Investments and Valuation: cram pack

Formula sheets, the key method steps for every topic and 8 practice problems, with full solutions at the back.

New problemsBack to the course

In the print window, choose “Save as PDF” to keep a copy on your device.

1Formulas and methods

Time value of money

Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i

Method

  1. Draw a timeline with every cash flow and its timing.
  2. Match the rate to the period: a monthly rate for monthly payments.
  3. Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
  4. Check the sign and the order of magnitude of the answer.

Bond pricing & yield

Bond price
P = C·(1 − (1 + y)−n)/y + F/(1 + y)n
Semi-annual
C/2, y/2 and 2n periods
Current yield
C/P
Price and yield
yield up → price down

Method

  1. Find the coupon per period and the yield per period.
  2. Price = present value of the coupons (an annuity) + present value of the face value.
  3. For semi-annual coupons use half the coupon, half the yield and twice the periods.
  4. Check: if the yield is above the coupon rate, the price is below face value.

CAPM & WACC

CAPM
re = rf + β·(rm − rf)
WACC
E/V·re + D/V·rd·(1 − T)
Firm value
V = E + D

NPV & IRR

Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)

Method

  1. List all cash flows with their year; the investment at year 0 is negative.
  2. Discount each cash flow: CFt/(1 + r)t.
  3. Add them up to get the NPV. Positive means the project earns more than r.
  4. For the IRR, find the rate that makes NPV zero by trial or interpolation.

2Practice problems

1.Time value of moneyMedium
years012€12 000FV = ?

You invest €12 000 at a nominal rate of 6% per year, compounded quarterly. Find the value FV of the investment after 2 years.

PV = €12 0006% / 4n = 2
FV = €
2.Time value of moneyHard
months01…216…360€200 000AB = ?A4.2% / 12

A mortgage of €200 000 is repaid with equal monthly payments over 30 years at 4.2% per year, compounded monthly. How much is still owed just after the payment at the end of year 18? Find the outstanding balance B.

P = €200 0004.2% / 12N = 360k = 216
B = €
3.Bond pricing & yieldMedium
years0123…8P€80€80€80 + €1 000

A bond with a face value of €1 000 pays an annual coupon of 8% and matures in 8 years. Its yield to maturity changes from 3% to 2%. By how much ΔP does the bond price change?

F = €1 000coupon = 8%n = 8y1 = 3%y2 = 2%
ΔP = €
4.Bond pricing & yieldHard
years012345€1 127€90€90€90 + €1 090

A bond with 14 years to maturity (face value €1 000, annual coupon 9%) sells for €1 127. The issuer can call it in 5 years at a call price of €1 090. Find the yield to call YTC in percent.

F = €1 000coupon = 9%P = €1 127call price = €1 090call in 5 years
YTC = %
5.CAPM & WACCMedium
βr (%)SMLrf​ = 2.5%β = 1rm​ = ?β = 1.4re​ = 11.6%

A share with a beta of 1.4 has a required return of 11.6%. The risk-free rate is 2.5%. What expected market return rm does CAPM imply?

β = 1.4re = 11.6%rf = 2.5%
rm = %
6.CAPM & WACCHard
rf​ = 1.5%, rm​ − rf​ = 4.5%D/E = 0.2equityβL​ = 1debtD/E = 1.25equityre​ = ?debtT = 25%

A company's shares have a beta of 1 at its current debt-to-equity ratio of 0.2. It plans to raise its debt-to-equity ratio to 1.25. The tax rate is 25%, the risk-free rate 1.5% and the market risk premium 4.5%. Find the cost of equity re after the change.

βL = 1D/E1 = 0.2D/E2 = 1.25T = 25%rf = 1.5%rm − rf = 4.5%
re = %
7.NPV & IRRMedium
years0123−75 00024 00034 00034 000

An investment of €75 000 gives these cash flows at the end of years 1 to 3: €24 000, €34 000, €34 000. The cost of capital is 9%. Find the net present value NPV.

r = 9%CF0 = −75 000CF1 = 24 000CF2 = 34 000CF3 = 34 000
NPV = €
8.NPV & IRRHard
years0123−40 00016 50020 00019 500

A project costs €40 000 and returns €16 500, €20 000, €19 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.

