A project costs €20 000 today and returns €4 000, €7 500, €7 000, €7 500 at the end of years 1 to 4. Assume cash flows arrive evenly through each year. Find the payback period PB in years.
NPV & IRR worksheet with answers
A project costs €10 000 today and returns €4 000 at the end of each year for 4 years. The required rate of return is 15%. Find the net present value NPV.
A project costs €60 000 today and returns €19 000 at the end of each year for 6 years. The cost of capital is 12%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
A project costs €50 000 today and returns €21 000, €22 500, €20 500, €11 500, €13 000, €10 500 at the end of years 1 to 6. The cost of capital is 12%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
A project costs €40 000 and returns €14 000, €14 500, €18 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €10 000 and returns €3 500, €6 000, €6 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Answer key
- 1. PB = 3.2 years
- 2. NPV = 1420 €
- 3. DPB = 4.212 years
- 4. DPB = 2.912 years
- 5. IRR = 7.579 %
- 6. IRR = 24.81 %
Full step-by-step solutions: practise this topic on examproblems.com.