In the print window, choose “Save as PDF” to keep a copy on your device.
1Formulas and methods
Time value of money
Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i
Method
Draw a timeline with every cash flow and its timing.
Match the rate to the period: a monthly rate for monthly payments.
Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
Check the sign and the order of magnitude of the answer.
Bond pricing & yield
Bond price
P = C·(1 − (1 + y)−n)/y + F/(1 + y)n
Semi-annual
C/2, y/2 and 2n periods
Current yield
C/P
Price and yield
yield up → price down
Method
Find the coupon per period and the yield per period.
Price = present value of the coupons (an annuity) + present value of the face value.
For semi-annual coupons use half the coupon, half the yield and twice the periods.
Check: if the yield is above the coupon rate, the price is below face value.
CAPM & WACC
CAPM
re = rf + β·(rm − rf)
WACC
E/V·re + D/V·rd·(1 − T)
Firm value
V = E + D
NPV & IRR
Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)
Method
List all cash flows with their year; the investment at year 0 is negative.
Discount each cash flow: CFt/(1 + r)t.
Add them up to get the NPV. Positive means the project earns more than r.
For the IRR, find the rate that makes NPV zero by trial or interpolation.
2Practice problems
1.Time value of moneyMedium
You invest €2 000 at 2% per year with continuous compounding. Find the value FV after 18 years.
PV = €2 000r = 2%t = 18
FV = €
2.Time value of moneyHard
A loan of €20 000 is repaid with equal monthly payments over 5 years. The interest rate is 6% per year, compounded monthly. Find the monthly payment A.
P = €20 0006% / 12N = 60
A = €
3.Bond pricing & yieldMedium
You buy a bond with 10 years to maturity (face value €1 000, annual coupon 4%) when its yield to maturity is 8%. One year later, just after receiving the first coupon, you sell it when the yield to maturity is 8.5%. Find your holding period return HPR in percent.
F = €1 000coupon = 4%n = 10y0 = 8%y1 = 8.5%
HPR = %
4.Bond pricing & yieldHard
A bond with a face value of €1 000 and an annual coupon of 7% matures in 7 years and sells for €900. Find its yield to maturity YTM in percent.
F = €1 000coupon = 7%n = 7P = €900
YTM = %
5.CAPM & WACCMedium
A company has equity worth €5 000 000 and debt worth €3 000 000. Its WACC is 8.4%, its pre-tax cost of debt is 3% and the tax rate is 20%. Find the cost of equity re.
A company's shares have a beta of 1.1 at its current debt-to-equity ratio of 0.4. It plans to raise its debt-to-equity ratio to 1.5. The tax rate is 28%, the risk-free rate 1% and the market risk premium 4.5%. Find the cost of equity re after the change.
A machine costs €40 000 today. It generates €9 000 at the end of each year for 6 years and can then be sold for €4 000. The cost of capital is 6%. Find the net present value NPV.
C0 = €40 000CF = €9 000S = €4 000n = 6r = 6%
NPV = €
8.NPV & IRRHard
A project costs €10 000 and returns €3 500, €3 000, €4 000, €4 500 at the end of years 1 to 4. Cash flows can be reinvested at the cost of capital of 12%. Find the modified internal rate of return MIRR in percent.
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Exponent
r·t = 0.02·18 = 0.36
e0.36 = 1.433
Future value
FV = 2 000·1.433 = €2 866.66
Answer
FV = €2 866.66
2.Time value of money
Answer: A = 386.7 €
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Monthly rate and number of payments
i = 0.06/12 = 0.005
N = 12·5 = 60
Payment
The present value of N equal payments A is A·(1 − (1 + i)⁻ᴺ)/i. Set it equal to the loan and solve for A.
(1 + i)−N = 0.7414
A = 20 000·0.005/(1 − 0.7414) = €386.66
Answer
A = €386.66
3.Bond pricing & yield
Answer: HPR = 4.517 %
Bond pricing: a bond’s price is the present value of its cash flows, discounted at the yield to maturity (YTM): the coupons form an annuity and the face value is paid back at maturity. P = C·(1 − (1 + y)⁻ⁿ)/y + F/(1 + y)ⁿ. When the yield is above the coupon rate the bond trades below face value, and the other way round.
Bond pricing: a bond’s price is the present value of its cash flows, discounted at the yield to maturity (YTM): the coupons form an annuity and the face value is paid back at maturity. P = C·(1 − (1 + y)⁻ⁿ)/y + F/(1 + y)ⁿ. When the yield is above the coupon rate the bond trades below face value, and the other way round.
Equation for the yield
€900 = €70·(1 − (1 + y)⁻⁷)/y + €1 000/(1 + y)⁷
Solve numerically
P(8%) = €947.94, P(9%) = €899.34
YTM = 8.986%
Answer
YTM = 8.986%
5.CAPM & WACC
Answer: re = 12 %
Cost of capital: CAPM gives the return shareholders require: re = rf + β·(rm − rf). The weighted average cost of capital mixes equity and debt by their market values: WACC = E/V·re + D/V·rd·(1 − T), with V = E + D. Interest is tax-deductible, hence the (1 − T).
Weights
V = €8 000 000, E/V = 0.625, D/V = 0.375
Debt part of the WACC
0.375·3%·(1 − 0.2) = 0.9%
Cost of equity
re = (8.4% − 0.9%)/0.625 = 12%
Answer
re = 12%
6.CAPM & WACC
Answer: re = 8.994 %
Levered beta (Hamada): debt makes equity riskier. βL = βU·(1 + (1 − T)·D/E), where βU is the beta of the business without debt. To move a beta to another capital structure, unlever it first and then relever it at the new D/E.
Unlever the beta
βU = 1.1/(1 + 0.72·0.4) = 0.854
Relever at the new D/E
βL = 0.854·(1 + 0.72·1.5) = 1.776
Cost of equity (CAPM)
re = 1% + 1.776·4.5% = 8.994%
Answer
re = 8.994%
7.NPV & IRR
Answer: NPV = 7076 €
Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.
Present value of the yearly cash flows
9 000·4.917 = 44 255.92
Present value of the salvage value
4 000/1.419 = 2 819.84
NPV
NPV = −40 000 + 44 255.92 + 2 819.84 = €7 075.76
Answer
NPV = €7 075.76
8.NPV & IRR
Answer: MIRR = 15.28 %
Modified IRR: compound every inflow forward to the end of the project at the reinvestment rate (usually the cost of capital) to get the terminal value TV. MIRR is the rate that turns the initial investment into TV: MIRR = (TV/C₀)^(1/n) − 1.