FE Civil exam practice: cram pack

Formula sheets, the key method steps for every topic and 30 practice problems, with full solutions at the back.

New problemsBack to the course

In the print window, choose “Save as PDF” to keep a copy on your device.

1Formulas and methods

Beam support reactions

Equilibrium
ΣFx = 0, ΣFy = 0, ΣM = 0
Uniform load
resultant w·L at the middle of the load
Moment
M = F·d

Method

  1. Draw a free-body diagram and replace each support by its reactions.
  2. Replace every distributed load by a single force at its centroid.
  3. Take moments about one support to find the reaction at the other.
  4. Use ΣFy = 0 to find the remaining reaction, and check with a second moment equation.

Truss: method of joints

Method of joints
ΣFx = 0, ΣFy = 0 at each joint
Method of sections
ΣM = 0 about a cut point
Member force
positive = tension, negative = compression

Method

  1. Find the support reactions for the whole truss.
  2. Method of joints: start at a joint with at most two unknown member forces and use ΣFx = 0 and ΣFy = 0.
  3. Method of sections: cut through the member you need and take moments about a point where the other unknown members meet.
  4. Assume tension; a negative answer means compression.

Shear force & bending moment

Shear and moment
V = ΣF on one side, M = ΣF·d on one side
Bending stress
σ = M·y/I
Rectangle
I = bh³/12
Section modulus
W = I/ymax
Simply supported, uniform load
Mmax = wL²/8

Method

  1. Find the support reactions from equilibrium of the whole beam.
  2. Cut the beam at the section you need and keep one side.
  3. Shear force: sum of the vertical forces on that side. Bending moment: sum of their moments about the cut.
  4. For the maximum moment, find where the shear force is zero.

Beam deflection

Point load at midspan
δ = PL³/(48EI)
Uniform load, simply supported
δ = 5wL⁴/(384EI)
Cantilever, end load
δ = PL³/(3EI)
Cantilever, uniform load
δ = wL⁴/(8EI)
Superposition
δ = δ1 + δ2

Column buckling

Euler load
Pcr = π²EI/(KL)²
Effective length factor
K = 1 pinned–pinned, 0.5 fixed–fixed, 0.7 fixed–pinned, 2 fixed–free
Critical stress
σcr = Pcr/A
Slenderness
λ = KL/r, r = √(I/A)

Centroid & second moment of area

Centroid
ȳ = ΣAiyi/ΣAi
Rectangle
I = bh³/12
Parallel-axis theorem
I = Ic + A·d²
Composite section
I = Σ(Ic,i + Aidi²)

Effective stress in soil

Total stress
σ = Σγi·hi
Pore water pressure
u = γw·(z − zw)
Effective stress
σ′ = σ − u
Water
γw = 9.81 kN/m³

Consolidation settlement

Normally consolidated
S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0)
Final stress
σ′f = σ′0 + Δσ (at mid-depth of the layer)
Overconsolidated, σ′f ≤ σ′p
S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0)
Overconsolidated, σ′f > σ′p
S = H/(1 + e0)·[Cr·log₁₀(σ′p/σ′0) + Cc·log₁₀(σ′f/σ′p)]
Overconsolidation ratio
OCR = σ′p/σ′0
Time for consolidation
t = Tv·Hdr²/cv
Drainage path
Hdr = H/2 (double drainage), H (single drainage)
Time factors
U 50% → 0.197, 60% → 0.287, 70% → 0.403, 80% → 0.567, 90% → 0.848

Hydrostatic force

Pressure at depth
p = ρgh
Force on a vertical wall
F = ρg·hc·A
Centre of pressure
yp = yc + Ic/(ycA)
Rectangle
Ic = bH³/12

Pipe friction & head loss

Reynolds number
Re = V·D/ν = ρ·V·D/μ
Flow regime
laminar below Re ≈ 2000, turbulent above Re ≈ 4000
Mean velocity
V = Q/A, A = π·D²/4
Darcy–Weisbach
hf = f·(L/D)·V²/(2g)
Minor losses
hm = ΣK·V²/(2g)
Typical K values
entrance 0.5, exit 1.0, 90° bend ≈ 0.3
Pressure drop
Δp = ρ·g·hf
Two open reservoirs
Δz = (f·L/D + ΣK)·V²/(2g)
Free outlet
H = (1 + f·L/D + ΣK)·V²/(2g)

Open-channel flow (Manning)

