1Formulas and methods

Time value of money

Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i

Method

  1. Draw a timeline with every cash flow and its timing.
  2. Match the rate to the period: a monthly rate for monthly payments.
  3. Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
  4. Check the sign and the order of magnitude of the answer.

Bond pricing & yield

Bond price
P = C·(1 − (1 + y)−n)/y + F/(1 + y)n
Semi-annual
C/2, y/2 and 2n periods
Current yield
C/P
Price and yield
yield up → price down

Method

  1. Find the coupon per period and the yield per period.
  2. Price = present value of the coupons (an annuity) + present value of the face value.
  3. For semi-annual coupons use half the coupon, half the yield and twice the periods.
  4. Check: if the yield is above the coupon rate, the price is below face value.

CAPM & WACC

CAPM
re = rf + β·(rm − rf)
WACC
E/V·re + D/V·rd·(1 − T)
Firm value
V = E + D

NPV & IRR

Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)

Method

  1. List all cash flows with their year; the investment at year 0 is negative.
  2. Discount each cash flow: CFt/(1 + r)t.
  3. Add them up to get the NPV. Positive means the project earns more than r.
  4. For the IRR, find the rate that makes NPV zero by trial or interpolation.

2Practice problems

1.Time value of moneyMedium
years012345€12 000FV = ?

You invest €12 000 at a nominal rate of 5% per year, compounded monthly. Find the value FV of the investment after 5 years.

PV = €12 0005% / 12n = 5
FV = €
2.Time value of moneyHard
months0123…240€250 000A?AAA

A loan of €250 000 is repaid with equal monthly payments over 20 years. The interest rate is 3% per year, compounded monthly. Find the monthly payment A.

P = €250 0003% / 12N = 240
A = €
3.Bond pricing & yieldMedium
half-years0123…18€10€10€10 + €1 000P = ?

A bond with a face value of €1 000 pays a 2% annual coupon in two half-yearly payments and matures in 9 years. The yield to maturity is 6% per year. Find the price P of the bond.

F = €1 000coupon = 2%YTM = 6%n = 9
P = €
4.Bond pricing & yieldHard
half-years0123…10€910€10€10€10 + €1 000

A bond with a face value of €1 000 pays a 2% annual coupon in two half-yearly payments and matures in 5 years. It sells for €910. Find its yield to maturity YTM as an annual rate (twice the half-yearly yield), in percent.

F = €1 000coupon = 2% (2×)n = 5P = €910
YTM = %
5.CAPM & WACCMedium
WACC = ?equity€2 000 000re​ = 12%debt€4 000 000rd​ = 6%T = 25.8%

A company has equity worth €2 000 000 and debt worth €4 000 000. Its cost of equity is 12%, its pre-tax cost of debt is 6% and the tax rate is 25.8%. Find the WACC.

E = €2 000 000D = €4 000 000re = 12%rd = 6%T = 25.8%
WACC = %
6.CAPM & WACCHard
rf​ = 2.5%, rm​ − rf​ = 6.5%no debtequityβU​ = 0.7D/E = 0.25equityre​ = ?debtT = 20%

A company's business has an unlevered (asset) beta of 0.7. It plans a debt-to-equity ratio of 0.25. The tax rate is 20%, the risk-free rate is 2.5% and the market risk premium is 6.5%. Find the cost of equity re at the new capital structure.

βU = 0.7D/E = 0.25T = 20%rf = 2.5%rm − rf = 6.5%
re = %
7.NPV & IRRMedium
years0123−75 00024 00024 00029 000

An investment of €75 000 gives these cash flows at the end of years 1 to 3: €24 000, €24 000, €29 000. The cost of capital is 15%. Find the net present value NPV.

r = 15%CF0 = −75 000CF1 = 24 000CF2 = 24 000CF3 = 29 000
NPV = €
8.NPV & IRRHard
years01234567−40 0009 5009 5009 5009 5009 5009 5009 500

An investment of €40 000 returns €9 500 at the end of each year for 7 years. Find its internal rate of return IRR in percent.