CF0 = −40 000CF1 = 16 500CF2 = 20 000CF3 = 19 500
IRR = %

3Solutions

1.Time value of money

Answer: FV = 13518 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Rate and number of periods

i = r/m = 0.06/4 = 0.015
N = m·n = 4·2 = 8

Future value

FV = 12 000·(1 + 0.015)8 = 12 000·1.126 = €13 517.91

Answer

FV = €13 517.91
2.Time value of money

Answer: B = 110478 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Monthly payment

i = 0.0035, N = 360
A = 200 000·0.0035/(1 − (1 + 0.0035)−360) = €978.03

Present value of the remaining payments

Whatever is still owed must be exactly paid off by the remaining payments.

N − k = 360 − 216 = 144
B = 978·(1 − (1 + 0.0035)−144)/0.0035 = €110 478.42

Answer

B = €110 478.42
3.Bond pricing & yield

Answer: ΔP = 88.54 €

Bond pricing: a bond’s price is the present value of its cash flows, discounted at the yield to maturity (YTM): the coupons form an annuity and the face value is paid back at maturity. P = C·(1 − (1 + y)⁻ⁿ)/y + F/(1 + y)ⁿ. When the yield is above the coupon rate the bond trades below face value, and the other way round.

Price at the old yield

C = €80.00, i = 0.03, N = 8
€80.00·(1 − 0.7894)/0.03 + €1 000·0.7894 = €561.58 + €789.41 = €1 350.98

Price at the new yield

C = €80.00, i = 0.02, N = 8
€80.00·(1 − 0.8535)/0.02 + €1 000·0.8535 = €586.04 + €853.49 = €1 439.53

Change

ΔP = 1 439.53 − 1 350.98 = €88.54

Answer

ΔP = €88.54
4.Bond pricing & yield

Answer: YTC = 7.42 %

Bond pricing: a bond’s price is the present value of its cash flows, discounted at the yield to maturity (YTM): the coupons form an annuity and the face value is paid back at maturity. P = C·(1 − (1 + y)⁻ⁿ)/y + F/(1 + y)ⁿ. When the yield is above the coupon rate the bond trades below face value, and the other way round.

Equation for the yield

1127 = 90·(1 − (1 + y)−5)/y + 1090/(1 + y)5

Solve numerically

y = 7%: €1 146.17
y = 8%: €1 101.18
YTC = 7.42%

Answer

YTC = 7.42%

The yield to maturity is 7.504%. Investors in a premium bond expect it to be called, so the lower yield to call is the more realistic one.

5.CAPM & WACC

Answer: rm = 9 %

Cost of capital: CAPM gives the return shareholders require: re = rf + β·(rm − rf). The weighted average cost of capital mixes equity and debt by their market values: WACC = E/V·re + D/V·rd·(1 − T), with V = E + D. Interest is tax-deductible, hence the (1 − T).

Market risk premium

rm − rf = (11.6% − 2.5%)/1.4 = 6.5%

Market return

rm = 2.5% + 6.5% = 9%

Answer

rm = 9%
6.CAPM & WACC

Answer: re = 9.082 %

Levered beta (Hamada): debt makes equity riskier. βL = βU·(1 + (1 − T)·D/E), where βU is the beta of the business without debt. To move a beta to another capital structure, unlever it first and then relever it at the new D/E.

Unlever the beta

βU = 1/(1 + 0.75·0.2) = 0.8696

Relever at the new D/E

βL = 0.8696·(1 + 0.75·1.25) = 1.685

Cost of equity (CAPM)

re = 1.5% + 1.685·4.5% = 9.082%

Answer

re = 9.082%
7.NPV & IRR

Answer: NPV = 1890 €

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Present value of each cash flow

CF0 = −75 000
CF1/(1 + 0.09)1 = 24 000/1.09 = 22 018.35
CF2/(1 + 0.09)2 = 34 000/1.188 = 28 617.12
CF3/(1 + 0.09)3 = 34 000/1.295 = 26 254.24

Add them up

NPV = €1 889.71

Answer

NPV = €1 889.71

NPV is positive, so the project earns more than the required return.

8.NPV & IRR

Answer: IRR = 18.33 %

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Bracket the IRR

NPV falls as the rate rises, so the IRR lies between a rate with positive NPV and one with negative NPV.

NPV(15%) = 2 292.27
NPV(20%) = −1 076.39

Narrow down

Linear interpolation gives a first estimate; repeating it (or a calculator's IRR function) gives the exact rate.

IRR ≈ 15 + 5·2 292.27/(2 292.27 − (−1 076.39)) = 18.4%
exact: NPV(18.33%) = 0 → IRR = 18.33%

Answer

IRR = 18.33%