A project costs €100 000 today and returns €56 000 at the end of each year for 3 years. The required rate of return is 10%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €20 000 today and returns €8 000, €5 500, €3 000, €5 000, €6 500, €6 000 at the end of years 1 to 6. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
A project costs €200 000 today. It generates €10 000 at the end of the first year, and the cash flow then grows by 3% per year forever. The cost of capital is 9%. Find the net present value NPV.
An investment of €20 000 gives these cash flows at the end of years 1 to 4: €5 000, €5 000, €5 000, €6 000. The cost of capital is 10%. Find the net present value NPV.
A project costs €50 000 and returns €27 500, €25 000, €25 000 at the end of years 1 to 3. Cash flows can be reinvested at the cost of capital of 12%. Find the modified internal rate of return MIRR in percent.
A project costs €50 000 today. Its cash flow is €9 000 at the end of year 1 and grows by 4% per year until the last cash flow at the end of year 6. The cost of capital is 12%. Find the net present value NPV.
Answer key
- 1. NPV = 39264 €
- 2. PB = 3.7 years
- 3. NPV = −33333 €
- 4. NPV = −3468 €
- 5. MIRR = 20.51 %
- 6. NPV = −9618 €