FE Civil exam practice: cram pack

Formula sheets, the key method steps for every topic and 30 practice problems, with full solutions at the back.

New problemsBack to the course

In the print window, choose “Save as PDF” to keep a copy on your device.

1Formulas and methods

Beam support reactions

Equilibrium
ΣFx = 0, ΣFy = 0, ΣM = 0
Uniform load
resultant w·L at the middle of the load
Moment
M = F·d

Method

  1. Draw a free-body diagram and replace each support by its reactions.
  2. Replace every distributed load by a single force at its centroid.
  3. Take moments about one support to find the reaction at the other.
  4. Use ΣFy = 0 to find the remaining reaction, and check with a second moment equation.

Truss: method of joints

Method of joints
ΣFx = 0, ΣFy = 0 at each joint
Method of sections
ΣM = 0 about a cut point
Member force
positive = tension, negative = compression

Method

  1. Find the support reactions for the whole truss.
  2. Method of joints: start at a joint with at most two unknown member forces and use ΣFx = 0 and ΣFy = 0.
  3. Method of sections: cut through the member you need and take moments about a point where the other unknown members meet.
  4. Assume tension; a negative answer means compression.

Shear force & bending moment

Shear and moment
V = ΣF on one side, M = ΣF·d on one side
Bending stress
σ = M·y/I
Rectangle
I = bh³/12
Section modulus
W = I/ymax
Simply supported, uniform load
Mmax = wL²/8

Method

  1. Find the support reactions from equilibrium of the whole beam.
  2. Cut the beam at the section you need and keep one side.
  3. Shear force: sum of the vertical forces on that side. Bending moment: sum of their moments about the cut.
  4. For the maximum moment, find where the shear force is zero.

Beam deflection

Point load at midspan
δ = PL³/(48EI)
Uniform load, simply supported
δ = 5wL⁴/(384EI)
Cantilever, end load
δ = PL³/(3EI)
Cantilever, uniform load
δ = wL⁴/(8EI)
Superposition
δ = δ1 + δ2

Column buckling

Euler load
Pcr = π²EI/(KL)²
Effective length factor
K = 1 pinned–pinned, 0.5 fixed–fixed, 0.7 fixed–pinned, 2 fixed–free
Critical stress
σcr = Pcr/A
Slenderness
λ = KL/r, r = √(I/A)

Centroid & second moment of area

Centroid
ȳ = ΣAiyi/ΣAi
Rectangle
I = bh³/12
Parallel-axis theorem
I = Ic + A·d²
Composite section
I = Σ(Ic,i + Aidi²)

Effective stress in soil

Total stress
σ = Σγi·hi
Pore water pressure
u = γw·(z − zw)
Effective stress
σ′ = σ − u
Water
γw = 9.81 kN/m³

Consolidation settlement

Normally consolidated
S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0)
Final stress
σ′f = σ′0 + Δσ (at mid-depth of the layer)
Overconsolidated, σ′f ≤ σ′p
S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0)
Overconsolidated, σ′f > σ′p
S = H/(1 + e0)·[Cr·log₁₀(σ′p/σ′0) + Cc·log₁₀(σ′f/σ′p)]
Overconsolidation ratio
OCR = σ′p/σ′0
Time for consolidation
t = Tv·Hdr²/cv
Drainage path
Hdr = H/2 (double drainage), H (single drainage)
Time factors
U 50% → 0.197, 60% → 0.287, 70% → 0.403, 80% → 0.567, 90% → 0.848

Hydrostatic force

Pressure at depth
p = ρgh
Force on a vertical wall
F = ρg·hc·A
Centre of pressure
yp = yc + Ic/(ycA)
Rectangle
Ic = bH³/12

Pipe friction & head loss

Reynolds number
Re = V·D/ν = ρ·V·D/μ
Flow regime
laminar below Re ≈ 2000, turbulent above Re ≈ 4000
Mean velocity
V = Q/A, A = π·D²/4
Darcy–Weisbach
hf = f·(L/D)·V²/(2g)
Minor losses
hm = ΣK·V²/(2g)
Typical K values
entrance 0.5, exit 1.0, 90° bend ≈ 0.3
Pressure drop
Δp = ρ·g·hf
Two open reservoirs
Δz = (f·L/D + ΣK)·V²/(2g)
Free outlet
H = (1 + f·L/D + ΣK)·V²/(2g)

Open-channel flow (Manning)

