A project costs €20 000 today and returns €10 000 at the end of each year for 3 years. The required rate of return is 6%. Find the net present value NPV.
NPV & IRR worksheet with answers
A machine is expected to save €5 000, €10 000, €20 000 at the end of years 1 to 3, after which it is worthless. The required return is 6%. What is the most the company should pay for the machine today? Find PV.
An investment of €30 000 gives these cash flows at the end of years 1 to 3: €9 000, €10 000, €12 000. The cost of capital is 10%. Find the net present value NPV.
An investment of €45 000 gives these cash flows at the end of years 1 to 3: €19 000, €17 000, €14 000. The cost of capital is 10%. Find the net present value NPV.
A project costs €40 000 and returns €27 000, €19 000, €16 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
Project A costs €10 000 and returns €5 500, €4 000, €2 500 at the end of years 1 to 3. Project B costs €15 000 and returns €4 000, €6 000, €7 500. Find the crossover rate r* at which both projects have the same NPV, in percent.
Answer key
- 1. NPV = 6730 €
- 2. PV = 30409 €
- 3. NPV = −4538 €
- 4. NPV = −3159 €
- 5. IRR = 28.61 %
- 6. r* = 3.029 %