A project costs €100 000 today and returns €36 000 at the end of each year for 5 years. The required rate of return is 15%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €40 000 today and returns €17 500 at the end of each year for 4 years. The required rate of return is 5%. Find the net present value NPV.
A project costs €400 000 today. It generates €32 000 at the end of the first year, and the cash flow then grows by 1% per year forever. The cost of capital is 11%. Find the net present value NPV.
An investment of €60 000 gives these cash flows at the end of years 1 to 3: €14 000, €26 000, €19 000. The cost of capital is 7.000000000000001%. Find the net present value NPV.
A project costs €20 000 and returns €9 000, €9 500, €10 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
An investment of €80 000 returns €22 500 at the end of each year for 5 years. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 20678 €
- 2. NPV = 22054 €
- 3. NPV = −80000 €
- 4. NPV = −8697 €
- 5. IRR = 19.64 %
- 6. IRR = 12.56 %
Full step-by-step solutions: practise this topic on examproblems.com.