Manning equation
V = (1/n)·R2/3·S1/2
Flow rate
Q = A·V
Hydraulic radius
R = A/P (P = wetted perimeter, free surface excluded)
Rectangle
A = b·y, P = b + 2y
Trapezoid (side slope z:1)
A = (b + z·y)·y, P = b + 2y·√(1 + z²)
Circular pipe, full or half full
R = D/4
Required slope
S = (n·Q/(A·R2/3))²

Pumps & pump power

Hydraulic power
Ph = ρ·g·Q·H = Q·Δp
Shaft power
Pshaft = Ph/ηpump
Electrical power
Pel = Pshaft/ηmotor
Pump head
H = Δz + Δp/(ρ·g) + hL
System losses
hL = (f·L/D + ΣK)·V²/(2g)

Time value of money

Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i

Method

  1. Draw a timeline with every cash flow and its timing.
  2. Match the rate to the period: a monthly rate for monthly payments.
  3. Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
  4. Check the sign and the order of magnitude of the answer.

NPV & IRR

Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)

Method

  1. List all cash flows with their year; the investment at year 0 is negative.
  2. Discount each cash flow: CFt/(1 + r)t.
  3. Add them up to get the NPV. Positive means the project earns more than r.
  4. For the IRR, find the rate that makes NPV zero by trial or interpolation.

Normal distribution

z-score
z = (x − μ)/σ
Below x
P(X < x) = Φ(z)
Above x
P(X > x) = 1 − Φ(z)
Between
Φ(z2) − Φ(z1)
Percentile
x = μ + z·σ

Method

  1. Convert the value to a z-score: z = (x − μ)/σ.
  2. Look up Φ(z), the area to the left of z.
  3. For the area to the right use 1 − Φ(z); for an interval subtract the two left areas.
  4. For a percentile, work backwards: find z for the area, then x = μ + z·σ.

2Practice problems

1.Beam support reactionsMedium
P1​ = 15 kNP2​ = 15 kNABRA​RB​ = ?3 m3 m2 m

The simply supported beam has a pin at A and a roller at B. Find the vertical support reaction RB.

L = 8 mP1 = 15 kN at 3 mP2 = 15 kN at 6 m
RB = kN
2.Beam support reactionsHard
P = 35 kNQ = 35 kNADCMA​ = ?2 m2 m2 m2 m

A compound beam is fixed to the wall at A, has an internal hinge at C (4 m from A) and rests on a roller at D (8 m from A). It carries a point load P at 6 m from A and a point load Q at 2 m from A. Find the magnitude of the reaction moment MA at the wall.

AC = 4 mAD = 8 mP = 35 kN at 6 mQ = 35 kN at 2 m
MA = kN·m
3.Truss: method of jointsMedium
ABBCACACB35 kN5 m4 m4 m

Use the method of joints to find the force FBC in member BC. Give tension as positive and compression as negative.

span = 5 mheight = 4 mB is 4 m from Avertical load = 35 kN
FBC = kN
4.Truss: method of jointsHard
ABCDEFGH30 kN20 kN35 kN4 × 3 m4 m

Exactly one member of this truss carries no force under these loads. Which is the zero-force member? Click it in the diagram.

D: 30 kN ↓G: 20 kN ↓H: 35 kN ←
  1. 1member AB
  2. 2member BC
  3. 3member CD
  4. 4member DE
  5. 5member FG
  6. 6member GH
  7. 7member AF
  8. 8member HE
  9. 9member BF
  10. 10member CG
  11. 11member DH
  12. 12member FC
  13. 13member HC
5.Shear force & bending momentMedium
P1​ = 65 kNP2​ = 60 kNABC1 m3 m2 m

The beam rests on a pin at A and a roller at B and overhangs B by 2 m to the free end C. It carries a point load P1 between the supports and a point load P2 at C. Find the bending moment Mx under the load P1. Use sagging moments positive and upward shear on the left face positive.

L = 6 mP1 = 65 kN at 1 mP2 = 60 kN at 6 msupports at x = 0 and x = 4 m
Mx = kN·m
6.Shear force & bending momentHard
30 kN35 kN10 kNABCDEFG2 m2 m2 m2 m2 m2 m

The marks A to G split the beam into six equal parts. At which mark is the bending moment largest in size, sagging or hogging? Click it in the diagram.

