A project costs €80 000 today and returns €24 000 at the end of each year for 5 years. The required rate of return is 6%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €25 000 today and returns €12 000 at the end of each year for 3 years. The required rate of return is 12%. Find the profitability index PI.
An investment of €75 000 gives these cash flows at the end of years 1 to 3: €30 000, €23 000, €35 000. The cost of capital is 7.000000000000001%. Find the net present value NPV.
A project costs €60 000 today and returns €18 500, €21 500, €19 500, €23 500 at the end of years 1 to 4. The cost of capital is 10%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
A project costs €20 000 and returns €10 500, €9 000, €11 500, €9 500 at the end of years 1 to 4. Cash flows can be reinvested at the cost of capital of 10%. Find the modified internal rate of return MIRR in percent.
An investment of €50 000 returns €9 500 at the end of each year for 8 years. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 21097 €
- 2. PI = 1.153
- 3. NPV = 1697 €
- 4. DPB = 3.671 years
- 5. MIRR = 23.82 %
- 6. IRR = 10.37 %
Full step-by-step solutions: practise this topic on examproblems.com.