A project costs €50 000 today and returns €18 000 at the end of each year for 5 years. The required rate of return is 5%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €40 000 today and returns €6 500, €7 000, €12 500, €11 000, €8 500 at the end of years 1 to 5. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
A machine costs €50 000 today, lasts 8 years and costs €2 000 per year to run (paid at the end of each year). The cost of capital is 10%. Find its equivalent annual cost EAC.
A machine costs €30 000 today, lasts 6 years and costs €5 000 per year to run (paid at the end of each year). The cost of capital is 6%. Find its equivalent annual cost EAC.
Project A costs €10 000 and returns €5 500, €3 500, €2 500 at the end of years 1 to 3. Project B costs €12 000 and returns €3 000, €5 000, €6 000. Find the crossover rate r* at which both projects have the same NPV, in percent.
Project A costs €10 000 and returns €6 000, €4 000, €2 500 at the end of years 1 to 3. Project B costs €15 000 and returns €4 500, €6 500, €8 000. Find the crossover rate r* at which both projects have the same NPV, in percent.
Answer key
- 1. NPV = 27931 €
- 2. PB = 4.353 years
- 3. EAC = 11372 €
- 4. EAC = 11101 €
- 5. r* = 5.034 %
- 6. r* = 8.826 %
Full step-by-step solutions: practise this topic on examproblems.com.