Manning equation
V = (1/n)·R2/3·S1/2
Flow rate
Q = A·V
Hydraulic radius
R = A/P (P = wetted perimeter, free surface excluded)
Rectangle
A = b·y, P = b + 2y
Trapezoid (side slope z:1)
A = (b + z·y)·y, P = b + 2y·√(1 + z²)
Circular pipe, full or half full
R = D/4
Required slope
S = (n·Q/(A·R2/3))²

Pumps & pump power

Hydraulic power
Ph = ρ·g·Q·H = Q·Δp
Shaft power
Pshaft = Ph/ηpump
Electrical power
Pel = Pshaft/ηmotor
Pump head
H = Δz + Δp/(ρ·g) + hL
System losses
hL = (f·L/D + ΣK)·V²/(2g)

Time value of money

Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i

Method

  1. Draw a timeline with every cash flow and its timing.
  2. Match the rate to the period: a monthly rate for monthly payments.
  3. Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
  4. Check the sign and the order of magnitude of the answer.

NPV & IRR

Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)

Method

  1. List all cash flows with their year; the investment at year 0 is negative.
  2. Discount each cash flow: CFt/(1 + r)t.
  3. Add them up to get the NPV. Positive means the project earns more than r.
  4. For the IRR, find the rate that makes NPV zero by trial or interpolation.

Normal distribution

z-score
z = (x − μ)/σ
Below x
P(X < x) = Φ(z)
Above x
P(X > x) = 1 − Φ(z)
Between
Φ(z2) − Φ(z1)
Percentile
x = μ + z·σ

Method

  1. Convert the value to a z-score: z = (x − μ)/σ.
  2. Look up Φ(z), the area to the left of z.
  3. For the area to the right use 1 − Φ(z); for an interval subtract the two left areas.
  4. For a percentile, work backwards: find z for the area, then x = μ + z·σ.

2Practice problems

1.Beam support reactionsMedium
P1​ = 40 kNP2​ = 50 kNABRA​ = ?RB​1 m2 m2 m

The simply supported beam has a pin at A and a roller at B. Find the vertical support reaction RA.

L = 5 mP1 = 40 kN at 1 mP2 = 50 kN at 3 m
RA = kN
2.Beam support reactionsHard
w = 6 kN/mP = 20 kNABRA​ = ?RB​3 m5 m2 m

The simply supported beam has a pin at A and a roller at B. Find the vertical support reaction RA.

L = 10 mP = 20 kN at 3 mw = 6 kN/m from 8 to 10 m
RA = kN
3.Truss: method of jointsMedium
ABCDEFGH25 kN4 × 4 m3 m

Exactly one member of this truss carries no force under these loads. Which is the zero-force member? Click it in the diagram.

B: 25 kN ↓
  1. 1member AB
  2. 2member BC
  3. 3member CD
  4. 4member DE
  5. 5member FG
  6. 6member GH
  7. 7member AF
  8. 8member HE
  9. 9member BF
  10. 10member CG
  11. 11member DH
  12. 12member BG
  13. 13member DG
4.Truss: method of jointsHard
ABBCACACB25 kN5 kN6 m5 m4 m

Use the method of joints to find the force FAB in member AB. Give tension as positive and compression as negative.

span = 6 mheight = 4 mB is 5 m from Avertical load = 25 kNhorizontal load = 5 kN →
FAB = kN
5.Shear force & bending momentMedium
6 kN/m60 kNABCDEFG1 m1 m1 m1 m1 m1 m

The marks A to G split the beam into six equal parts. At which mark is the bending moment largest in size, sagging or hogging? Click it in the diagram.

60 kN @ 2 m6 kN/m, 2–4 m
  1. 1A (x = 0 m)
  2. 2B (x = 1 m)
  3. 3C (x = 2 m)
  4. 4D (x = 3 m)
  5. 5E (x = 4 m)
  6. 6F (x = 5 m)
  7. 7G (x = 6 m)
6.Shear force & bending momentHard
w = 2 kN/mP = 55 kNABsection7 m1 m

Find the bending moment Mx at the section x = 7 m from support A. Use sagging moments positive and upward shear on the left face positive.

L = 8 mP = 55 kN at 7 mw = 2 kN/m from 0 to 8 mx = 7 m
Mx = kN·m
7.Beam deflectionMedium
P = 30 kNABδ1.5 m4.5 m

A cantilever of length L is fixed at A and carries a point load P at a distance a = 1.5 m from A. Find the deflection δB at the free end B.

