laminar below Re ≈ 2000, turbulent above Re ≈ 4000
Mean velocity
V = Q/A, A = π·D²/4
Darcy–Weisbach
hf = f·(L/D)·V²/(2g)
Minor losses
hm = ΣK·V²/(2g)
Typical K values
entrance 0.5, exit 1.0, 90° bend ≈ 0.3
Pressure drop
Δp = ρ·g·hf
Two open reservoirs
Δz = (f·L/D + ΣK)·V²/(2g)
Free outlet
H = (1 + f·L/D + ΣK)·V²/(2g)
Open-channel flow (Manning)
Manning equation
V = (1/n)·R2/3·S1/2
Flow rate
Q = A·V
Hydraulic radius
R = A/P (P = wetted perimeter, free surface excluded)
Rectangle
A = b·y, P = b + 2y
Trapezoid (side slope z:1)
A = (b + z·y)·y, P = b + 2y·√(1 + z²)
Circular pipe, full or half full
R = D/4
Required slope
S = (n·Q/(A·R2/3))²
Pumps & pump power
Hydraulic power
Ph = ρ·g·Q·H = Q·Δp
Shaft power
Pshaft = Ph/ηpump
Electrical power
Pel = Pshaft/ηmotor
Pump head
H = Δz + Δp/(ρ·g) + hL
System losses
hL = (f·L/D + ΣK)·V²/(2g)
Time value of money
Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i
Method
Draw a timeline with every cash flow and its timing.
Match the rate to the period: a monthly rate for monthly payments.
Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
Check the sign and the order of magnitude of the answer.
NPV & IRR
Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)
Method
List all cash flows with their year; the investment at year 0 is negative.
Discount each cash flow: CFt/(1 + r)t.
Add them up to get the NPV. Positive means the project earns more than r.
For the IRR, find the rate that makes NPV zero by trial or interpolation.
Normal distribution
z-score
z = (x − μ)/σ
Below x
P(X < x) = Φ(z)
Above x
P(X > x) = 1 − Φ(z)
Between
Φ(z2) − Φ(z1)
Percentile
x = μ + z·σ
Method
Convert the value to a z-score: z = (x − μ)/σ.
Look up Φ(z), the area to the left of z.
For the area to the right use 1 − Φ(z); for an interval subtract the two left areas.
For a percentile, work backwards: find z for the area, then x = μ + z·σ.
2Practice problems
1.Beam support reactionsMedium
The cantilever beam is fixed to the wall at A. It carries a uniformly distributed load w along its whole length and a point load P at 5 m from the wall. Find the vertical reaction RA at the wall.
L = 6 mP = 50 kN at 5 mw = 6 kN/m from 0 to 6 m
RA = kN
2.Beam support reactionsHard
The simply supported beam has a pin at A and a roller at B. Find the vertical support reaction RA.
L = 8 mP = 60 kN at 6 mw = 10 kN/m from 4 to 7 m
RA = kN
3.Truss: method of jointsMedium
Use the method of joints to find the force FBC in member BC. Give tension as positive and compression as negative.
span = 5 mheight = 2 mB is 3 m from Avertical load = 20 kN
FBC = kN
4.Truss: method of jointsHard
Exactly one member of this truss carries no force under these loads. Which is the zero-force member? Click it in the diagram.
B: 40 kN ↓F: 35 kN →G: 25 kN ↓H: 30 kN ↓
1member AB
2member BC
3member CD
4member DE
5member FG
6member GH
7member AF
8member HE
9member BF
10member CG
11member DH
12member BG
13member DG
5.Shear force & bending momentMedium
The simply supported beam carries a clockwise couple M0 = 35 kN·m at x = 2.5 m from A, and no other load. Find the bending moment Mx just to the right of the couple. Use sagging moments positive and upward shear on the left face positive.
L = 6 mM0 = 35 kN·m clockwise, at 2.5 m
Mx = kN·m
6.Shear force & bending momentHard
The marks A to G split the beam into six equal parts. At which mark is the bending moment largest in size, sagging or hogging? Click it in the diagram.