30 kN @ 0 m35 kN @ 12 m10 kN @ 6 m
  1. 1A (x = 0 m)
  2. 2B (x = 2 m)
  3. 3C (x = 4 m)
  4. 4D (x = 6 m)
  5. 5E (x = 8 m)
  6. 6F (x = 10 m)
  7. 7G (x = 12 m)
7.Beam deflectionMedium
w = 12 kN/mδL = 1.5 m

A cantilever carries a uniformly distributed load w over its whole length. Find the deflection δ at the free end.

w = 12 kN/mL = 1.5 mE = 70 GPa (aluminium)I = 36 × 10⁶ mm⁴
δ = mm
8.Beam deflectionHard
P = 17 kNABδ6.5 m1.5 m

A simply supported beam carries a point load P at b = 1.5 m from support B. Find the maximum deflection δmax of the beam.

P = 17 kNb = 1.5 mL = 8 mE = 11 GPa (timber)I = 120 × 10⁶ mm⁴
δmax = mm
9.Column bucklingMedium
PL = 2 m50 × 100 mmcross-section

A column of length L made of steel is pinned at both ends. Using Euler’s formula, find its critical buckling load Pcr.

L = 2 mE = 200 GPa (steel)b × h = 50 × 100 mm
Pcr = kN
10.Column bucklingHard
PL = 3 md = 50 mmcross-section

A column of length L made of aluminium is fixed at the base and pinned at the top. Find its slenderness and the critical buckling stress σcr from Euler’s formula.

L = 3 mE = 70 GPa (aluminium)d = 50 mm
σcr = MPa
11.Centroid & second moment of areaMedium
300140t = 16ȳ = ?dimensions in mm

A channel section lies with its open side up: a base plate 300 mm wide with two upright legs, 140 mm high overall. Base and legs are all 16 mm thick. Find the height ȳ of the centroid above the bottom edge.

b = 300 mmh = 140 mmt = 16 mm
ȳ = mm
12.Centroid & second moment of areaHard
150 mm240 mm72 mm80 × 50xIx​ = ?

A 150 mm × 240 mm plate has a rectangular cut-out 80 mm wide and 50 mm high, centred on the vertical centre line with its centre 72 mm above the bottom. Find the second moment of area Ix about the horizontal axis through the centroid.

b = 150 mmh = 240 mmcut-out: 80 × 50 mmhole centre: y = 72 mm
Ix = × 10⁶ mm⁴
13.Effective stress in soilMedium
sandγd​ = 17 kN/m³γsat​ = 20 kN/m³13 mwater tableXz = 10 m

For the soil profile shown, find the total vertical stress σ at point X.

z = 10 mzw = 4 mγw = 9.81 kN/m³sand: γd = 17 kN/m³sand: γsat = 20 kN/m³
σ = kPa
14.Effective stress in soilHard
sandγd​ = 15 kN/m³γsat​ = 18.5 kN/m³3 mclayγsat​ = 19 kN/m³6 mwater tableXz = 6 m

For the soil profile shown, find the vertical effective stress σ′ at point X.

z = 6 mzw = 1 mγw = 9.81 kN/m³sand: γd = 15 kN/m³sand: γsat = 18.5 kN/m³clay: γsat = 19 kN/m³
σ′ = kPa
15.Consolidation settlementMedium
Δσ = 150 kPasandclayCc​ = 0.4, Cr​ = 0.05e0​ = 0.9σ′0​ = 45 kPaOCR = 1.54.5 mwater table

A 4.5 m thick overconsolidated clay layer has Cc = 0.4, Cr = 0.05 and e₀ = 0.9. At its mid-depth the effective vertical stress is 45 kPa and the overconsolidation ratio is OCR = 1.5. A new building adds 150 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.

H = 4.5 mCc = 0.4Cr = 0.05e0 = 0.9σ′0 = 45 kPaOCR = 1.5Δσ = 150 kPa
S = mm
16.Consolidation settlementHard
sandclayH = 6.5 mcv​ = 0.8 m²/year6.5 mimpervious rockwater table

A clay layer 6.5 m thick has a coefficient of consolidation cv = 0.8 m²/year. It lies on impervious rock, with sand above it, so water drains out only at the top. For 80% average consolidation the time factor is Tv = 0.567. How many years t does the layer take to reach 80% consolidation?