P = 30 kNa = 1.5 mL = 6 mE = 200 GPa (steel)I = 57 × 10⁶ mm⁴
δB = mm
8.Beam deflectionHard
w = 4 kN/mAB6 m

A propped cantilever is fixed at A and simply supported (propped) at B. It carries a uniformly distributed load w over its whole length. EI is constant. Find the size of the bending moment MA at the fixed end.

L = 6 mw = 4 kN/m
MA = kN·m
9.Column bucklingMedium
PL = 3 m40 × 60 mmcross-section

A column of length L made of steel is fixed at the base and free at the top. Using Euler’s formula, find its critical buckling load Pcr.

L = 3 mE = 200 GPa (steel)b × h = 40 × 60 mm
Pcr = kN
10.Column bucklingHard
PL = 2 md = 30 mmcross-section

A column of length L made of aluminium is pinned at both ends. Find its slenderness and the critical buckling stress σcr from Euler’s formula.

L = 2 mE = 70 GPa (aluminium)d = 30 mm
σcr = MPa
11.Centroid & second moment of areaMedium
2404202210xdimensions in mm

A symmetric I-section has flanges 240 mm wide and 22 mm thick, an overall depth of 420 mm and a web 10 mm thick. Find its second moment of area Ix about the horizontal centroidal axis x.

B = 240 mmH = 420 mmtf = 22 mmtw = 10 mm
Ix = × 10⁶ mm⁴
12.Centroid & second moment of areaHard
120 mm200 mm120 mm80 × 20xIx​ = ?

A 120 mm × 200 mm plate has a rectangular cut-out 80 mm wide and 20 mm high, centred on the vertical centre line with its centre 120 mm above the bottom. Find the second moment of area Ix about the horizontal axis through the centroid.

b = 120 mmh = 200 mmcut-out: 80 × 20 mmhole centre: y = 120 mm
Ix = × 10⁶ mm⁴
13.Effective stress in soilMedium
sandγd​ = 17 kN/m³γsat​ = 19 kN/m³10 mwater tableXz = 4 m

For the soil profile shown, find the vertical effective stress σ′ at point X.

z = 4 mzw = 2 mγw = 9.81 kN/m³sand: γd = 17 kN/m³sand: γsat = 19 kN/m³
σ′ = kPa
14.Effective stress in soilHard
sandγd​ = 17 kN/m³γsat​ = 20.5 kN/m³6 mclayγsat​ = 18 kN/m³8 mwater tableXz = 10 m

For the soil profile shown, find the vertical effective stress σ′ at point X.

z = 10 mzw = 2 mγw = 9.81 kN/m³sand: γd = 17 kN/m³sand: γsat = 20.5 kN/m³clay: γsat = 18 kN/m³
σ′ = kPa
15.Consolidation settlementMedium
Δσ = 20 kPasandclayCc​ = 0.2, Cr​ = 0.06e0​ = 0.6σ′0​ = 95 kPaOCR = 24 mwater table

A 4 m thick overconsolidated clay layer has Cc = 0.2, Cr = 0.06 and e₀ = 0.6. At its mid-depth the effective vertical stress is 95 kPa and the overconsolidation ratio is OCR = 2. A new building adds 20 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.

H = 4 mCc = 0.2Cr = 0.06e0 = 0.6σ′0 = 95 kPaOCR = 2Δσ = 20 kPa
S = mm
16.Consolidation settlementHard
sandclayH = 2 mcv​ = 4 m²/year2 mimpervious rockwater table

A clay layer 2 m thick has a coefficient of consolidation cv = 4 m²/year. It lies on impervious rock, with sand above it, so water drains out only at the top. For 70% average consolidation the time factor is Tv = 0.403. How many years t does the layer take to reach 70% consolidation?

H = 2 mcv = 4 m²/yearU = 70%Tv = 0.403single drainage
t = years
17.Hydrostatic forceMedium
gated = 2.5 mH = 3 m

A vertical rectangular gate 1.5 m wide sits in the wall of a tank of water, with its top edge 2.5 m below the surface. Find the resultant hydrostatic force F on the gate.

d = 2.5 mH = 3 mb = 1.5 mρ = 1000 kg/m³g = 9.81 m/s²
F = kN
18.Hydrostatic forceHard
gated = 1 mH = 1 m

A vertical rectangular gate 1.5 m wide sits in the wall of a tank of seawater, with its top edge 1 m below the surface. Find the resultant hydrostatic force F on the gate.

d = 1 mH = 1 mb = 1.5 mρ = 1025 kg/m³g = 9.81 m/s²
F = kN
19.Pipe friction & head lossMedium
V = 1.2 m/sD = 50 mmL = 500 mf = 0.02

Water (ρ = 1000 kg/m³) flows at 1.2 m/s through a horizontal pipe, 500 m long, with an inside diameter of 50 mm. Use the Darcy friction factor f = 0.02 and g = 9.81 m/s². Find the pressure drop Δp over the pipe in kPa.