15 kN @ 0 m55 kN @ 12 m
1A (x = 0 m)
2B (x = 2 m)
3C (x = 4 m)
4D (x = 6 m)
5E (x = 8 m)
6F (x = 10 m)
7G (x = 12 m)
7.Beam deflectionMedium
A simply supported beam carries a uniformly distributed load w over its whole span. Find the maximum deflection δmax, at midspan.
w = 10 kN/mL = 4 mE = 200 GPa (steel)I = 23 × 10⁶ mm⁴
δmax = mm
8.Beam deflectionHard
A simply supported beam carries a uniformly distributed load w and a point load P at midspan. Using superposition, find the midspan deflection δmax.
P = 7 kNw = 2 kN/mL = 2 mE = 11 GPa (timber)I = 12 × 10⁶ mm⁴
δmax = mm
9.Column bucklingMedium
A column of length L made of aluminium is fixed at the base and pinned at the top. Using Euler’s formula, find its critical buckling load Pcr.
L = 1.5 mE = 70 GPa (aluminium)b × h = 20 × 50 mm
Pcr = kN
10.Column bucklingHard
A column of length L made of aluminium is fixed at the base and pinned at the top. Find its slenderness and the critical buckling stress σcr from Euler’s formula.
L = 6 mE = 70 GPa (aluminium)d = 40 mm
σcr = MPa
11.Centroid & second moment of areaMedium
A 200 mm × 300 mm plate has a circular hole of diameter 40 mm on its vertical centre line, with its centre 90 mm above the bottom. Find the second moment of area Ix about the horizontal axis through the centroid.
b = 200 mmh = 300 mmd = 40 mmhole centre: y = 90 mm
Ix = × 10⁶ mm⁴
12.Centroid & second moment of areaHard
A cast-iron beam has the T-section shown, with the flange on top. The allowable stresses are 30 MPa in tension and 120 MPa in compression. Find the largest hogging bending moment Mallow the beam can carry (give its size).
A 7 m thick overconsolidated clay layer has Cc = 0.45, Cr = 0.02 and e₀ = 0.85. At its mid-depth the effective vertical stress is 105 kPa and the preconsolidation pressure is 215 kPa. A new building adds 25 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.
A clay layer 5.5 m thick has a coefficient of consolidation cv = 4 m²/year. It lies between two sand layers, so water drains out at the top and the bottom. For 90% average consolidation the time factor is Tv = 0.848. How many years t does the layer take to reach 90% consolidation?
A vertical rectangular gate 1 m wide sits in the wall of a tank of water, with its top edge 4 m below the surface. Find the resultant hydrostatic force F on the gate.
d = 4 mH = 2 mb = 1 mρ = 1000 kg/m³g = 9.81 m/s²
F = kN
18.Hydrostatic forceHard
A vertical rectangular gate 3 m wide sits in the wall of a tank of water, with its top edge 2 m below the surface. Find the depth ycp of the centre of pressure below the surface.
d = 2 mH = 3 mb = 3 mρ = 1000 kg/m³g = 9.81 m/s²
ycp = m
19.Pipe friction & head lossMedium
Water flows at a mean velocity of 1.3 m/s through a pipe 500 m long with an inside diameter of 50 mm. Use the Darcy friction factor f = 0.015 and g = 9.81 m/s². Find the friction head loss hf.
Two open reservoirs are joined by a pipe 150 m long with an inside diameter of 100 mm and a Darcy friction factor f = 0.02. The water surface of the upper reservoir is 11 m above that of the lower one. The minor losses are a square-edged entrance (K = 0.5), 3 bends (K = 0.3 each), a valve (K = 10) and the exit into the lower reservoir (K = 1.0). Use g = 9.81 m/s². Find the flow rate Q in L/s.