H = 6.5 mcv = 0.8 m²/yearU = 80%Tv = 0.567single drainage
t = years
17.Hydrostatic forceMedium
gated = 1.5 mH = 2.5 m

A vertical rectangular gate 2 m wide sits in the wall of a tank of water, with its top edge 1.5 m below the surface. Find the resultant hydrostatic force F on the gate.

d = 1.5 mH = 2.5 mb = 2 mρ = 1000 kg/m³g = 9.81 m/s²
F = kN
18.Hydrostatic forceHard
gated = 4 mH = 3 m

A vertical rectangular gate 1 m wide sits in the wall of a tank of water, with its top edge 4 m below the surface. Find the depth ycp of the centre of pressure below the surface.

d = 4 mH = 3 mb = 1 mρ = 1000 kg/m³g = 9.81 m/s²
ycp = m
19.Pipe friction & head lossMedium
Q = 10 L/sD = 100 mmL = 150 mf = 0.025

Water flows at 10 L/s through a pipe 150 m long with an inside diameter of 100 mm. Use the Darcy friction factor f = 0.025 and g = 9.81 m/s². Find the friction head loss hf.

Q = 10 L/sL = 150 mD = 100 mmf = 0.025g = 9.81 m/s²
hf = m
20.Pipe friction & head lossHard
K = 5Δz = 30 mL = 300 m, D = 300 mm, f = 0.0254× bend (K = 0.3)

Two open reservoirs are joined by a pipe 300 m long with an inside diameter of 300 mm and a Darcy friction factor f = 0.025. The water surface of the upper reservoir is 30 m above that of the lower one. The minor losses are a square-edged entrance (K = 0.5), 4 bends (K = 0.3 each), a valve (K = 5) and the exit into the lower reservoir (K = 1.0). Use g = 9.81 m/s². Find the flow rate Q in L/s.

Δz = 30 mL = 300 mD = 300 mmf = 0.025Kentrance = 0.5Kbend = 0.3 (×4)Kvalve = 5Kexit = 1.0
Q = L/s
21.Open-channel flow (Manning)Medium
D = 300 mmn = 0.013, S = 0.0015

A concrete storm sewer with an inside diameter of 300 mm flows just full (as an open channel, not under pressure). Manning n = 0.013 and the slope is S = 0.0015. Find the flow rate Q in m³/s.

D = 300 mmn = 0.013S = 0.0015
Q = m³/s
22.Open-channel flow (Manning)Hard
b = 4.5 my = 1.1 mn = 0.025, Q = 7.2 m³/s

A rectangular gravel channel 4.5 m wide must carry 7.2 m³/s in uniform flow at a depth of 1.1 m. Manning n = 0.025. Find the required bed slope S (in m/m).

Q = 7.2 m³/sb = 4.5 my = 1.1 mn = 0.025
S = m/m
23.Pumps & pump powerMedium
PQ = 20 L/sH = 44 m

A pump delivers 20 L/s of water (ρ = 1000 kg/m³) against a head of 44 m. The pump efficiency is 75% and the electric motor driving it has an efficiency of 95%. Use g = 9.81 m/s². Find the electrical power Pel the motor draws, in kW.

Q = 20 L/sH = 44 mηpump = 75%ηmotor = 95%g = 9.81 m/s²
Pel = kW
24.Pumps & pump powerHard
PQ = 80 L/sΔz = 18 mL = 200 m, D = 200 mm, f = 0.02, ΣK = 5

A pump moves 80 L/s of water (ρ = 1000 kg/m³) from an open lower reservoir to an upper tank whose water surface is 18 m higher. The pipe is 200 m long with an inside diameter of 200 mm and a Darcy friction factor f = 0.02; the minor-loss coefficients add up to ΣK = 5 (entrance and exit included). Use g = 9.81 m/s². The pump efficiency is 82%. Find the shaft power Pshaft in kW.

Q = 80 L/sΔz = 18 mL = 200 mD = 200 mmf = 0.02ΣK = 5η = 82%
Pshaft = kW
25.Time value of moneyMedium
years0123…16PV = ?€3 000€3 000€3 000€3 000

An annuity pays €3 000 at the end of each year for 16 years. The interest rate is 4% per year. Find the present value PV of the annuity.

A = €3 000i = 4%n = 16
PV = €
26.Time value of moneyHard
years0123…8€2 500€2 500€2 500FV = ?

You deposit €2 500 at the start of every year for 8 years, the first deposit today. The account pays 3% per year. How much is in the account at the end of year 8? Find FV.

A = €2 500i = 3%n = 8
FV = €
27.NPV & IRRMedium
years0123−60 00024 00021 00021 000

An investment of €60 000 gives these cash flows at the end of years 1 to 3: €24 000, €21 000, €21 000. The cost of capital is 15%. Find the net present value NPV.

r = 15%CF0 = −60 000CF1 = 24 000CF2 = 21 000CF3 = 21 000
NPV = €
28.NPV & IRRHard
years0123−50 00031 00025 00026 500

A project costs €50 000 and returns €31 000, €25 000, €26 500 at the end of years 1 to 3. Find its internal rate of return IRR in percent.

