1Formulas and methods

Time value of money

Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i

Method

  1. Draw a timeline with every cash flow and its timing.
  2. Match the rate to the period: a monthly rate for monthly payments.
  3. Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
  4. Check the sign and the order of magnitude of the answer.

Bond pricing & yield

Bond price
P = C·(1 − (1 + y)−n)/y + F/(1 + y)n
Semi-annual
C/2, y/2 and 2n periods
Current yield
C/P
Price and yield
yield up → price down

Method

  1. Find the coupon per period and the yield per period.
  2. Price = present value of the coupons (an annuity) + present value of the face value.
  3. For semi-annual coupons use half the coupon, half the yield and twice the periods.
  4. Check: if the yield is above the coupon rate, the price is below face value.

CAPM & WACC

CAPM
re = rf + β·(rm − rf)
WACC
E/V·re + D/V·rd·(1 − T)
Firm value
V = E + D

NPV & IRR

Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)

Method

  1. List all cash flows with their year; the investment at year 0 is negative.
  2. Discount each cash flow: CFt/(1 + r)t.
  3. Add them up to get the NPV. Positive means the project earns more than r.
  4. For the IRR, find the rate that makes NPV zero by trial or interpolation.

2Practice problems

1.Time value of moneyMedium
years0123…20PV = ?€1 000€1 000€1 000€1 000

An annuity pays €1 000 at the end of each year for 20 years. The interest rate is 10% per year. Find the present value PV of the annuity.

A = €1 000i = 10%n = 20
PV = €
2.Time value of moneyHard
months0123…36€20 000AAAA5.4% / 12, I = ?

A loan of €20 000 is repaid with equal monthly payments over 3 years at 5.4% per year, compounded monthly. How much interest I is paid in total over the life of the loan?

P = €20 0005.4% / 12N = 36
I = €
3.Bond pricing & yieldMedium
half-years0123…18€22.50€22.50€22.50 + €1 000P = ?

A bond with a face value of €1 000 pays a 4.5% annual coupon in two half-yearly payments and matures in 9 years. The yield to maturity is 5% per year. Find the price P of the bond.

F = €1 000coupon = 4.5%YTM = 5%n = 9
P = €
4.Bond pricing & yieldHard
years01234€1 275€50€50€50 + €1 050

A bond with 13 years to maturity (face value €1 000, annual coupon 5%) sells for €1 275. The issuer can call it in 4 years at a call price of €1 050. Find the yield to call YTC in percent.

F = €1 000coupon = 5%P = €1 275call price = €1 050call in 4 years
YTC = %
5.CAPM & WACCMedium
βr (%)SMLrf​ = 4%β = 1rm​ = ?β = 2re​ = 18%

A share with a beta of 2 has a required return of 18%. The risk-free rate is 4%. What expected market return rm does CAPM imply?

β = 2re = 18%rf = 4%
rm = %
6.CAPM & WACCHard
WACC = ?equity1 000 000 × €25.50D0​ = €0.50g = 4%debt€7 700 000rd​ = 6%T = 21%

A company has 1 000 000 shares trading at €25.50; the book value of its equity is €7 700 000. It just paid a dividend of €0.50 per share, and dividends grow by 4% per year. Its debt has a market value of €7 700 000 and a pre-tax cost of 6%. The tax rate is 21%. Find the WACC, using the dividend growth model for the cost of equity.

N = 1 000 000P0 = €25.50book equity = €7 700 000D0 = €0.50g = 4%D = €7 700 000rd = 6%T = 21%
WACC = %
7.NPV & IRRMedium
years01234567€60 000€1 500€1 500€1 500€1 500€1 500€1 500€1 500r = 5%, EAC = ?

A machine costs €60 000 today, lasts 7 years and costs €1 500 per year to run (paid at the end of each year). The cost of capital is 5%. Find its equivalent annual cost EAC.

C0 = €60 000M = €1 500n = 7r = 5%
EAC = €
8.NPV & IRRHard
years012−50 00025 50033 500

A project costs €50 000 and returns €25 500, €33 500 at the end of years 1 to 2. Find its internal rate of return IRR in percent.

