An 8 m thick layer of normally consolidated clay (Cc = 0.35, e₀ = 1.35) has an effective vertical stress of 70 kPa at its mid-depth. A wide fill raises the vertical stress in the clay by 125 kPa. Treat the layer as one sublayer with the stresses at its mid-depth. Find the primary consolidation settlement S in mm.
Consolidation settlement worksheet with answers
A 3 m thick layer of normally consolidated clay (Cc = 0.2, e₀ = 0.7) has an effective vertical stress of 140 kPa at its mid-depth. A wide fill raises the vertical stress in the clay by 120 kPa. Treat the layer as one sublayer with the stresses at its mid-depth. Find the primary consolidation settlement S in mm.
A 2 m thick overconsolidated clay layer has Cc = 0.2, Cr = 0.06 and e₀ = 0.6. At its mid-depth the effective vertical stress is 105 kPa and the preconsolidation pressure is 185 kPa. A new building adds 160 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.
A 5.5 m thick overconsolidated clay layer has Cc = 0.4, Cr = 0.05 and e₀ = 1.05. At its mid-depth the effective vertical stress is 100 kPa and the preconsolidation pressure is 160 kPa. A new building adds 40 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.
A clay layer 6 m thick has a coefficient of consolidation cv = 4 m²/year. It lies between two sand layers, so water drains out at the top and the bottom. For 80% average consolidation the time factor is Tv = 0.567. How many years t does the layer take to reach 80% consolidation?
A clay layer 5 m thick has a coefficient of consolidation cv = 5 m²/year. It lies between two sand layers, so water drains out at the top and the bottom. For 60% average consolidation the time factor is Tv = 0.287. How many years t does the layer take to reach 60% consolidation?
Answer key
- 1. S = 530.1 mm
- 2. S = 94.89 mm
- 3. S = 57.47 mm
- 4. S = 19.6 mm
- 5. t = 1.276 years
- 6. t = 0.3587 years
Full step-by-step solutions: practise this topic on examproblems.com.