V = 1.2 m/sL = 500 mD = 50 mmf = 0.02ρ = 1000 kg/m³
Δp = kPa
20.Pipe friction & head lossHard
K = 2Δz = ?L = 200 m, D = 250 mm, f = 0.0224× bend (K = 0.3)

Two open reservoirs are joined by a pipe 200 m long with an inside diameter of 250 mm and a Darcy friction factor f = 0.022. The minor losses are a square-edged entrance (K = 0.5), 4 bends (K = 0.3 each), a valve (K = 2) and the exit into the lower reservoir (K = 1.0). Use g = 9.81 m/s². What difference in water level Δz between the reservoirs gives a flow rate of 150 L/s?

Q = 150 L/sL = 200 mD = 250 mmf = 0.022Kentrance = 0.5Kbend = 0.3 (×4)Kvalve = 2Kexit = 1.0
Δz = m
21.Open-channel flow (Manning)Medium
b = 6 my = 1 m1 : 1n = 0.015, S = 0.0015

A trapezoidal brickwork channel has a bottom width of 6 m and side slopes of 1:1 (horizontal:vertical). Water flows uniformly 1 m deep. Manning n = 0.015 and the bed slope is S = 0.0015. Find the flow rate Q in m³/s.

b = 6 my = 1 mz = 1n = 0.015S = 0.0015
Q = m³/s
22.Open-channel flow (Manning)Hard
b = 2.5 my = 2.2 m2 : 1n = 0.015, Q = 33 m³/s

A trapezoidal brickwork channel with a bottom width of 2.5 m and side slopes of 2:1 (horizontal:vertical) must carry 33 m³/s in uniform flow at a depth of 2.2 m. Manning n = 0.015. Find the required bed slope S (in m/m).

Q = 33 m³/sb = 2.5 my = 2.2 mz = 2n = 0.015
S = m/m
23.Pumps & pump powerMedium
PQ = 15 L/sH = 62 m

In a test, a pump delivers 15 L/s of water (ρ = 1000 kg/m³) against a head of 62 m while its shaft takes 11.1 kW. Use g = 9.81 m/s². Find the pump efficiency η in percent.

Q = 15 L/sH = 62 mPshaft = 11.1 kWg = 9.81 m/s²
η = %
24.Pumps & pump powerHard
PQ = 50 L/sΔz = 29 mL = 200 m, D = 150 mm, f = 0.015, ΣK = 6

A pump moves 50 L/s of water (ρ = 1000 kg/m³) from an open lower reservoir to an upper tank whose water surface is 29 m higher. The pipe is 200 m long with an inside diameter of 150 mm and a Darcy friction factor f = 0.015; the minor-loss coefficients add up to ΣK = 6 (entrance and exit included). Use g = 9.81 m/s². Find the head H the pump must add.

Q = 50 L/sΔz = 29 mL = 200 mD = 150 mmf = 0.015ΣK = 6
H = m
25.Time value of moneyMedium
years012€2 000FV = ?

You invest €2 000 at a nominal rate of 4% per year, compounded quarterly. Find the value FV of the investment after 2 years.

PV = €2 0004% / 4n = 2
FV = €
26.Time value of moneyHard
months0123…96A?AA€100 000

You want €100 000 in 8 years. You save the same amount at the end of every month in an account paying 7.2% per year, compounded monthly. Find the monthly deposit A.

FV = €100 0007.2% / 12N = 96
A = €
27.NPV & IRRMedium
years012345−40 0009 5009 5009 5009 50017 500

A machine costs €40 000 today. It generates €9 500 at the end of each year for 5 years and can then be sold for €8 000. The cost of capital is 10%. Find the net present value NPV.

C0 = €40 000CF = €9 500S = €8 000n = 5r = 10%
NPV = €
28.NPV & IRRHard
years0123…8−20 0003 0003 0003 0003 000

An investment of €20 000 returns €3 000 at the end of each year for 8 years. Find its internal rate of return IRR in percent.

C0 = €20 000CF = €3 000n = 8
IRR = %
29.Normal distributionMedium
488560P = ?

The battery lifetimes are normally distributed with mean 500 h and standard deviation 40 h. What fraction lies between 488 and 560 h? Give P as a decimal.

