A project costs €50 000 today and returns €17 000, €15 500, €13 000, €15 500, €13 500, €13 500 at the end of years 1 to 6. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
NPV & IRR worksheet with answers
A project costs €40 000 today and returns €15 500, €12 000, €15 500, €8 000 at the end of years 1 to 4. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
A machine costs €40 000 today. It generates €12 500 at the end of each year for 4 years and can then be sold for €6 000. The cost of capital is 8%. Find the net present value NPV.
A project costs €20 000 today and returns €7 500, €5 500, €8 000, €4 000, €5 500, €4 500 at the end of years 1 to 6. The cost of capital is 8%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
A project costs €25 000 and returns €17 000, €14 500, €12 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €25 000 and returns €13 000, €15 000, €14 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. PB = 3.29 years
- 2. PB = 2.806 years
- 3. NPV = 5812 €
- 4. DPB = 3.677 years
- 5. IRR = 36.35 %
- 6. IRR = 31.32 %