A rectangular finished concrete channel is 3.5 m wide. Water flows uniformly 1.8 m deep. Manning n = 0.012 and the bed slope is S = 0.0008. Find the flow rate Q in m³/s.
b = 3.5 my = 1.8 mn = 0.012S = 0.0008
Q = m³/s
22.Open-channel flow (Manning)Hard
A concrete sewer with an inside diameter of 200 mm (Manning n = 0.013) must reach a self-cleansing velocity of 0.75 m/s when flowing just full. Find the minimum slope S (in m/m).
D = 200 mmn = 0.013V = 0.75 m/s
S = m/m
23.Pumps & pump powerMedium
A pump with an efficiency of 60% delivers 15 L/s of water (ρ = 1000 kg/m³) against a head of 14 m. Use g = 9.81 m/s². Find the shaft power Pshaft needed, in kW.
Q = 15 L/sH = 14 mη = 60%g = 9.81 m/s²
Pshaft = kW
24.Pumps & pump powerHard
A pump moves 50 L/s of water (ρ = 1000 kg/m³) from an open lower reservoir to an upper tank whose water surface is 18 m higher. The pipe is 150 m long with an inside diameter of 150 mm and a Darcy friction factor f = 0.02; the minor-loss coefficients add up to ΣK = 4 (entrance and exit included). Use g = 9.81 m/s². The upper tank is closed and the air above its water is at a gauge pressure of 400 kPa. Find the head H the pump must add.
You invest €1 000 at 3% per year with continuous compounding. Find the value FV after 16 years.
PV = €1 000r = 3%t = 16
FV = €
26.Time value of moneyHard
You save €100 at the end of every month for 12 years. The account pays 4.2% per year, compounded monthly. How much have you saved at the end? Find FV.
A = €1004.2% / 12N = 144
FV = €
27.NPV & IRRMedium
An investment of €75 000 gives these cash flows at the end of years 1 to 3: €32 000, €24 000, €25 000. The cost of capital is 6%. Find the net present value NPV.
A project costs €50 000 and returns €35 500, €20 000, €24 000 at the end of years 1 to 3. Find its internal rate of return IRR in percent.
CF0 = −50 000CF1 = 35 500CF2 = 20 000CF3 = 24 000
IRR = %
29.Normal distributionMedium
Drag z so that the shaded area under the standard normal curve, to the right of z, is 0.7967. Find z to two decimals.
A = 0.7967
z =
30.Normal distributionHard
The heights of adult men are normally distributed with mean 178 cm and standard deviation 7 cm. Drag the cut-off so the shaded top 75% is to the right of it. Find the cut-off x.
μ = 178 cmσ = 7 cm75%
x = cm
3Solutions
1.Beam support reactions
Answer: RA = 86 kN
Cantilever equilibrium: a fixed support can push up and also resist rotation, so it gives a vertical reaction RA and a reaction moment MA. ΣFy = 0 gives RA, and moments about the wall give MA = Σ(load × distance from the wall). A distributed load acts as its resultant at the centroid of the load diagram.
Resultant of the distributed load
W = 6·6 = 36 kN, x̄ = 3 m
Vertical equilibrium
RA = P + W = 50 + 36 = 86 kN
Answer
RA = 86 kN
2.Beam support reactions
Answer: RA = 24.38 kN
Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Taking moments about one support removes that support’s reaction from the equation.
Free-body diagram
Replace the supports with reaction forces. A roller gives one vertical reaction; with only vertical loads the pin gives one vertical reaction too.
Equilibrium
Moments about A, counter-clockwise positive. Then vertical force balance.
UDL resultant: W = w·ℓ = 10·3 = 30 kN, acting at x̄ = 5.5 m
ΣMA = 0: RB·8 = 60·6 + 10·3·5.5
RB = 525/8 = 65.63 kN
ΣFy = 0: RA = 90 − 65.63 = 24.38 kN
Answer
RA = 24.38 kN
3.Truss: method of joints
Answer: FBC = −16.97 kN
Method of joints: every pin of a truss is in equilibrium, so ΣFx = 0 and ΣFy = 0 at each joint. Start at a joint with at most two unknown member forces. A negative result means the member is in compression.
Support reactions
Equilibrium of the whole truss. Moments about A, counter-clockwise positive.