CF0 = −50 000CF1 = 31 000CF2 = 25 000CF3 = 26 500
IRR = %
29.Normal distributionMedium
−3−2−10123zshaded area between −z and z = 0.8098

Drag z so that the shaded area between −z and z under the standard normal curve is 0.8098. Find z to two decimals.

A = 0.8098
z =
30.Normal distributionHard
10 g0X − Y?

The mass X of a product from line 1 and Y from line 2 are independent and normal: X has mean 500 g and standard deviation 8 g, Y has mean 490 g and standard deviation 6 g. Find the probability P that X is greater than Y. Round z to two decimals.

μX = 500 g, σX = 8 gμY = 490 g, σY = 6 g
P =

3Solutions

1.Beam support reactions

Answer: RB = 16.88 kN

Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Taking moments about one support removes that support’s reaction from the equation.

P1​ = 15 kNP2​ = 15 kNABRA​RB​3 m3 m2 m

Free-body diagram

Replace the supports with reaction forces. A roller gives one vertical reaction; with only vertical loads the pin gives one vertical reaction too.

Equilibrium

Moments about A, counter-clockwise positive. Then vertical force balance.

ΣMA = 0: RB·8 = 15·3 + 15·6
RB = 135/8 = 16.88 kN
ΣFy = 0: RA = 30 − 16.88 = 13.13 kN

Answer

RB = 16.88 kN
2.Beam support reactions

Answer: MA = 140 kN·m

Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Replace each distributed load by its resultant (its area) acting at the centroid of the load diagram, and take moments about a support to remove that support’s reaction from the equation. An internal hinge cannot carry a bending moment, which gives one extra equation: the moment about the hinge of the forces on either side is zero.

Part CD

The hinge has no moment, so moments about C on CD alone must balance.

ΣMC = 0: RD·4 = 35·2
RD = 17.5 kN
VC = 35 − 17.5 = 17.5 kN

Part AC

The hinge force VC acts downward on AC (equal and opposite to its action on CD).

RA = 35 + 17.5 = 52.5 kN
MA = 35·2 + 17.5·4 = 140 kN·m

Answer

MA = 140 kN·m
3.Truss: method of joints

Answer: FBC = −28.86 kN

Method of joints: every pin of a truss is in equilibrium, so ΣFx = 0 and ΣFy = 0 at each joint. Start at a joint with at most two unknown member forces. A negative result means the member is in compression.

ABBCACACB35 kNAy​Cy​

Support reactions

Equilibrium of the whole truss. Moments about A, counter-clockwise positive.

ΣMA = 0: Cy·5 = 35·4 → Cy = 28 kN
ΣFy = 0: Ay = 35 − 28 = 7 kN

Joint C

The roller gives only a vertical reaction, so joint C has just two unknown member forces. Assume both in tension.

sin γ = 4/4.123 = 0.9701, cos γ = 1/4.123 = 0.2425
ΣFy = 0: Cy + FBC·sin γ = 0 → FBC = −28/0.9701 = −28.86 kN

Answer

FBC = −28.86 kN (compression)
4.Truss: method of joints

Answer: member BF

Zero-force members: at a joint, the forces must balance in every direction. If a joint has no load and no support, and two of its three members are in line, then the balance across that line involves only the third member, so its force is zero. If only two members meet at an unloaded joint and they are not in line, both are zero.

Joint B

AB and BC lie on one straight line and the joint carries no load. Balancing forces across that line leaves only BF.

ΣF⊥ = 0 → FBF = 0

Check with the method of joints

Solving all joints gives these member forces (T = tension, C = compression).

AB: 13.12 kN (C), BC: 13.12 kN (C), CD: 15.62 kN (T), DE: 15.62 kN (T), FG: 43.75 kN (C), GH: 43.75 kN (C), AF: 36.46 kN (C), HE: 26.04 kN (C), BF: 0, CG: 20 kN (C), DH: 30 kN (T), FC: 36.46 kN (T), HC: 11.46 kN (C)

Answer

Zero-force member: BF
5.Shear force & bending moment

Answer: Mx = 18.75 kN·m

Method of sections: cut the beam where you want the internal forces and keep one side. The shear force V balances the vertical forces on that side, and the bending moment M balances their moments about the cut.

