A project costs €50 000 today and returns €20 000 at the end of each year for 5 years. The required rate of return is 15%. Find the net present value NPV.
NPV & IRR worksheet with answers
A project costs €10 000 today and returns €2 500 at the end of each year for 5 years. The required rate of return is 9%. Find the net present value NPV.
A project costs €20 000 today and returns €7 500, €6 500, €9 000, €7 000, €8 500, €5 500 at the end of years 1 to 6. The cost of capital is 12%. Assume cash flows arrive evenly through each year. Find the discounted payback period DPB in years.
An investment of €30 000 gives these cash flows at the end of years 1 to 3: €15 000, €14 000, €14 000. The cost of capital is 8%. Find the net present value NPV.
A project costs €20 000 and returns €7 500, €7 500, €10 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
A project costs €80 000 today. Its cash flow is €11 500 at the end of year 1 and grows by 2% per year until the last cash flow at the end of year 7. The cost of capital is 10%. Find the net present value NPV.
Answer key
- 1. NPV = 17043 €
- 2. NPV = −275.9 €
- 3. DPB = 3.386 years
- 4. NPV = 7005 €
- 5. IRR = 11.43 %
- 6. NPV = −20984 €