A project costs €50 000 today and returns €11 500 at the end of each year for 6 years. The required rate of return is 10%. Find the profitability index PI.
NPV & IRR worksheet with answers
A machine is expected to save €6 000, €8 000, €8 000 at the end of years 1 to 3, after which it is worthless. The required return is 8%. What is the most the company should pay for the machine today? Find PV.
An investment of €60 000 gives these cash flows at the end of years 1 to 4: €25 000, €21 000, €18 000, €13 000. The cost of capital is 5%. Find the net present value NPV.
A project costs €400 000 today. It generates €31 000 at the end of the first year, and the cash flow then grows by 2% per year forever. The cost of capital is 9%. Find the net present value NPV.
A project costs €25 000 and returns €16 500, €12 000, €15 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €40 000 and returns €26 000, €29 000 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
Answer key
- 1. PI = 1.002
- 2. PV = 18765 €
- 3. NPV = 9101 €
- 4. NPV = 42857 €
- 5. IRR = 34.7 %
- 6. IRR = 23.64 %
Full step-by-step solutions: practise this topic on examproblems.com.