Water flows uniformly 1.9 m deep in a rectangular brickwork channel 5 m wide (Manning n = 0.015). The bed slope is S = 0.005. Use Manning’s equation in SI units to find the mean velocity V.
Open-channel flow (Manning) worksheet with answers
Water flows uniformly 0.9 m deep in a rectangular clean earth channel 1 m wide (Manning n = 0.022). The bed slope is S = 0.001. Use Manning’s equation in SI units to find the mean velocity V.
A rectangular unfinished concrete channel is 5.5 m wide. Water flows uniformly 0.7 m deep. Manning n = 0.014 and the bed slope is S = 0.003. Find the flow rate Q in m³/s.
A trapezoidal finished concrete channel has a bottom width of 4 m and side slopes of 1:1 (horizontal:vertical). Water flows uniformly 2.3 m deep. Manning n = 0.012 and the bed slope is S = 0.002. Find the flow rate Q in m³/s.
A rectangular brickwork channel 2 m wide must carry 3.4 m³/s in uniform flow at a depth of 0.8 m. Manning n = 0.015. Find the required bed slope S (in m/m).
A rectangular finished concrete channel 3.5 m wide must carry 19 m³/s in uniform flow at a depth of 2.1 m. Manning n = 0.012. Find the required bed slope S (in m/m).
Answer key
- 1. V = 4.961 m/s
- 2. V = 0.6745 m/s
- 3. Q = 10.21 m³/s
- 4. Q = 66.91 m³/s
- 5. S = 0.002996 m/m
- 6. S = 0.001024 m/m
Full step-by-step solutions: practise this topic on examproblems.com.