A project costs €50 000 today and returns €20 000 at the end of each year for 5 years. The required rate of return is 10%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €10 000 today and returns €4 000 at the end of each year for 3 years. The required rate of return is 10%. Find the net present value NPV.
A project costs €20 000 today and returns €6 000 at the end of each year for 5 years. The cost of capital is 5%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €20 000 gives these cash flows at the end of years 1 to 3: €7 000, €5 000, €5 000. The cost of capital is 15%. Find the net present value NPV.
A project costs €50 000 and returns €29 000, €17 000, €26 000 at the end of years 1 to 3. Cash flows can be reinvested at the cost of capital of 8%. Find the modified internal rate of return MIRR in percent.
A project costs €25 000 and returns €13 000, €13 000, €12 500, €10 500 at the end of years 1 to 4. Cash flows can be reinvested at the cost of capital of 8%. Find the modified internal rate of return MIRR in percent.
Answer key
- 1. NPV = 25816 €
- 2. NPV = −52.59 €
- 3. DPB = 3.742 years
- 4. NPV = −6845 €
- 5. MIRR = 16.07 %
- 6. MIRR = 22.09 %
Full step-by-step solutions: practise this topic on examproblems.com.