A load takes 23 kW of real power and 14 kvar of reactive power (lagging). Find the power factor cos φ.
AC power & power factor worksheet with answers
A single-phase load draws 18 A (rms) from a 120 V (rms) supply at a power factor of 0.75 lagging. Find the real power P it takes.
A single-phase motor takes 15 kW at a power factor of 0.9 lagging from a 230 V supply. Find the reactive power Q it draws.
A single-phase motor takes 33 kW at a power factor of 0.8 lagging from a 400 V supply. Find the line current I.
A single-phase load takes 25 kW at a power factor of 0.6 lagging from a 230 V, 60 Hz supply. A capacitor connected in parallel raises the power factor to 0.95. Find the new line current Inew.
A single-phase load takes 45 kW at a power factor of 0.65 lagging from a 240 V, 60 Hz supply. A capacitor connected in parallel raises the power factor to 0.92. Find the reactive power QC the capacitor must supply.
Answer key
- 1. cos φ = 0.8542
- 2. P = 1620 W
- 3. Q = 7.265 kvar
- 4. I = 103.1 A
- 5. Inew = 114.4 A
- 6. QC = 33.44 kvar