μ = 500σ = 40x1 = 488x2 = 560
P =
30.Normal distributionHard
0.04 mm0D − d?

Hole diameters D are normal with mean 25.04 mm and standard deviation 0.02 mm. Shaft diameters d are independent and normal with mean 25 mm and standard deviation 0.02 mm. A randomly chosen shaft fits when D − d > 0. Find the probability P that it fits. Round z to two decimals.

hole: μ = 25.04 mm, σ = 0.02 mmshaft: μ = 25 mm, σ = 0.02 mm
P =

3Solutions

1.Beam support reactions

Answer: RA = 52 kN

Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Taking moments about one support removes that support’s reaction from the equation.

P1​ = 40 kNP2​ = 50 kNABRA​RB​1 m2 m2 m

Free-body diagram

Replace the supports with reaction forces. A roller gives one vertical reaction; with only vertical loads the pin gives one vertical reaction too.

Equilibrium

Moments about A, counter-clockwise positive. Then vertical force balance.

ΣMA = 0: RB·5 = 40·1 + 50·3
RB = 190/5 = 38 kN
ΣFy = 0: RA = 90 − 38 = 52 kN

Answer

RA = 52 kN
2.Beam support reactions

Answer: RA = 15.2 kN

Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Taking moments about one support removes that support’s reaction from the equation.

w = 6 kN/mP = 20 kNABRA​RB​3 m5 m2 m

Free-body diagram

Replace the supports with reaction forces. A roller gives one vertical reaction; with only vertical loads the pin gives one vertical reaction too.

Equilibrium

Moments about A, counter-clockwise positive. Then vertical force balance.

UDL resultant: W = w·ℓ = 6·2 = 12 kN, acting at x̄ = 9 m
ΣMA = 0: RB·10 = 20·3 + 6·2·9
RB = 168/10 = 16.8 kN
ΣFy = 0: RA = 32 − 16.8 = 15.2 kN

Answer

RA = 15.2 kN
3.Truss: method of joints

Answer: member CG

Zero-force members: at a joint, the forces must balance in every direction. If a joint has no load and no support, and two of its three members are in line, then the balance across that line involves only the third member, so its force is zero. If only two members meet at an unloaded joint and they are not in line, both are zero.

Joint C

BC and CD lie on one straight line and the joint carries no load. Balancing forces across that line leaves only CG.

ΣF⊥ = 0 → FCG = 0

Check with the method of joints

Solving all joints gives these member forces (T = tension, C = compression).

AB: 25 kN (T), BC: 16.67 kN (T), CD: 16.67 kN (T), DE: 8.333 kN (T), FG: 25 kN (C), GH: 8.333 kN (C), AF: 31.25 kN (C), HE: 10.42 kN (C), BF: 18.75 kN (T), CG: 0, DH: 6.25 kN (T), BG: 10.42 kN (T), DG: 10.42 kN (C)

Answer

Zero-force member: CG
4.Truss: method of joints

Answer: FAB = −1.334 kN

Method of joints: every pin of a truss is in equilibrium, so ΣFx = 0 and ΣFy = 0 at each joint. Start at a joint with at most two unknown member forces. A negative result means the member is in compression.

ABBCACACB25 kN5 kNAy​Cy​Ax​

Support reactions

Equilibrium of the whole truss. Moments about A, counter-clockwise positive.

ΣMA = 0: Cy·6 = 25·5 + 5·4 → Cy = 24.17 kN
ΣFy = 0: Ay = 25 − 24.17 = 0.8333 kN
ΣFx = 0: Ax = −5 kN

Joint A

Assume every member is in tension (pulling away from the joint). Only AB has a vertical component at A.

sin α = 4/6.403 = 0.6247
ΣFy = 0: Ay + FAB·sin α = 0
FAB = −0.8333/0.6247 = −1.334 kN

Answer

FAB = −1.334 kN (compression)
5.Shear force & bending moment

Answer: C (x = 2 m)

Largest bending moment: M changes slope wherever the shear force changes, so its peaks sit where the shear force crosses zero: under a point load, inside a distributed load, or over a support of an overhang. At a fixed support of a cantilever the moment is largest at the wall. Compare the size of M at those places, sagging or hogging.

Support reactions

Take moments about one support, then use the vertical force balance.

R1 = 46 kN, R2 = 26 kN

Bending moment at every mark

Sum the moments of all forces on one side of the cut. Sagging is positive, hogging negative.