Support reactions

Equilibrium of the whole beam. The overhang load also acts about A.

ΣMA = 0: RB·4 = 65·1 + 60·6
RB = 425/4 = 106.3 kN
ΣFy = 0: RA = 125 − 106.3 = 18.75 kN

Cut under P1 and keep the left part

Mx = RA·1 = 18.75·1 = 18.75 kN·m

Answer

Mx = 18.75 kN·m
6.Shear force & bending moment

Answer: F (x = 10 m)

Largest bending moment: M changes slope wherever the shear force changes, so its peaks sit where the shear force crosses zero: under a point load, inside a distributed load, or over a support of an overhang. At a fixed support of a cantilever the moment is largest at the wall. Compare the size of M at those places, sagging or hogging.

Support reactions

Take moments about one support, then use the vertical force balance.

R1 = 33.75 kN, R2 = 41.25 kN

Bending moment at every mark

Sum the moments of all forces on one side of the cut. Sagging is positive, hogging negative.

MA = 0, MB = −60, MC = −52.5, MD = −45, ME = −57.5, MF = −70 kN·m, MG = 0

Answer

Mark F: MF = −70 kN·m
7.Beam deflection

Answer: δ = 3.013 mm

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).

Consistent units

Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.

w = 12 N/mm, L = 1500 mm
EI = 2.52 × 10¹² N·mm²

Deflection

δ = wL⁴/(8EI) = 12·1500⁴/(8·2.52 × 10¹²) = 3.013 mm

Answer

δ = 3.013 mm
8.Beam deflection

Answer: δmax = 75.17 mm

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).

Consistent units

Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.

P = 17000 N, b = 1500 mm, L = 8000 mm
EI = 1.32 × 10¹² N·mm²

Position of the maximum

Setting the slope in the longer segment to zero gives the position.

x = √((L² − b²)/3) = √((8000² − 1500²)/3) = 4537 mm

Maximum deflection

δmax = Pb(L² − b²)3/2/(9√3·EIL) = 75.17 mm

Answer

δmax = 75.17 mm
9.Column buckling

Answer: Pcr = 514 kN

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Smallest second moment of area

A rectangle buckles about its weak axis, using the smaller dimension cubed.

Imin = h·b³/12 = 100·50³/12 = 1.042 × 10⁶ mm⁴

Effective length

KL = 1·2000 = 2000 mm

Critical load

Pcr = π²EI/(KL)² = π²·200000·1.042 × 10⁶/2000² = 514042 N = 514 kN

Answer

Pcr = 514 kN
10.Column buckling

Answer: σcr = 24.48 MPa

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Smallest second moment of area

A round section has the same I about every axis.

I = πd⁴/64 = π·50⁴/64 = 306796 mm⁴

Radius of gyration and slenderness

A = 1963 mm²
r = √(I/A) = √(306796/1963) = 12.5 mm
KL = 0.7·3000 = 2100 mm
KL/r = 2100/12.5 = 168

Critical stress

σcr = π²E/(KL/r)² = π²·70000/168² = 24.48 MPa

Answer

σcr = 24.48 MPa
11.Centroid & second moment of area

Answer: ȳ = 39.68 mm

Composite areas: split the section into rectangles. The centroid is the area-weighted average ȳ = ΣAᵢyᵢ/ΣAᵢ. The second moment of area about the centroidal axis adds each part’s own bh³/12 and its parallel-axis term A·d², where d is the distance from the part’s centroid to the overall centroid. Bending stress is σ = M·y/I.

Split into rectangles

Take the base at full width and the two legs above it (height h − t), so nothing is counted twice.

base: A1 = 300·16 = 4800 mm², y1 = 8 mm
two legs: A2 = 2·16·124 = 3968 mm², y2 = 16 + 124/2 = 78 mm

Centroid

ȳ = (4800·8 + 3968·78)/8768 = 39.68 mm

Answer

ȳ = 39.68 mm
12.Centroid & second moment of area

Answer: Ix = 161.6 × 10⁶ mm⁴

Sections with holes: treat a hole as a negative area. The centroid is ȳ = (A₁y₁ − A₂y₂)/(A₁ − A₂), with A₁, y₁ for the full plate and A₂, y₂ for the hole. For the second moment of area about the centroidal axis, use the parallel-axis theorem for each part and subtract the hole: I = (Ic1 + A₁d₁²) − (Ic2 + A₂d₂²), where d is the distance from each part's own centroid to the axis through ȳ. A rectangle has Ic = bh³/12 and a circle Ic = πd⁴/64.

