A project costs €60 000 today and returns €13 000, €16 500, €20 500, €19 500, €23 000 at the end of years 1 to 5. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
NPV & IRR worksheet with answers
A project costs €40 000 today and returns €10 000, €7 000, €6 500, €9 500, €14 000 at the end of years 1 to 5. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
A project costs €60 000 today and returns €16 000 at the end of each year for 6 years. The cost of capital is 10%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €20 000 gives these cash flows at the end of years 1 to 3: €8 000, €8 000, €8 000. The cost of capital is 9%. Find the net present value NPV.
A project costs €10 000 and returns €3 500, €3 000, €3 000, €4 000 at the end of years 1 to 4. Cash flows can be reinvested at the cost of capital of 8%. Find the modified internal rate of return MIRR in percent.
A project costs €20 000 and returns €13 500, €9 000, €9 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. PB = 3.513 years
- 2. PB = 4.5 years
- 3. DPB = 4.934 years
- 4. NPV = 250.4 €
- 5. MIRR = 10.94 %
- 6. IRR = 30.13 %