Efficiency

η = Ph/Pshaft = 6.867/8.4 = 81.75%

Answer

η = 81.75%
24.Pumps & pump power

Answer: H = 24.55 m

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Velocity

V = Q/A = 0.075/0.03142 = 2.387 m/s
V²/(2g) = 0.2905 m

Head losses

hL = (f·L/D + ΣK)·V²/(2g) = (18 + 8)·0.2905 = 7.553 m

Pump head

Both surfaces are open and practically at rest, so pressure and velocity terms drop out.

H = Δz + hL = 17 + 7.553 = 24.55 m

Answer

H = 24.55 m
25.Time value of money

Answer: PV = 33333 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Growing perpetuity

PV = C1/(r − g) = 2 000/(0.075 − 0.015) = 2 000/0.06 = €33 333.33

Answer

PV = €33 333.33
26.Time value of money

Answer: FV = 23215 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Ordinary annuity factor

((1 + 0.08)13 − 1)/0.08 = 21.5

Annuity due

Each deposit is invested one year longer.

FV = 1 000·21.5·1.08 = €23 214.92

Answer

FV = €23 214.92
27.NPV & IRR

Answer: DPB = 2.913 years

Payback period: the time until the cumulative cash flows repay the initial investment. Cash is assumed to come in evenly during each year, so the last part is a fraction of a year. The simple payback ignores the time value of money; the discounted payback period uses the discounted cash flows instead.

Discounted and cumulative cash flows

year 1: 17 000/1.1 = 15 454.55 → Σ = 15 454.55
year 2: 16 000/1.21 = 13 223.14 → Σ = 28 677.69
year 3: 16 500/1.331 = 12 396.69 → Σ = 41 074.38

Fraction of the last year

DPB = 2 + 11 322.31/12 396.69 = 2.913

Answer

DPB = 2.913 years

The discounted payback is always longer than the simple payback (2.424 years).

28.NPV & IRR

Answer: IRR = 32.79 %

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Bracket the IRR

NPV falls as the rate rises, so the IRR lies between a rate with positive NPV and one with negative NPV.

NPV(30%) = 789.71
NPV(35%) = −589.85

Narrow down

Linear interpolation gives a first estimate; repeating it (or a calculator's IRR function) gives the exact rate.

IRR ≈ 30 + 5·789.71/(789.71 − (−589.85)) = 32.86%
exact: NPV(32.79%) = 0 → IRR = 32.79%

Answer

IRR = 32.79%
29.Normal distribution

Answer: P = 0.1587

Sums and differences of normal variables: if X and Y are independent and normal, X + Y and X − Y are normal too. Means add or subtract: E(X ± Y) = μX ± μY. Variances always add, also for a difference: Var(X ± Y) = σX² + σY², so σ = √(σX² + σY²). Standard deviations never add directly. The total of n independent items with the same distribution has mean n·μ and standard deviation σ·√n. Then standardise as usual: z = (x − mean)/σ and read Φ(z).

Distribution of the total

μT = 225 kg, σT = 0.5·√9 = 1.5 kg

Standardise

z = (223.5 − 225)/1.5 = −1

Probability

P = Φ(−1) = 0.1587

Answer

P = 0.1587
30.Normal distribution

Answer: P = 0.7881

Sums and differences of normal variables: if X and Y are independent and normal, X + Y and X − Y are normal too. Means add or subtract: E(X ± Y) = μX ± μY. Variances always add, also for a difference: Var(X ± Y) = σX² + σY², so σ = √(σX² + σY²). Standard deviations never add directly. The total of n independent items with the same distribution has mean n·μ and standard deviation σ·√n. Then standardise as usual: z = (x − mean)/σ and read Φ(z).

Distribution of the difference

μ = 52 − 48 = 4 s, σ = 5 s

Standardise

z = (0 − 4)/5 = −0.8

Probability

P = 1 − Φ(−0.8) = 0.7881

Answer

P = 0.7881

This is independent practice material. ExamProblems is not affiliated with or endorsed by the organisation that runs this exam, and the exam name is used only to describe the content. The FE exam is run by NCEES, which is not affiliated with ExamProblems and does not endorse it.

ExamProblems · examproblems.com/courses/fe-exam-civil