A machine is expected to save €20 000, €25 000, €25 000 at the end of years 1 to 3, after which it is worthless. The required return is 10%. What is the most the company should pay for the machine today? Find PV.
NPV & IRR worksheet with answers
A project costs €30 000 today and returns €6 500, €6 000, €10 000, €9 000, €10 000 at the end of years 1 to 5. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
An investment of €60 000 gives these cash flows at the end of years 1 to 3: €20 000, €23 000, €24 000. The cost of capital is 10%. Find the net present value NPV.
A project costs €50 000 today and returns €21 000, €15 500, €20 500, €12 000, €13 500 at the end of years 1 to 5. The cost of capital is 5%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
A project costs €40 000 and returns €14 500, €29 500, €25 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €50 000 and returns €19 000, €37 000 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
Answer key
- 1. PV = 57626 €
- 2. PB = 3.833 years
- 3. NPV = −4778 €
- 4. DPB = 2.9 years
- 5. IRR = 29.98 %
- 6. IRR = 7.097 %