A project costs €40 000 today and returns €7 000 at the end of each year for 7 years. The required rate of return is 8%. Find the profitability index PI.
NPV & IRR worksheet with answers
A machine is expected to save €18 000, €25 000, €8 000, €12 000 at the end of years 1 to 4, after which it is worthless. The required return is 12%. What is the most the company should pay for the machine today? Find PV.
An investment of €75 000 gives these cash flows at the end of years 1 to 3: €23 000, €16 000, €23 000. The cost of capital is 10%. Find the net present value NPV.
An investment of €30 000 gives these cash flows at the end of years 1 to 4: €14 000, €14 000, €7 000, €8 000. The cost of capital is 15%. Find the net present value NPV.
A project costs €25 000 and returns €12 000, €12 500, €16 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €25 000 and returns €18 000, €14 000 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
Answer key
- 1. PI = 0.9111
- 2. PV = 49322 €
- 3. NPV = −23588 €
- 4. NPV = 1937 €
- 5. IRR = 27.03 %
- 6. IRR = 19.04 %
Full step-by-step solutions: practise this topic on examproblems.com.