ΣMA = 0: Cy·5 = 20·3 → Cy = 12 kN
ΣFy = 0: Ay = 20 − 12 = 8 kN
Joint C
The roller gives only a vertical reaction, so joint C has just two unknown member forces. Assume both in tension.
sin γ = 2/2.828 = 0.7071, cos γ = 2/2.828 = 0.7071
Zero-force members: at a joint, the forces must balance in every direction. If a joint has no load and no support, and two of its three members are in line, then the balance across that line involves only the third member, so its force is zero. If only two members meet at an unloaded joint and they are not in line, both are zero.
Joint C
BC and CD lie on one straight line and the joint carries no load. Balancing forces across that line leaves only CG.
ΣF⊥ = 0 → FCG = 0
Check with the method of joints
Solving all joints gives these member forces (T = tension, C = compression).
Method of sections: cut the beam where you want the internal forces and keep one side. The shear force V balances the vertical forces on that side, and the bending moment M balances their moments about the cut. An applied couple makes the bending moment diagram jump by the size of the couple.
Support reactions
Moments about A, counter-clockwise positive: RB·L − M0 = 0. Vertical balance: RA + RB = 0.
RB = M0/L = 35/6 = 5.833 kN (upward)
RA = −RB = −5.833 kN (downward)
Cut just right of the couple
The left part now contains RA and the couple.
Mx = RA·a + M0 = −5.833·2.5 + 35 = 20.42 kN·m
Answer
Mx = 20.42 kN·m
6.Shear force & bending moment
Answer: F (x = 10 m)
Largest bending moment: M changes slope wherever the shear force changes, so its peaks sit where the shear force crosses zero: under a point load, inside a distributed load, or over a support of an overhang. At a fixed support of a cantilever the moment is largest at the wall. Compare the size of M at those places, sagging or hogging.
Support reactions
Take moments about one support, then use the vertical force balance.
R1 = 5 kN, R2 = 65 kN
Bending moment at every mark
Sum the moments of all forces on one side of the cut. Sagging is positive, hogging negative.
MA = 0, MB = −30, MC = −50, MD = −70, ME = −90, MF = −110 kN·m, MG = 0
Answer
Mark F: MF = −110 kN·m
7.Beam deflection
Answer: δmax = 7.246 mm
Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).
Consistent units
Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.
w = 10 N/mm, L = 4000 mm
EI = 4.6 × 10¹² N·mm²
Deflection
δmax = 5wL⁴/(384EI) = 5·10·4000⁴/(384·4.6 × 10¹²) = 7.246 mm
Answer
δmax = 7.246 mm
8.Beam deflection
Answer: δmax = 11.99 mm
Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).
Consistent units
Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.
P = 7000 N, w = 2 N/mm, L = 2000 mm, EI = 1.32 × 10¹¹ N·mm²
Each load on its own
δP = PL³/(48EI) = 7000·2000³/(48·1.32 × 10¹¹) = 8.838 mm
δw = 5wL⁴/(384EI) = 5·2·2000⁴/(384·1.32 × 10¹¹) = 3.157 mm
Add them
δmax = 8.838 + 3.157 = 11.99 mm
Answer
δmax = 11.99 mm
9.Column buckling
Answer: Pcr = 20.89 kN
Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.
Smallest second moment of area
A rectangle buckles about its weak axis, using the smaller dimension cubed.
Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.
Smallest second moment of area
A round section has the same I about every axis.
I = πd⁴/64 = π·40⁴/64 = 125664 mm⁴
Radius of gyration and slenderness
A = 1257 mm²
r = √(I/A) = √(125664/1257) = 10 mm
KL = 0.7·6000 = 4200 mm
KL/r = 4200/10 = 420
Critical stress
σcr = π²E/(KL/r)² = π²·70000/420² = 3.917 MPa
Answer
σcr = 3.917 MPa
11.Centroid & second moment of area
Answer: Ix = 445.3 × 10⁶ mm⁴
Sections with holes: treat a hole as a negative area. The centroid is ȳ = (A₁y₁ − A₂y₂)/(A₁ − A₂), with A₁, y₁ for the full plate and A₂, y₂ for the hole. For the second moment of area about the centroidal axis, use the parallel-axis theorem for each part and subtract the hole: I = (Ic1 + A₁d₁²) − (Ic2 + A₂d₂²), where d is the distance from each part's own centroid to the axis through ȳ. A rectangle has Ic = bh³/12 and a circle Ic = πd⁴/64.