MA = 0, MB = 46, MC = 92 kN·m, MD = 75, ME = 52, MF = 26, MG = 0

Answer

Mark C: MC = 92 kN·m
6.Shear force & bending moment

Answer: Mx = 55.13 kN·m

Method of sections: cut the beam where you want the internal forces and keep one side. The shear force V balances the vertical forces on that side, and the bending moment M balances their moments about the cut.

Support reactions

Equilibrium of the whole beam.

UDL resultant: W = w·ℓ = 2·8 = 16 kN, acting at x̄ = 4 m
ΣMA = 0: RB·8 = 55·7 + 2·8·4
RB = 449/8 = 56.13 kN
ΣFy = 0: RA = 71 − 56.13 = 14.88 kN
w = 2 kN/mP = 55 kNABRA​ = 14.88RB​ = 56.13section7 m1 m

Cut at x = 7 m and keep the left part

Only forces left of the cut appear. A UDL portion acts as one force at the middle of that portion.

M = RA·x − (each load left of the cut × its distance to the cut)
Mx = 14.88·7 − 2·7·3.5 = 55.13 kN·m

Answer

Mx = 55.13 kN·m
7.Beam deflection

Answer: δB = 16.28 mm

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).

Consistent units

Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.

P = 30000 N, a = 1500 mm, L = 6000 mm
EI = 1.14 × 10¹³ N·mm²

Deflection at the free end

Deflection at the load plus the slope at the load times the remaining length.

δP = Pa³/(3EI) = 2.961 mm
θP = Pa²/(2EI) = 0.002961 rad
δB = δP + θP·(L − a) = Pa²(3L − a)/(6EI) = 16.28 mm

Answer

δB = 16.28 mm
8.Beam deflection

Answer: MA = 18 kN·m

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition). For a statically indeterminate beam, remove a redundant support and require the deflection there to be zero (compatibility).

Remove the prop

Without the prop the beam is a cantilever. Its free end would deflect under the load.

δload = wL⁴/(8EI)

Compatibility at the prop

The prop force RB alone lifts the free end by RBL³/(3EI). The prop holds B at zero deflection, so the two must cancel. EI cancels out.

RB·L³/(3EI) = wL⁴/(8EI) → RB = 3wL/8 = 3·4·6/8 = 9 kN

Moment at the fixed end

Moments about A of the loads and the prop force.

MA = wL²/2 − RB·L = 72 − 54 = 18 kN·m

Answer

MA = 18 kN·m
9.Column buckling

Answer: Pcr = 17.55 kN

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Smallest second moment of area

A rectangle buckles about its weak axis, using the smaller dimension cubed.

Imin = h·b³/12 = 60·40³/12 = 320000 mm⁴

Effective length

KL = 2·3000 = 6000 mm

Critical load

Pcr = π²EI/(KL)² = π²·200000·320000/6000² = 17546 N = 17.55 kN

Answer

Pcr = 17.55 kN
10.Column buckling

Answer: σcr = 9.715 MPa

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Smallest second moment of area

A round section has the same I about every axis.

I = πd⁴/64 = π·30⁴/64 = 39761 mm⁴

Radius of gyration and slenderness

A = 706.9 mm²
r = √(I/A) = √(39761/706.9) = 7.5 mm
KL = 1·2000 = 2000 mm
KL/r = 2000/7.5 = 266.7

Critical stress

σcr = π²E/(KL/r)² = π²·70000/266.7² = 9.715 MPa

Answer

σcr = 9.715 MPa
11.Centroid & second moment of area

Answer: Ix = 462.9 × 10⁶ mm⁴

Second moment of area: for a rectangle about its own centroidal axis I = bh³/12, and about its base bh³/3 (parallel-axis theorem I = Ic + A·d²). A hole is handled by subtracting its I, as long as both parts share the same axis. The elastic section modulus is S = I/c, where c is the distance to the extreme fibre.

Outer rectangle minus the two side cut-outs

Both cut-outs together are (B − tw) wide and hw = H − 2tf high, and share the axis x.

hw = 420 − 2·22 = 376 mm
Ix = (B·H³ − (B − tw)·hw³)/12 = (240·420³ − 230·376³)/12
Ix = 4.629 × 10⁸ mm⁴ = 462.9 × 10⁶ mm⁴

Answer

Ix = 462.9 × 10⁶ mm⁴
12.Centroid & second moment of area

Answer: Ix = 79.26 × 10⁶ mm⁴

Sections with holes: treat a hole as a negative area. The centroid is ȳ = (A₁y₁ − A₂y₂)/(A₁ − A₂), with A₁, y₁ for the full plate and A₂, y₂ for the hole. For the second moment of area about the centroidal axis, use the parallel-axis theorem for each part and subtract the hole: I = (Ic1 + A₁d₁²) − (Ic2 + A₂d₂²), where d is the distance from each part's own centroid to the axis through ȳ. A rectangle has Ic = bh³/12 and a circle Ic = πd⁴/64.

