A project costs €60 000 today and returns €11 500, €21 000, €22 500, €13 000, €12 500, €14 500 at the end of years 1 to 6. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
NPV & IRR worksheet with answers
A project costs €20 000 today and returns €4 500 at the end of each year for 8 years. The required rate of return is 8%. Find the profitability index PI.
A project costs €20 000 today and returns €4 500, €6 000, €8 000, €5 500, €4 000 at the end of years 1 to 5. The cost of capital is 12%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
A project costs €60 000 today and returns €21 500 at the end of each year for 4 years. The cost of capital is 12%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
Project A costs €30 000 and returns €17 500, €12 500, €7 000 at the end of years 1 to 3. Project B costs €35 000 and returns €9 500, €15 500, €19 000. Find the crossover rate r* at which both projects have the same NPV, in percent.
A project costs €10 000 and returns €5 500, €7 500 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
Answer key
- 1. PB = 3.385 years
- 2. PI = 1.293
- 3. DPB = 4.885 years
- 4. DPB = 3.612 years
- 5. r* = 6.762 %
- 6. IRR = 18.36 %