Centroid
ȳ = (60000·150 − 1257·90)/(60000 − 1257) = 151.3 mm
Full plate about ȳ
200·300³/12 + 60000·−1.284² = 450.1 × 10⁶ mm⁴
Hole about ȳ
π·40⁴/64 + 1257·−61.28² = 4.845 × 10⁶ mm⁴
Subtract
Ix = 445.3 × 10⁶ mm⁴
Answer
Ix = 445.3 × 10⁶ mm⁴
12.Centroid & second moment of area
Answer: Mallow = 4.533 kN·m
Composite areas: split the section into rectangles. The centroid is the area-weighted average ȳ = ΣAᵢyᵢ/ΣAᵢ. The second moment of area about the centroidal axis adds each part’s own bh³/12 and its parallel-axis term A·d², where d is the distance from the part’s centroid to the overall centroid. Bending stress is σ = M·y/I.
Hogging: the top is in tension, the bottom in compression.
top edge: M = 30·4.928 × 10⁶/32.62 = 4.533 kN·m
bottom edge: M = 120·4.928 × 10⁶/112.4 = 5.262 kN·m
Governing value
Mallow = min = 4.533 kN·m (top edge)
Answer
Mallow = 4.533 kN·m
13.Effective stress in soil
Answer: σ = 103 kPa
Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).
Total stress
Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.
Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).
Total stress
Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.
σ = γd·4 + γsat,sand·2 + γsat,clay·3.5
σ = 15·4 + 20·2 + 17.5·3.5 = 161.3 kPa
Pore water pressure
Water pressure grows with depth below the water table.
u = γw·(z − zw) = 9.81·5.5 = 53.96 kPa
Effective stress
σ′ = σ − u = 161.3 − 53.96 = 107.3 kPa
Answer
σ′ = 107.3 kPa
15.Consolidation settlement
Answer: S = 7.019 mm
Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.
Compare with the preconsolidation pressure
σ′f = 105 + 25 = 130 kPa ≤ 215 kPa
Settlement
The clay stays on its recompression line.
S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0) = 0.02·7/(1 + 0.85)·log₁₀(130/105) = 7.019 mm
Answer
S = 7.019 mm
16.Consolidation settlement
Answer: t = 1.603 years
Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.
Drainage path
Hdr = H/2 = 5.5/2 = 2.75 m
Time
t = Tv·Hdr²/cv = 0.848·2.75²/4 = 1.603 years
Answer
t = 1.603 years
17.Hydrostatic force
Answer: F = 98.1 kN
Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.
Centroid depth and area
yc = d + H/2 = 4 + 2/2 = 5 m
A = H·b = 2·1 = 2 m²
Resultant force
F = ρ·g·yc·A = 1000·9.81·5·2 = 98.1 kN
Answer
F = 98.1 kN
18.Hydrostatic force
Answer: ycp = 3.714 m
Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.
Centroid depth and area
yc = d + H/2 = 2 + 3/2 = 3.5 m
A = H·b = 3·3 = 9 m²
Resultant force
F = ρ·g·yc·A = 1000·9.81·3.5·9 = 309 kN
Centre of pressure
Pressure grows with depth, so the resultant acts below the centroid.
Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.
Velocity head
V²/(2g) = 1.3²/(2·9.81) = 0.08614 m
Darcy–Weisbach
hf = f·(L/D)·V²/(2g) = 0.015·(500/0.05)·1.3²/(2·9.81) = 12.92 m
Answer
hf = 12.92 m
20.Pipe friction & head loss
Answer: Q = 17.72 L/s
Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.
