FE Civil exam practice: cram pack

Formula sheets, the key method steps for every topic and 30 practice problems, with full solutions at the back.

New problemsBack to the course

In the print window, choose “Save as PDF” to keep a copy on your device.

1Formulas and methods

Beam support reactions

Equilibrium
ΣFx = 0, ΣFy = 0, ΣM = 0
Uniform load
resultant w·L at the middle of the load
Moment
M = F·d

Method

  1. Draw a free-body diagram and replace each support by its reactions.
  2. Replace every distributed load by a single force at its centroid.
  3. Take moments about one support to find the reaction at the other.
  4. Use ΣFy = 0 to find the remaining reaction, and check with a second moment equation.

Truss: method of joints

Method of joints
ΣFx = 0, ΣFy = 0 at each joint
Method of sections
ΣM = 0 about a cut point
Member force
positive = tension, negative = compression

Method

  1. Find the support reactions for the whole truss.
  2. Method of joints: start at a joint with at most two unknown member forces and use ΣFx = 0 and ΣFy = 0.
  3. Method of sections: cut through the member you need and take moments about a point where the other unknown members meet.
  4. Assume tension; a negative answer means compression.

Shear force & bending moment

Shear and moment
V = ΣF on one side, M = ΣF·d on one side
Bending stress
σ = M·y/I
Rectangle
I = bh³/12
Section modulus
W = I/ymax
Simply supported, uniform load
Mmax = wL²/8

Method

  1. Find the support reactions from equilibrium of the whole beam.
  2. Cut the beam at the section you need and keep one side.
  3. Shear force: sum of the vertical forces on that side. Bending moment: sum of their moments about the cut.
  4. For the maximum moment, find where the shear force is zero.

Beam deflection

Point load at midspan
δ = PL³/(48EI)
Uniform load, simply supported
δ = 5wL⁴/(384EI)
Cantilever, end load
δ = PL³/(3EI)
Cantilever, uniform load
δ = wL⁴/(8EI)
Superposition
δ = δ1 + δ2

Column buckling

Euler load
Pcr = π²EI/(KL)²
Effective length factor
K = 1 pinned–pinned, 0.5 fixed–fixed, 0.7 fixed–pinned, 2 fixed–free
Critical stress
σcr = Pcr/A
Slenderness
λ = KL/r, r = √(I/A)

Centroid & second moment of area

Centroid
ȳ = ΣAiyi/ΣAi
Rectangle
I = bh³/12
Parallel-axis theorem
I = Ic + A·d²
Composite section
I = Σ(Ic,i + Aidi²)

Effective stress in soil

Total stress
σ = Σγi·hi
Pore water pressure
u = γw·(z − zw)
Effective stress
σ′ = σ − u
Water
γw = 9.81 kN/m³

Consolidation settlement

Normally consolidated
S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0)
Final stress
σ′f = σ′0 + Δσ (at mid-depth of the layer)
Overconsolidated, σ′f ≤ σ′p
S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0)
Overconsolidated, σ′f > σ′p
S = H/(1 + e0)·[Cr·log₁₀(σ′p/σ′0) + Cc·log₁₀(σ′f/σ′p)]
Overconsolidation ratio
OCR = σ′p/σ′0
Time for consolidation
t = Tv·Hdr²/cv
Drainage path
Hdr = H/2 (double drainage), H (single drainage)
Time factors
U 50% → 0.197, 60% → 0.287, 70% → 0.403, 80% → 0.567, 90% → 0.848

Hydrostatic force

Pressure at depth
p = ρgh
Force on a vertical wall
F = ρg·hc·A
Centre of pressure
yp = yc + Ic/(ycA)
Rectangle
Ic = bH³/12

Pipe friction & head loss

Reynolds number
Re = V·D/ν = ρ·V·D/μ
Flow regime
laminar below Re ≈ 2000, turbulent above Re ≈ 4000
Mean velocity
V = Q/A, A = π·D²/4
Darcy–Weisbach
hf = f·(L/D)·V²/(2g)
Minor losses
hm = ΣK·V²/(2g)
Typical K values
entrance 0.5, exit 1.0, 90° bend ≈ 0.3
Pressure drop
Δp = ρ·g·hf
Two open reservoirs
Δz = (f·L/D + ΣK)·V²/(2g)
Free outlet
H = (1 + f·L/D + ΣK)·V²/(2g)