C0 = €40 000CF = €9 500n = 7
IRR = %

3Solutions

1.Time value of money

Answer: FV = 15400 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Rate and number of periods

i = r/m = 0.05/12 = 0.004167
N = m·n = 12·5 = 60

Future value

FV = 12 000·(1 + 0.004167)60 = 12 000·1.283 = €15 400.30

Answer

FV = €15 400.30
2.Time value of money

Answer: A = 1386 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Monthly rate and number of payments

i = 0.03/12 = 0.0025
N = 12·20 = 240

Payment

The present value of N equal payments A is A·(1 − (1 + i)⁻ᴺ)/i. Set it equal to the loan and solve for A.

(1 + i)−N = 0.5492
A = 250 000·0.0025/(1 − 0.5492) = €1 386.49

Answer

A = €1 386.49
3.Bond pricing & yield

Answer: P = 724.9 €

Bond pricing: a bond’s price is the present value of its cash flows, discounted at the yield to maturity (YTM): the coupons form an annuity and the face value is paid back at maturity. P = C·(1 − (1 + y)⁻ⁿ)/y + F/(1 + y)ⁿ. When the yield is above the coupon rate the bond trades below face value, and the other way round.

Per period

C = €10.00, i = 0.03, N = 18

Present value of the coupons

€10.00·(1 − 0.5874)/0.03 = €137.54

Present value of the face value

€1 000·0.5874 = €587.39

Price

P = €724.93

Answer

P = €724.93

The yield is above the coupon rate, so the bond sells at a discount.

4.Bond pricing & yield

Answer: YTM = 4.004 %

Bond pricing: a bond’s price is the present value of its cash flows, discounted at the yield to maturity (YTM): the coupons form an annuity and the face value is paid back at maturity. P = C·(1 − (1 + y)⁻ⁿ)/y + F/(1 + y)ⁿ. When the yield is above the coupon rate the bond trades below face value, and the other way round.

Per period

C = €10.00, N = 10

Solve numerically

i = 2.002% per half-year

YTM

YTM = 2·2.002% = 4.004%

Answer

YTM = 4.004%
5.CAPM & WACC

Answer: WACC = 6.968 %

Cost of capital: CAPM gives the return shareholders require: re = rf + β·(rm − rf). The weighted average cost of capital mixes equity and debt by their market values: WACC = E/V·re + D/V·rd·(1 − T), with V = E + D. Interest is tax-deductible, hence the (1 − T).

Weights

V = €6 000 000, E/V = 0.3333, D/V = 0.6667

WACC

WACC = 0.3333·12% + 0.6667·6%·(1 − 0.258) = 6.968%

Answer

WACC = 6.968%
6.CAPM & WACC

Answer: re = 7.96 %

Levered beta (Hamada): debt makes equity riskier. βL = βU·(1 + (1 − T)·D/E), where βU is the beta of the business without debt. To move a beta to another capital structure, unlever it first and then relever it at the new D/E.

Levered beta

βL = 0.7·(1 + 0.8·0.25) = 0.84

Cost of equity (CAPM)

re = 2.5% + 0.84·6.5% = 7.96%

Answer

re = 7.96%
7.NPV & IRR

Answer: NPV = −16915 €

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Present value of each cash flow

CF0 = −75 000
CF1/(1 + 0.15)1 = 24 000/1.15 = 20 869.57
CF2/(1 + 0.15)2 = 24 000/1.322 = 18 147.45
CF3/(1 + 0.15)3 = 29 000/1.521 = 19 067.97

Add them up

NPV = €−16 915.02

Answer

NPV = €−16 915.02

NPV is negative, so the project earns less than the required return.

8.NPV & IRR

Answer: IRR = 14.6 %

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Required annuity factor

(1 − (1 + i)−7)/i = 40 000/9 500 = 4.211

Solve for the rate

The annuity factor falls as the rate rises; bracket the rate and narrow down.

i = 14%: 4.288
i = 15%: 4.16
IRR = 14.6%

Answer

IRR = 14.6%

ExamProblems · examproblems.com/courses/investments-and-valuation