Loss coefficients
f·L/D = 0.02·150/0.1 = 30
ΣK = 0.5 + 3·0.3 + 10 + 1.0 = 12.4
Energy equation
Both surfaces are open to the air and practically at rest, so all of Δz is lost in the pipe.
Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.
Geometry
A = b·y = 3.5·1.8 = 6.3 m²
P = b + 2y = 3.5 + 2·1.8 = 7.1 m
R = A/P = 0.8873 m
Velocity
V = (1/0.012)·0.88732/3·0.00081/2 = 2.176 m/s
Flow rate
Q = A·V = 6.3·2.176 = 13.71 m³/s
Answer
Q = 13.71 m³/s
22.Open-channel flow (Manning)
Answer: S = 0.005161 m/m
Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.
Hydraulic radius
R = D/4 = 0.2/4 = 0.05 m
Solve Manning for S
S = (n·V/R2/3)² = (0.013·0.75/0.1357)² = 0.005161
Answer
S = 0.005161
That is a fall of 5.161 m per kilometre.
23.Pumps & pump power
Answer: Pshaft = 3.433 kW
Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.
Hydraulic power
Ph = ρ·g·Q·H = 1000·9.81·0.015·14 = 2.06 kW
Shaft power
Pshaft = Ph/η = 2.06/0.6 = 3.433 kW
Answer
Pshaft = 3.433 kW
24.Pumps & pump power
Answer: H = 68.57 m
Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.
Both surfaces are practically at rest, so there is no velocity head term.
H = Δz + p/(ρ·g) + hL = 18 + 40.77 + 9.793 = 68.57 m
Answer
H = 68.57 m
25.Time value of money
Answer: FV = 1616 €
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Exponent
r·t = 0.03·16 = 0.48
e0.48 = 1.616
Future value
FV = 1 000·1.616 = €1 616.07
Answer
FV = €1 616.07
26.Time value of money
Answer: FV = 18682 €
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
You paid in €14 400 yourself; the rest is interest.
27.NPV & IRR
Answer: NPV = −2461 €
Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.
Present value of each cash flow
CF0 = −75 000
CF1/(1 + 0.06)1 = 32 000/1.06 = 30 188.68
CF2/(1 + 0.06)2 = 24 000/1.124 = 21 359.91
CF3/(1 + 0.06)3 = 25 000/1.191 = 20 990.48
Add them up
NPV = €−2 460.92
Answer
NPV = €−2 460.92
NPV is negative, so the project earns less than the required return.
28.NPV & IRR
Answer: IRR = 30.1 %
Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.
Bracket the IRR
NPV falls as the rate rises, so the IRR lies between a rate with positive NPV and one with negative NPV.
NPV(30%) = 66.00
NPV(35%) = −2 975.16
Narrow down
Linear interpolation gives a first estimate; repeating it (or a calculator's IRR function) gives the exact rate.
IRR ≈ 30 + 5·66.00/(66.00 − (−2 975.16)) = 30.11%
exact: NPV(30.1%) = 0 → IRR = 30.1%
Answer
IRR = 30.1%
29.Normal distribution
Answer: z = −0.83
From an area back to z: Φ(z) is the area to the left of z. For a left-tail area A, find z with Φ(z) = A in the table. A right-tail area A means Φ(z) = 1 − A. A central area A between −z and z leaves (1 − A)/2 in each tail, so Φ(z) = (1 + A)/2. For a value x, use x = μ + zσ.
Area to the left of z
Φ(z) = 1 − 0.7967 = 0.2033
Read the z-table backwards
Find 0.2033 inside the table and read off z.
z = −0.83
Answer
z = −0.83
30.Normal distribution
Answer: x = 173.3 cm
From an area back to z: Φ(z) is the area to the left of z. For a left-tail area A, find z with Φ(z) = A in the table. A right-tail area A means Φ(z) = 1 − A. A central area A between −z and z leaves (1 − A)/2 in each tail, so Φ(z) = (1 + A)/2. For a value x, use x = μ + zσ.