Centroid

ȳ = (24000·100 − 1600·120)/(24000 − 1600) = 98.57 mm

Full plate about ȳ

120·200³/12 + 24000·1.429² = 80.05 × 10⁶ mm⁴

Hole about ȳ

80·20³/12 + 1600·21.43² = 0.788 × 10⁶ mm⁴

Subtract

Ix = 79.26 × 10⁶ mm⁴

Answer

Ix = 79.26 × 10⁶ mm⁴
13.Effective stress in soil

Answer: σ′ = 52.38 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Total stress

Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.

σ = γd·zw + γsat·(z − zw) = 17·2 + 19·2 = 72 kPa

Pore water pressure

Water pressure grows with depth below the water table.

u = γw·(z − zw) = 9.81·2 = 19.62 kPa

Effective stress

σ′ = σ − u = 72 − 19.62 = 52.38 kPa

Answer

σ′ = 52.38 kPa
14.Effective stress in soil

Answer: σ′ = 109.5 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Total stress

Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.

σ = γd·2 + γsat,sand·4 + γsat,clay·4
σ = 17·2 + 20.5·4 + 18·4 = 188 kPa

Pore water pressure

Water pressure grows with depth below the water table.

u = γw·(z − zw) = 9.81·8 = 78.48 kPa

Effective stress

σ′ = σ − u = 188 − 78.48 = 109.5 kPa

Answer

σ′ = 109.5 kPa
15.Consolidation settlement

Answer: S = 12.45 mm

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Preconsolidation pressure

σ′p = OCR·σ′0 = 2·95 = 190 kPa

Compare with the preconsolidation pressure

σ′f = 95 + 20 = 115 kPa ≤ 190 kPa

Settlement

The clay stays on its recompression line.

S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0) = 0.06·4/(1 + 0.6)·log₁₀(115/95) = 12.45 mm

Answer

S = 12.45 mm
16.Consolidation settlement

Answer: t = 0.403 years

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Drainage path

Hdr = H = 2 m

Time

t = Tv·Hdr²/cv = 0.403·2²/4 = 0.403 years

Answer

t = 0.403 years
17.Hydrostatic force

Answer: F = 176.6 kN

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 2.5 + 3/2 = 4 m
A = H·b = 3·1.5 = 4.5 m²
gated = 2.5 mH = 3 mF

Resultant force

F = ρ·g·yc·A = 1000·9.81·4·4.5 = 176.6 kN

Answer

F = 176.6 kN
18.Hydrostatic force

Answer: F = 22.62 kN

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 1 + 1/2 = 1.5 m
A = H·b = 1·1.5 = 1.5 m²
gated = 1 mH = 1 mF

Resultant force

F = ρ·g·yc·A = 1025·9.81·1.5·1.5 = 22.62 kN

Answer

F = 22.62 kN
19.Pipe friction & head loss

Answer: Δp = 144 kPa

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Head loss

hf = f·(L/D)·V²/(2g) = 0.02·(500/0.05)·1.2²/(2·9.81) = 14.68 m

Pressure drop

The pipe is horizontal and the velocity does not change, so the energy equation reduces to Δp = ρ·g·hf.

Δp = ρ·g·hf = 1000·9.81·14.68 = 144000 Pa = 144 kPa

Answer

Δp = 144 kPa
20.Pipe friction & head loss

Answer: Δz = 10.61 m

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Velocity

V = Q/A = 0.15/0.04909 = 3.056 m/s
V²/(2g) = 0.4759 m

Loss coefficients

f·L/D = 0.022·200/0.25 = 17.6
ΣK = 0.5 + 4·0.3 + 2 + 1.0 = 4.7

Total head loss

hf = 17.6·0.4759 = 8.376 m
hm = 4.7·0.4759 = 2.237 m
Δz = hf + hm = 10.61 m

Answer

Δz = 10.61 m
21.Open-channel flow (Manning)

Answer: Q = 15.48 m³/s

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Geometry

A = (b + z·y)·y = (6 + 1·1)·1 = 7 m²
P = b + 2y·√(1 + z²) = 6 + 2·1·√(1 + 1²) = 8.828 m
R = A/P = 0.7929 m

