A machine is expected to save €10 000, €20 000, €6 000, €12 000 at the end of years 1 to 4, after which it is worthless. The required return is 8%. What is the most the company should pay for the machine today? Find PV.
NPV & IRR worksheet with answers
A project costs €80 000 today and returns €22 500 at the end of each year for 4 years. The required rate of return is 12%. Find the profitability index PI.
A project costs €50 000 today and returns €19 500, €17 000, €21 000, €21 500, €14 000, €21 000 at the end of years 1 to 6. The cost of capital is 5%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €30 000 gives these cash flows at the end of years 1 to 4: €11 000, €14 000, €10 000, €13 000. The cost of capital is 5%. Find the net present value NPV.
A project costs €10 000 and returns €5 000, €6 000, €5 000, €4 500 at the end of years 1 to 4. Cash flows can be reinvested at the cost of capital of 12%. Find the modified internal rate of return MIRR in percent.
A project costs €10 000 and returns €5 000, €7 500 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
Answer key
- 1. PV = 39989 €
- 2. PI = 0.8543
- 3. DPB = 2.883 years
- 4. NPV = 12508 €
- 5. MIRR = 25.3 %
- 6. IRR = 15.14 %
Full step-by-step solutions: practise this topic on examproblems.com.