Centroid

ȳ = (36000·120 − 4000·72)/(36000 − 4000) = 126 mm

Full plate about ȳ

150·240³/12 + 36000·−6² = 174.1 × 10⁶ mm⁴

Hole about ȳ

80·50³/12 + 4000·−54² = 12.5 × 10⁶ mm⁴

Subtract

Ix = 161.6 × 10⁶ mm⁴

Answer

Ix = 161.6 × 10⁶ mm⁴
13.Effective stress in soil

Answer: σ = 188 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Total stress

Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.

σ = γd·zw + γsat·(z − zw) = 17·4 + 20·6 = 188 kPa

Answer

σ = 188 kPa
14.Effective stress in soil

Answer: σ′ = 59.95 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Total stress

Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.

σ = γd·1 + γsat,sand·2 + γsat,clay·3
σ = 15·1 + 18.5·2 + 19·3 = 109 kPa

Pore water pressure

Water pressure grows with depth below the water table.

u = γw·(z − zw) = 9.81·5 = 49.05 kPa

Effective stress

σ′ = σ − u = 109 − 49.05 = 59.95 kPa

Answer

σ′ = 59.95 kPa
15.Consolidation settlement

Answer: S = 457.3 mm

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Preconsolidation pressure

σ′p = OCR·σ′0 = 1.5·45 = 67.5 kPa

Compare with the preconsolidation pressure

σ′f = 45 + 150 = 195 kPa > 67.5 kPa

Settlement

Recompression up to σ′p, virgin compression beyond it.

S = 0.05·4.5/(1 + 0.9)·log₁₀(67.5/45) + 0.4·4.5/(1 + 0.9)·log₁₀(195/67.5)
S = 20.85 + 436.5 = 457.3 mm

Answer

S = 457.3 mm
16.Consolidation settlement

Answer: t = 29.94 years

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Drainage path

Hdr = H = 6.5 m

Time

t = Tv·Hdr²/cv = 0.567·6.5²/0.8 = 29.94 years

Answer

t = 29.94 years
17.Hydrostatic force

Answer: F = 134.9 kN

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 1.5 + 2.5/2 = 2.75 m
A = H·b = 2.5·2 = 5 m²
gated = 1.5 mH = 2.5 mF

Resultant force

F = ρ·g·yc·A = 1000·9.81·2.75·5 = 134.9 kN

Answer

F = 134.9 kN
18.Hydrostatic force

Answer: ycp = 5.636 m

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 4 + 3/2 = 5.5 m
A = H·b = 3·1 = 3 m²
gated = 4 mH = 3 mF

Resultant force

F = ρ·g·yc·A = 1000·9.81·5.5·3 = 161.9 kN

Centre of pressure

Pressure grows with depth, so the resultant acts below the centroid.

Ic = b·H³/12 = 1·3³/12 = 2.25 m⁴
ycp = yc + Ic/(yc·A) = 5.5 + 2.25/(5.5·3) = 5.636 m

Answer

ycp = 5.636 m
19.Pipe friction & head loss

Answer: hf = 3.099 m

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Mean velocity

A = π·0.1²/4 = 0.007854 m²
V = Q/A = 0.01/0.007854 = 1.273 m/s

Velocity head

V²/(2g) = 1.273²/(2·9.81) = 0.08263 m

Darcy–Weisbach

hf = f·(L/D)·V²/(2g) = 0.025·(150/0.1)·1.273²/(2·9.81) = 3.099 m

Answer

hf = 3.099 m
20.Pipe friction & head loss

Answer: Q = 299.9 L/s

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Loss coefficients

f·L/D = 0.025·300/0.3 = 25
ΣK = 0.5 + 4·0.3 + 5 + 1.0 = 7.7

Energy equation

Both surfaces are open to the air and practically at rest, so all of Δz is lost in the pipe.

