A project costs €80 000 today and returns €45 000 at the end of each year for 3 years. The required rate of return is 9%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €50 000 today and returns €17 000 at the end of each year for 4 years. The required rate of return is 7.000000000000001%. Find the net present value NPV.
A project costs €40 000 today and returns €15 500, €15 000, €12 000, €16 500, €10 500 at the end of years 1 to 5. The cost of capital is 12%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €30 000 gives these cash flows at the end of years 1 to 3: €7 000, €10 000, €9 000. The cost of capital is 6%. Find the net present value NPV.
A project costs €50 000 and returns €28 000, €29 000 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
A project costs €10 000 and returns €7 000, €6 500 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 33908 €
- 2. NPV = 7583 €
- 3. DPB = 3.54 years
- 4. NPV = −6940 €
- 5. IRR = 9.142 %
- 6. IRR = 22.89 %