A project costs €100 000 today and returns €30 000 at the end of each year for 5 years. The required rate of return is 10%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €50 000 today and returns €24 500 at the end of each year for 3 years. The required rate of return is 12%. Find the net present value NPV.
An investment of €20 000 gives these cash flows at the end of years 1 to 3: €8 000, €6 000, €7 000. The cost of capital is 15%. Find the net present value NPV.
A project costs €400 000 today. It generates €26 000 at the end of the first year, and the cash flow then grows by 4% per year forever. The cost of capital is 9%. Find the net present value NPV.
A project costs €25 000 and returns €17 500, €16 000 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
A project costs €20 000 and returns €14 500, €13 500 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
Answer key
- 1. NPV = 13724 €
- 2. NPV = 8845 €
- 3. NPV = −3904 €
- 4. NPV = 120000 €
- 5. IRR = 22.32 %
- 6. IRR = 26.05 %
Full step-by-step solutions: practise this topic on examproblems.com.