A project costs €20 000 today and returns €6 000 at the end of each year for 5 years. The required rate of return is 10%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €25 000 today and returns €12 500 at the end of each year for 3 years. The required rate of return is 15%. Find the net present value NPV.
An investment of €75 000 gives these cash flows at the end of years 1 to 4: €22 000, €35 000, €24 000, €33 000. The cost of capital is 15%. Find the net present value NPV.
A project costs €100 000 today. It generates €12 000 at the end of the first year, and the cash flow then grows by 2% per year forever. The cost of capital is 11%. Find the net present value NPV.
A project costs €20 000 and returns €11 000, €7 500, €11 000, €11 500 at the end of years 1 to 4. Cash flows can be reinvested at the cost of capital of 8%. Find the modified internal rate of return MIRR in percent.
A project costs €10 000 and returns €4 500, €5 000, €4 000, €3 500 at the end of years 1 to 4. Cash flows can be reinvested at the cost of capital of 6%. Find the modified internal rate of return MIRR in percent.
Answer key
- 1. NPV = 2745 €
- 2. NPV = 3540 €
- 3. NPV = 5244 €
- 4. NPV = 33333 €
- 5. MIRR = 23.14 %
- 6. MIRR = 16.97 %
Full step-by-step solutions: practise this topic on examproblems.com.