30 = (25 + 7.7)·V²/(2·9.81)
V = √(2·9.81·30/32.7) = 4.243 m/s

Flow rate

Q = V·π·D²/4 = 4.243·0.07069 = 0.2999 m³/s = 299.9 L/s

Answer

Q = 299.9 L/s
21.Open-channel flow (Manning)

Answer: Q = 0.03745 m³/s

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Geometry

A = 0.07069 m², R = D/4 = 0.075 m

Velocity

V = (1/0.013)·0.0752/3·0.00151/2 = 0.5298 m/s

Flow rate

Q = A·V = 0.07069·0.5298 = 0.03745 m³/s

Answer

Q = 0.03745 m³/s
22.Open-channel flow (Manning)

Answer: S = 0.00198 m/m

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Geometry

A = b·y = 4.5·1.1 = 4.95 m²
P = b + 2y = 4.5 + 2·1.1 = 6.7 m
R = A/P = 0.7388 m

Solve Manning for S

S1/2 = n·Q/(A·R2/3) = 0.025·7.2/(4.95·0.8172) = 0.0445
S = 0.0445² = 0.00198

Answer

S = 0.00198

That is a fall of 1.98 m per kilometre.

23.Pumps & pump power

Answer: Pel = 12.12 kW

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Hydraulic power

Ph = ρ·g·Q·H = 1000·9.81·0.02·44 = 8.633 kW

Shaft power

Pshaft = 8.633/0.75 = 11.51 kW

Electrical power

Pel = 11.51/0.95 = 12.12 kW

Answer

Pel = 12.12 kW
24.Pumps & pump power

Answer: Pshaft = 25.14 kW

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Velocity

V = Q/A = 0.08/0.03142 = 2.546 m/s
V²/(2g) = 0.3305 m

Head losses

hL = (f·L/D + ΣK)·V²/(2g) = (20 + 5)·0.3305 = 8.263 m

Pump head

H = Δz + hL = 18 + 8.263 = 26.26 m

Shaft power

Pshaft = ρ·g·Q·H/η = 1000·9.81·0.08·26.26/0.82 = 25.14 kW

Answer

Pshaft = 25.14 kW
25.Time value of money

Answer: PV = 34957 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Annuity factor

(1 − (1 + i)−n)/i = (1 − 0.5339)/0.04 = 11.65

Present value

PV = 3 000·11.65 = €34 956.89

Answer

PV = €34 956.89
26.Time value of money

Answer: FV = 22898 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Ordinary annuity factor

((1 + 0.03)8 − 1)/0.03 = 8.892

Annuity due

Each deposit is invested one year longer.

FV = 2 500·8.892·1.03 = €22 897.77

Answer

FV = €22 897.77
27.NPV & IRR

Answer: NPV = −9444 €

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Present value of each cash flow

CF0 = −60 000
CF1/(1 + 0.15)1 = 24 000/1.15 = 20 869.57
CF2/(1 + 0.15)2 = 21 000/1.322 = 15 879.02
CF3/(1 + 0.15)3 = 21 000/1.521 = 13 807.84

Add them up

NPV = €−9 443.58

Answer

NPV = €−9 443.58

NPV is negative, so the project earns less than the required return.

28.NPV & IRR

Answer: IRR = 31.03 %

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Bracket the IRR

NPV falls as the rate rises, so the IRR lies between a rate with positive NPV and one with negative NPV.

NPV(30%) = 700.96
NPV(35%) = −2 548.90

Narrow down

Linear interpolation gives a first estimate; repeating it (or a calculator's IRR function) gives the exact rate.

IRR ≈ 30 + 5·700.96/(700.96 − (−2 548.90)) = 31.08%
exact: NPV(31.03%) = 0 → IRR = 31.03%

Answer

IRR = 31.03%
29.Normal distribution

Answer: z = 1.31

From an area back to z: Φ(z) is the area to the left of z. For a left-tail area A, find z with Φ(z) = A in the table. A right-tail area A means Φ(z) = 1 − A. A central area A between −z and z leaves (1 − A)/2 in each tail, so Φ(z) = (1 + A)/2. For a value x, use x = μ + zσ.

Area to the left of z

Φ(z) = (1 + 0.8098)/2 = 0.9049

Read the z-table backwards

Find 0.9049 inside the table and read off z.

z = 1.31

Answer

z = 1.31
30.Normal distribution

Answer: P = 0.8413

Sums and differences of normal variables: if X and Y are independent and normal, X + Y and X − Y are normal too. Means add or subtract: E(X ± Y) = μX ± μY. Variances always add, also for a difference: Var(X ± Y) = σX² + σY², so σ = √(σX² + σY²). Standard deviations never add directly. The total of n independent items with the same distribution has mean n·μ and standard deviation σ·√n. Then standardise as usual: z = (x − mean)/σ and read Φ(z).

Distribution of the difference

μ = 500 − 490 = 10 g, σ = 10 g

Standardise

z = (0 − 10)/10 = −1

Probability

P = 1 − Φ(−1) = 0.8413

Answer

P = 0.8413