A project costs €25 000 today and returns €14 000 at the end of each year for 3 years. The required rate of return is 15%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €10 000 today and returns €4 500 at the end of each year for 4 years. The required rate of return is 5%. Find the net present value NPV.
A project costs €400 000 today. It generates €32 000 at the end of the first year, and the cash flow then grows by 2% per year forever. The cost of capital is 11%. Find the net present value NPV.
A project costs €40 000 today and returns €11 500 at the end of each year for 6 years. The cost of capital is 5%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
A project costs €20 000 and returns €9 500, €12 500 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
Project A costs €30 000 and returns €17 000, €12 000, €7 000 at the end of years 1 to 3. Project B costs €32 000 and returns €8 500, €14 500, €16 500. Find the crossover rate r* at which both projects have the same NPV, in percent.
Answer key
- 1. NPV = 6965 €
- 2. NPV = 5957 €
- 3. NPV = −44444 €
- 4. DPB = 3.918 years
- 5. IRR = 6.297 %
- 6. r* = 6.97 %