NPV & IRR worksheet with answers

Free printable NPV & IRR worksheet: 6 problems from easy to exam level, with an answer key. Print it or save it as a PDF.

For teachers: free to print, copy and use in class. Every new worksheet has new values and its own answer key. A link to ExamProblems on your course page is appreciated.

Name: ____________________   Date: ____________

1.Easy
years0123−25 00014 00014 00014 000

A project costs €25 000 today and returns €14 000 at the end of each year for 3 years. The required rate of return is 6%. Find the net present value NPV.

r = 6%CF0 = −25 000CF1 = 14 000CF2 = 14 000CF3 = 14 000
NPV = €
2.Easy
years0123456−80 00021 50021 50021 50021 50021 50021 500

A project costs €80 000 today and returns €21 500 at the end of each year for 6 years. The required rate of return is 8%. Find the profitability index PI.

C0 = €80 000CF = €21 500n = 6r = 8%
PI =
3.Medium
years01234−30 0007 0009 00011 00013 000

An investment of €30 000 gives these cash flows at the end of years 1 to 4: €7 000, €9 000, €11 000, €13 000. The cost of capital is 7.000000000000001%. Find the net present value NPV.

r = 7.000000000000001%CF0 = −30 000CF1 = 7 000CF2 = 9 000CF3 = 11 000CF4 = 13 000
NPV = €
4.Medium
years01234567€50 000€4 000€4 000€4 000€4 000€4 000€4 000€4 000r = 5%, EAC = ?

A machine costs €50 000 today, lasts 7 years and costs €4 000 per year to run (paid at the end of each year). The cost of capital is 5%. Find its equivalent annual cost EAC.

C0 = €50 000M = €4 000n = 7r = 5%
EAC = €
5.Hard
years0123−50 00019 50037 00020 000

A project costs €50 000 and returns €19 500, €37 000, €20 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.

CF0 = −50 000CF1 = 19 500CF2 = 37 000CF3 = 20 000
IRR = %
6.Hard
years012−40 00024 50022 500

A project costs €40 000 and returns €24 500, €22 500 at the end of years 1 to 2. Find its internal rate of return IRR in percent.

CF0 = −40 000CF1 = 24 500CF2 = 22 500
IRR = %

Answer key

  1. 1. NPV = 12422 €
  2. 2. PI = 1.242
  3. 3. NPV = 3300 €
  4. 4. EAC = 12641 €
  5. 5. IRR = 24.36 %
  6. 6. IRR = 11.64 %