A machine is expected to save €6 000, €10 000, €12 000, €18 000 at the end of years 1 to 4, after which it is worthless. The required return is 12%. What is the most the company should pay for the machine today? Find PV.
NPV & IRR worksheet with answers
A project costs €40 000 today and returns €6 500, €13 000, €12 500, €12 000, €12 000, €15 000 at the end of years 1 to 6. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
A project costs €50 000 today and returns €15 500 at the end of each year for 5 years. The cost of capital is 12%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €60 000 gives these cash flows at the end of years 1 to 3: €13 000, €14 000, €23 000. The cost of capital is 7.000000000000001%. Find the net present value NPV.
An investment of €25 000 returns €10 000 at the end of each year for 3 years. Find its internal rate of return IRR in percent.
A project costs €50 000 today. Its cash flow is €11 000 at the end of year 1 and grows by 2% per year until the last cash flow at the end of year 5. The cost of capital is 12%. Find the net present value NPV.
Answer key
- 1. PV = 33310 €
- 2. PB = 3.667 years
- 3. DPB = 4.332 years
- 4. NPV = −16847 €
- 5. IRR = 9.701 %
- 6. NPV = −8913 €