A project costs €60 000 today and returns €10 500, €12 500, €22 000, €18 000, €20 000 at the end of years 1 to 5. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
NPV & IRR worksheet with answers
A project costs €50 000 today and returns €23 000 at the end of each year for 3 years. The required rate of return is 8%. Find the net present value NPV.
A project costs €50 000 today and returns €16 500, €19 000, €19 000, €21 000 at the end of years 1 to 4. The cost of capital is 6%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €75 000 gives these cash flows at the end of years 1 to 4: €21 000, €22 000, €19 000, €22 000. The cost of capital is 5%. Find the net present value NPV.
An investment of €25 000 returns €4 000 at the end of each year for 8 years. Find its internal rate of return IRR in percent.
Project A costs €30 000 and returns €17 500, €11 000, €7 000 at the end of years 1 to 3. Project B costs €40 000 and returns €10 500, €16 000, €21 000. Find the crossover rate r* at which both projects have the same NPV, in percent.
Answer key
- 1. PB = 3.833 years
- 2. NPV = 9273 €
- 3. DPB = 3.094 years
- 4. NPV = −533 €
- 5. IRR = 5.837 %
- 6. r* = 4.898 %
Full step-by-step solutions: practise this topic on examproblems.com.