CF0 = −50 000CF1 = 25 500CF2 = 33 500
IRR = %

3Solutions

1.Time value of money

Answer: PV = 8514 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Annuity factor

(1 − (1 + i)−n)/i = (1 − 0.1486)/0.1 = 8.514

Present value

PV = 1 000·8.514 = €8 513.56

Answer

PV = €8 513.56
2.Time value of money

Answer: I = 1709 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Monthly payment

i = 0.0045, N = 36
A = 20 000·0.0045/(1 − (1 + 0.0045)−36) = €603.02

Total interest

I = N·A − P = 36·603 − 20 000 = €1 708.59

Answer

I = €1 708.59
3.Bond pricing & yield

Answer: P = 964.1 €

Bond pricing: a bond’s price is the present value of its cash flows, discounted at the yield to maturity (YTM): the coupons form an annuity and the face value is paid back at maturity. P = C·(1 − (1 + y)⁻ⁿ)/y + F/(1 + y)ⁿ. When the yield is above the coupon rate the bond trades below face value, and the other way round.

Per period

C = €22.50, i = 0.025, N = 18

Present value of the coupons

€22.50·(1 − 0.6412)/0.025 = €322.95

Present value of the face value

€1 000·0.6412 = €641.17

Price

P = €964.12

Answer

P = €964.12

The yield is above the coupon rate, so the bond sells at a discount.

4.Bond pricing & yield

Answer: YTC = 50 %

Bond pricing: a bond’s price is the present value of its cash flows, discounted at the yield to maturity (YTM): the coupons form an annuity and the face value is paid back at maturity. P = C·(1 − (1 + y)⁻ⁿ)/y + F/(1 + y)ⁿ. When the yield is above the coupon rate the bond trades below face value, and the other way round.

Equation for the yield

1275 = 50·(1 − (1 + y)−4)/y + 1050/(1 + y)4

Solve numerically

y = 50%: €287.65
y = 50%: €287.65
YTC = 50%

Answer

YTC = 50%

The yield to maturity is 2.497%. Investors in a premium bond expect it to be called, so the lower yield to call is the more realistic one.

5.CAPM & WACC

Answer: rm = 11 %

Cost of capital: CAPM gives the return shareholders require: re = rf + β·(rm − rf). The weighted average cost of capital mixes equity and debt by their market values: WACC = E/V·re + D/V·rd·(1 − T), with V = E + D. Interest is tax-deductible, hence the (1 − T).

Market risk premium

rm − rf = (18% − 4%)/2 = 7%

Market return

rm = 4% + 7% = 11%

Answer

rm = 11%
6.CAPM & WACC

Answer: WACC = 5.738 %

Cost of capital: CAPM gives the return shareholders require: re = rf + β·(rm − rf). The weighted average cost of capital mixes equity and debt by their market values: WACC = E/V·re + D/V·rd·(1 − T), with V = E + D. Interest is tax-deductible, hence the (1 − T).

Cost of equity

D1 = 0.5·1.04 = €0.52
re = 0.52/25.5 + 0.04 = 6.039%

Market values

E = 1 000 000·€25.50 = €25 500 000
V = €33 200 000, E/V = 0.7681, D/V = 0.2319

WACC

WACC = 0.7681·6.039% + 0.2319·6%·(1 − 0.21) = 5.738%

Answer

WACC = 5.738%
7.NPV & IRR

Answer: EAC = 11869 €

Equivalent annual cost: spread the present value of all costs over the life as an equal yearly amount (an annuity): EAC = PV·r/(1 − (1 + r)⁻ⁿ). It lets you compare machines with different lives.

Annuity factor

(1 − 1.05−7)/0.05 = 5.786

Annualised purchase price

60 000/5.786 = 10 369.19

EAC

EAC = 10 369.19 + 1 500 = €11 869.19

Answer

EAC = €11 869.19
8.NPV & IRR

Answer: IRR = 11.23 %

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Bracket the IRR

NPV falls as the rate rises, so the IRR lies between a rate with positive NPV and one with negative NPV.

NPV(10%) = 867.77
NPV(15%) = −2 495.27

Narrow down

Linear interpolation gives a first estimate; repeating it (or a calculator's IRR function) gives the exact rate.

IRR ≈ 10 + 5·867.77/(867.77 − (−2 495.27)) = 11.29%
exact: NPV(11.23%) = 0 → IRR = 11.23%

Answer

IRR = 11.23%