1Formulas and methods
Time value of money
Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i
Method
Draw a timeline with every cash flow and its timing.
Match the rate to the period: a monthly rate for monthly payments.
Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
Check the sign and the order of magnitude of the answer.
Bond pricing & yield
Bond price
P = C·(1 − (1 + y)−n)/y + F/(1 + y)n
Semi-annual
C/2, y/2 and 2n periods
Current yield
C/P
Price and yield
yield up → price down
Method
Find the coupon per period and the yield per period.
Price = present value of the coupons (an annuity) + present value of the face value.
For semi-annual coupons use half the coupon, half the yield and twice the periods.
Check: if the yield is above the coupon rate, the price is below face value.
CAPM & WACC
CAPM
re = rf + β·(rm − rf)
WACC
E/V·re + D/V·rd·(1 − T)
Firm value
V = E + D
NPV & IRR
Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)
Method
List all cash flows with their year; the investment at year 0 is negative.
Discount each cash flow: CFt/(1 + r)t.
Add them up to get the NPV. Positive means the project earns more than r.
For the IRR, find the rate that makes NPV zero by trial or interpolation.
2Practice problems
1.Time value of moneyMedium
You need €40 000 in 6 years. An account pays 3% per year, compounded quarterly. How much must you deposit today? Find the present value PV.
FV = €40 0003% / 4n = 6
PV = €
2.Time value of moneyHard
You save €100 at the end of every month for 20 years. The account pays 4.8% per year, compounded monthly. How much have you saved at the end? Find FV.
A = €1004.8% / 12N = 240
FV = €
3.Bond pricing & yieldMedium
A bond with a face value of €1 000 matures in 8 years and pays annual coupons. It sells for €1 251 when the yield to maturity is 2.5%. Find the coupon rate c in percent.
F = €1 000n = 8P = €1 251YTM = 2.5%
c = %
4.Bond pricing & yieldHard
A bond with 12 years to maturity (face value €1 000, annual coupon 7%) sells for €1 177. The issuer can call it in 3 years at a call price of €1 070. Find the yield to call YTC in percent.
F = €1 000coupon = 7%P = €1 177call price = €1 070call in 3 years
YTC = %
5.CAPM & WACCMedium
A company is financed with ordinary shares worth €12 000 000, preferred shares worth €500 000 and debt worth €4 000 000. The cost of equity is 10%, the cost of preferred stock 6% and the pre-tax cost of debt 4%. The tax rate is 25.8%. Find the WACC.
A company has 4 000 000 shares at €42.50 each and 10 000 bonds trading at €1 020 each. The pre-tax cost of debt is 6% and the tax rate is 21%. The share’s beta is 0.6, the risk-free rate 4% and the market return 8.5%. Find the WACC.
β = 0.6rf = 4%rm = 8.5%rd = 6%T = 21%
WACC = %
7.NPV & IRRMedium
An investment of €30 000 gives these cash flows at the end of years 1 to 4: €15 000, €8 000, €14 000, €15 000. The cost of capital is 6%. Find the net present value NPV.
A project costs €25 000 and returns €12 000, €13 500, €12 500 at the end of years 1 to 3. Cash flows can be reinvested at the cost of capital of 10%. Find the modified internal rate of return MIRR in percent.
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Rate and number of periods
i = 0.03/4 = 0.0075
N = 4·6 = 24
Present value
PV = FV/(1 + i)N = 40 000/1.196 = €33 433.26
Answer
PV = €33 433.26
2.Time value of money
Answer: FV = 40168 €
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
You paid in €24 000 yourself; the rest is interest.
3.Bond pricing & yield
Answer: c = 6.001 %
Bond pricing: a bond’s price is the present value of its cash flows, discounted at the yield to maturity (YTM): the coupons form an annuity and the face value is paid back at maturity. P = C·(1 − (1 + y)⁻ⁿ)/y + F/(1 + y)ⁿ. When the yield is above the coupon rate the bond trades below face value, and the other way round.
Present value of the face value
1000·(1 + 0.025)−8 = €820.75
Coupon
C = (1251 − 820.75)/7.17 = €60.01
Coupon rate
c = 60.01/1000 = 6.001%
Answer
c = 6.001%
4.Bond pricing & yield
Answer: YTC = 3.006 %
Bond pricing: a bond’s price is the present value of its cash flows, discounted at the yield to maturity (YTM): the coupons form an annuity and the face value is paid back at maturity. P = C·(1 − (1 + y)⁻ⁿ)/y + F/(1 + y)ⁿ. When the yield is above the coupon rate the bond trades below face value, and the other way round.
Equation for the yield
1177 = 70·(1 − (1 + y)−3)/y + 1070/(1 + y)3
Solve numerically
y = 3%: €1 177.20
y = 4%: €1 145.48
YTC = 3.006%
Answer
YTC = 3.006%
The yield to maturity is 5.003%. Investors in a premium bond expect it to be called, so the lower yield to call is the more realistic one.
5.CAPM & WACC
Answer: WACC = 8.174 %
Cost of capital: CAPM gives the return shareholders require: re = rf + β·(rm − rf). The weighted average cost of capital mixes equity and debt by their market values: WACC = E/V·re + D/V·rd·(1 − T), with V = E + D. Interest is tax-deductible, hence the (1 − T).
Cost of capital: CAPM gives the return shareholders require: re = rf + β·(rm − rf). The weighted average cost of capital mixes equity and debt by their market values: WACC = E/V·re + D/V·rd·(1 − T), with V = E + D. Interest is tax-deductible, hence the (1 − T).
Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.
Present value of each cash flow
CF0 = −30 000
CF1/(1 + 0.06)1 = 15 000/1.06 = 14 150.94
CF2/(1 + 0.06)2 = 8 000/1.124 = 7 119.97
CF3/(1 + 0.06)3 = 14 000/1.191 = 11 754.67
CF4/(1 + 0.06)4 = 15 000/1.262 = 11 881.40
Add them up
NPV = €14 906.99
Answer
NPV = €14 906.99
NPV is positive, so the project earns more than the required return.
8.NPV & IRR
Answer: MIRR = 18.76 %