A project costs €20 000 today and returns €4 500 at the end of each year for 6 years. The required rate of return is 6%. Find the profitability index PI.
NPV & IRR worksheet with answers
A project costs €80 000 today and returns €33 500 at the end of each year for 3 years. The required rate of return is 5%. Find the net present value NPV.
An investment of €30 000 gives these cash flows at the end of years 1 to 3: €8 000, €11 000, €9 000. The cost of capital is 6%. Find the net present value NPV.
An investment of €20 000 gives these cash flows at the end of years 1 to 4: €9 000, €6 000, €9 000, €9 000. The cost of capital is 7.000000000000001%. Find the net present value NPV.
A project costs €25 000 and returns €15 000, €14 500 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
A project costs €50 000 and returns €27 000, €30 000 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
Answer key
- 1. PI = 1.106
- 2. NPV = 11229 €
- 3. NPV = −5106 €
- 4. NPV = 7865 €
- 5. IRR = 11.85 %
- 6. IRR = 9.03 %