A machine is expected to save €8 000, €15 000, €5 000 at the end of years 1 to 3, after which it is worthless. The required return is 10%. What is the most the company should pay for the machine today? Find PV.
NPV & IRR worksheet with answers
A project costs €80 000 today and returns €28 000 at the end of each year for 4 years. The required rate of return is 5%. Find the profitability index PI.
An investment of €30 000 gives these cash flows at the end of years 1 to 4: €12 000, €9 000, €12 000, €10 000. The cost of capital is 7.000000000000001%. Find the net present value NPV.
A machine costs €40 000 today. It generates €6 500 at the end of each year for 7 years and can then be sold for €4 000. The cost of capital is 6%. Find the net present value NPV.
A project costs €20 000 and returns €9 500, €14 500 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
A project costs €20 000 and returns €10 000, €9 000, €8 000 at the end of years 1 to 3. Cash flows can be reinvested at the cost of capital of 8%. Find the modified internal rate of return MIRR in percent.
Answer key
- 1. PV = 23426 €
- 2. PI = 1.241
- 3. NPV = 6500 €
- 4. NPV = −1054 €
- 5. IRR = 12.15 %
- 6. MIRR = 13.68 %
Full step-by-step solutions: practise this topic on examproblems.com.