A project costs €25 000 today and returns €10 500 at the end of each year for 4 years. The required rate of return is 5%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €80 000 today and returns €34 500 at the end of each year for 3 years. The required rate of return is 6%. Find the profitability index PI.
An investment of €75 000 gives these cash flows at the end of years 1 to 3: €35 000, €34 000, €26 000. The cost of capital is 6%. Find the net present value NPV.
A machine costs €40 000 today. It generates €15 500 at the end of each year for 3 years and can then be sold for €10 000. The cost of capital is 12%. Find the net present value NPV.
A project costs €40 000 and returns €18 500, €15 500, €21 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €200 000 today. Its cash flow is €60 000 at the end of year 1 and grows by 5% per year until the last cash flow at the end of year 4. The cost of capital is 8%. Find the net present value NPV.
Answer key
- 1. NPV = 12232 €
- 2. PI = 1.153
- 3. NPV = 10109 €
- 4. NPV = 4346 €
- 5. IRR = 17.84 %
- 6. NPV = 13133 €
Full step-by-step solutions: practise this topic on examproblems.com.