Name: ____________________   Date: ____________

1.Easy
b = 5 my = 2.2 mn = 0.014

Water flows uniformly 2.2 m deep in a rectangular unfinished concrete channel 5 m wide (Manning n = 0.014). The bed slope is S = 0.0005. Use Manning’s equation in SI units to find the mean velocity V.

b = 5 my = 2.2 mn = 0.014S = 0.0005
V = m/s
2.Easy
b = 1 my = 2.3 mn = 0.03

Water flows uniformly 2.3 m deep in a rectangular grass-lined earth channel 1 m wide (Manning n = 0.03). The bed slope is S = 0.001. Use Manning’s equation in SI units to find the mean velocity V.

b = 1 my = 2.3 mn = 0.03S = 0.001
V = m/s
3.Medium
D = 750 mmn = 0.013, S = 0.0008

A concrete storm sewer with an inside diameter of 750 mm flows just full (as an open channel, not under pressure). Manning n = 0.013 and the slope is S = 0.0008. Find the flow rate Q in m³/s.

D = 750 mmn = 0.013S = 0.0008
Q = m³/s
4.Medium
b = 2 my = 1.5 m1.5 : 1n = 0.015, S = 0.0015

A trapezoidal brickwork channel has a bottom width of 2 m and side slopes of 1.5:1 (horizontal:vertical). Water flows uniformly 1.5 m deep. Manning n = 0.015 and the bed slope is S = 0.0015. Find the flow rate Q in m³/s.

b = 2 my = 1.5 mz = 1.5n = 0.015S = 0.0015
Q = m³/s
5.Hard
D = 200 mmn = 0.013, V = 0.9 m/s

A concrete sewer with an inside diameter of 200 mm (Manning n = 0.013) must reach a self-cleansing velocity of 0.9 m/s when flowing just full. Find the minimum slope S (in m/m).

D = 200 mmn = 0.013V = 0.9 m/s
S = m/m
6.Hard
b = 4.5 my = 1.7 m1 : 1n = 0.014, Q = 18 m³/s

A trapezoidal unfinished concrete channel with a bottom width of 4.5 m and side slopes of 1:1 (horizontal:vertical) must carry 18 m³/s in uniform flow at a depth of 1.7 m. Manning n = 0.014. Find the required bed slope S (in m/m).

Q = 18 m³/sb = 4.5 my = 1.7 mz = 1n = 0.014
S = m/m

Answer key

  1. 1. V = 1.774 m/s
  2. 2. V = 0.5824 m/s
  3. 3. Q = 0.3149 m³/s
  4. 4. Q = 14.89 m³/s
  5. 5. S = 0.007432 m/m
  6. 6. S = 0.0004844 m/m