A project costs €25 000 today and returns €13 000 at the end of each year for 3 years. The required rate of return is 5%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €25 000 today and returns €5 500 at the end of each year for 6 years. The required rate of return is 8%. Find the profitability index PI.
A project costs €400 000 today. It generates €48 000 at the end of the first year, and the cash flow then grows by 1% per year forever. The cost of capital is 11%. Find the net present value NPV.
A project costs €250 000 today. It generates €16 000 at the end of the first year, and the cash flow then grows by 4% per year forever. The cost of capital is 11%. Find the net present value NPV.
An investment of €50 000 returns €20 500 at the end of each year for 3 years. Find its internal rate of return IRR in percent.
An investment of €80 000 returns €38 000 at the end of each year for 3 years. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 10402 €
- 2. PI = 1.017
- 3. NPV = 80000 €
- 4. NPV = −21429 €
- 5. IRR = 11.11 %
- 6. IRR = 20.04 %
Full step-by-step solutions: practise this topic on examproblems.com.