A project costs €40 000 today and returns €22 500 at the end of each year for 3 years. The required rate of return is 5%. Find the net present value NPV.
NPV & IRR worksheet with answers
A machine is expected to save €25 000, €5 000, €20 000, €5 000 at the end of years 1 to 4, after which it is worthless. The required return is 15%. What is the most the company should pay for the machine today? Find PV.
A project costs €60 000 today and returns €21 500, €23 500, €19 000, €15 000, €22 500 at the end of years 1 to 5. The cost of capital is 5%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €45 000 gives these cash flows at the end of years 1 to 4: €11 000, €13 000, €16 000, €19 000. The cost of capital is 15%. Find the net present value NPV.
A project costs €10 000 and returns €5 500, €3 000, €4 000 at the end of years 1 to 3. Cash flows can be reinvested at the cost of capital of 12%. Find the modified internal rate of return MIRR in percent.
Project A costs €30 000 and returns €17 000, €12 000, €7 000 at the end of years 1 to 3. Project B costs €35 000 and returns €9 000, €14 000, €21 000. Find the crossover rate r* at which both projects have the same NPV, in percent.
Answer key
- 1. NPV = 21273 €
- 2. PV = 41529 €
- 3. DPB = 3.146 years
- 4. NPV = −4221 €
- 5. MIRR = 12.56 %
- 6. r* = 9.599 %
Full step-by-step solutions: practise this topic on examproblems.com.