Velocity

V = (1/0.015)·0.79292/3·0.00151/2 = 2.212 m/s

Flow rate

Q = A·V = 7·2.212 = 15.48 m³/s

Answer

Q = 15.48 m³/s
22.Open-channel flow (Manning)

Answer: S = 0.0008066 m/m

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Geometry

A = (b + z·y)·y = (2.5 + 2·2.2)·2.2 = 15.18 m²
P = b + 2y·√(1 + z²) = 2.5 + 2·2.2·√(1 + 2²) = 12.34 m
R = A/P = 1.23 m

Solve Manning for S

S1/2 = n·Q/(A·R2/3) = 0.015·33/(15.18·1.148) = 0.0284
S = 0.0284² = 0.0008066

Answer

S = 0.0008066

That is a fall of 0.8066 m per kilometre.

23.Pumps & pump power

Answer: η = 82.19 %

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Hydraulic power

Ph = ρ·g·Q·H = 1000·9.81·0.015·62 = 9.123 kW

Efficiency

η = Ph/Pshaft = 9.123/11.1 = 82.19%

Answer

η = 82.19%
24.Pumps & pump power

Answer: H = 39.61 m

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Velocity

V = Q/A = 0.05/0.01767 = 2.829 m/s
V²/(2g) = 0.408 m

Head losses

hL = (f·L/D + ΣK)·V²/(2g) = (20 + 6)·0.408 = 10.61 m

Pump head

Both surfaces are open and practically at rest, so pressure and velocity terms drop out.

H = Δz + hL = 29 + 10.61 = 39.61 m

Answer

H = 39.61 m
25.Time value of money

Answer: FV = 2166 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Rate and number of periods

i = r/m = 0.04/4 = 0.01
N = m·n = 4·2 = 8

Future value

FV = 2 000·(1 + 0.01)8 = 2 000·1.083 = €2 165.71

Answer

FV = €2 165.71
26.Time value of money

Answer: A = 773.3 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Monthly rate and number of deposits

i = 0.07200000000000001/12 = 0.006
N = 12·8 = 96

Deposit

A = FV·i/((1 + i)N − 1) = 100 000·0.006/(1.776 − 1) = €773.35

Answer

A = €773.35
27.NPV & IRR

Answer: NPV = 979.8 €

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Present value of the yearly cash flows

9 500·3.791 = 36 012.47

Present value of the salvage value

8 000/1.611 = 4 967.37

NPV

NPV = −40 000 + 36 012.47 + 4 967.37 = €979.84

Answer

NPV = €979.84
28.NPV & IRR

Answer: IRR = 4.239 %

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Required annuity factor

(1 − (1 + i)−8)/i = 20 000/3 000 = 6.667

Solve for the rate

The annuity factor falls as the rate rises; bracket the rate and narrow down.

i = 4%: 6.733
i = 5%: 6.463
IRR = 4.239%

Answer

IRR = 4.239%
29.Normal distribution

Answer: P = 0.5511

Normal distribution: convert a value x to a z-score, z = (x − μ)/σ, which counts standard deviations from the mean. A z-table (or Φ(z)) gives the area to the left of z, which is P(X < x). The area to the right is 1 − Φ(z), and the area between two values is the difference of their two areas.

z-scores

z₁ = (488 − 500)/40 = −0.3
z₂ = (560 − 500)/40 = 1.5

Area between

P = Φ(1.5) − Φ(−0.3) = 0.9332 − 0.3821 = 0.5511

Answer

P = 0.5511
30.Normal distribution

Answer: P = 0.9207

Sums and differences of normal variables: if X and Y are independent and normal, X + Y and X − Y are normal too. Means add or subtract: E(X ± Y) = μX ± μY. Variances always add, also for a difference: Var(X ± Y) = σX² + σY², so σ = √(σX² + σY²). Standard deviations never add directly. The total of n independent items with the same distribution has mean n·μ and standard deviation σ·√n. Then standardise as usual: z = (x − mean)/σ and read Φ(z).

Distribution of the difference

μ = 25.04 − 25 = 0.04 mm, σ = 0.02828 mm

Standardise

z = (0 − 0.04)/0.02828 = −1.41

Probability

P = 1 − Φ(−1.41) = 0.9207

Answer

P = 0.9207

This is independent practice material. ExamProblems is not affiliated with or endorsed by the organisation that runs this exam, and the exam name is used only to describe the content. The FE exam is run by NCEES, which is not affiliated with ExamProblems and does not endorse it.