Open-channel flow (Manning)

Manning equation
V = (1/n)·R2/3·S1/2
Flow rate
Q = A·V
Hydraulic radius
R = A/P (P = wetted perimeter, free surface excluded)
Rectangle
A = b·y, P = b + 2y
Trapezoid (side slope z:1)
A = (b + z·y)·y, P = b + 2y·√(1 + z²)
Circular pipe, full or half full
R = D/4
Required slope
S = (n·Q/(A·R2/3))²

Pumps & pump power

Hydraulic power
Ph = ρ·g·Q·H = Q·Δp
Shaft power
Pshaft = Ph/ηpump
Electrical power
Pel = Pshaft/ηmotor
Pump head
H = Δz + Δp/(ρ·g) + hL
System losses
hL = (f·L/D + ΣK)·V²/(2g)

Time value of money

Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i

Method

  1. Draw a timeline with every cash flow and its timing.
  2. Match the rate to the period: a monthly rate for monthly payments.
  3. Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
  4. Check the sign and the order of magnitude of the answer.

NPV & IRR

Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)

Method

  1. List all cash flows with their year; the investment at year 0 is negative.
  2. Discount each cash flow: CFt/(1 + r)t.
  3. Add them up to get the NPV. Positive means the project earns more than r.
  4. For the IRR, find the rate that makes NPV zero by trial or interpolation.

Normal distribution

z-score
z = (x − μ)/σ
Below x
P(X < x) = Φ(z)
Above x
P(X > x) = 1 − Φ(z)
Between
Φ(z2) − Φ(z1)
Percentile
x = μ + z·σ

Method

  1. Convert the value to a z-score: z = (x − μ)/σ.
  2. Look up Φ(z), the area to the left of z.
  3. For the area to the right use 1 − Φ(z); for an interval subtract the two left areas.
  4. For a percentile, work backwards: find z for the area, then x = μ + z·σ.

2Practice problems

1.Beam support reactionsMedium
P1​ = 30 kNP2​ = 25 kNABRA​ = ?RB​1 m1 m2 m

The simply supported beam has a pin at A and a roller at B. Find the vertical support reaction RA.

L = 4 mP1 = 30 kN at 1 mP2 = 25 kN at 2 m
RA = kN
2.Beam support reactionsHard
w0​ = 10 kN/mP = 25 kNABMA​ = ?6 m2 m

The cantilever beam is fixed to the wall at A. It carries a linearly varying load that is 10 kN/m at the wall and falls to zero at the free end B, plus a point load P at 6 m from the wall. Find the magnitude of the reaction moment MA at the wall.

L = 8 mw0 = 10 kN/mP = 25 kN at 6 m
MA = kN·m
3.Truss: method of jointsMedium
ABCDEFGH25 kN10 kN10 kN4 × 3 m3 m

Exactly one member of this truss carries no force under these loads. Which is the zero-force member? Click it in the diagram.

C: 25 kN ↓D: 10 kN ↓G: 10 kN ↓
  1. 1member AB
  2. 2member BC
  3. 3member CD
  4. 4member DE
  5. 5member FG
  6. 6member GH
  7. 7member AF
  8. 8member HE
  9. 9member BF
  10. 10member CG
  11. 11member DH
  12. 12member FC
  13. 13member HC
4.Truss: method of jointsHard
ABCDEFGH10 kN15 kN15 kN15 kN4 × 3 m4 m

Exactly one member of this truss carries no force under these loads. Which is the zero-force member? Click it in the diagram.

B: 10 kN ↓F: 15 kN ↓H: 15 kN ↓H: 15 kN ←
  1. 1member AB
  2. 2member BC
  3. 3member CD
  4. 4member DE
  5. 5member FG
  6. 6member GH
  7. 7member AF
  8. 8member HE
  9. 9member BF
  10. 10member CG
  11. 11member DH
  12. 12member BG
  13. 13member DG
5.Shear force & bending momentMedium
w = 6 kN/mP = 60 kNAB5 m

The cantilever is fixed at A. It carries a uniformly distributed load w over its whole length and a point load P at 5 m from A. Find the bending moment MA at the fixed support A. Use sagging moments positive and upward shear on the left face positive.

L = 5 mP = 60 kN at 5 mw = 6 kN/m from 0 to 5 m
MA = kN·m
6.Shear force & bending momentHard
60 kN30 kN35 kNABCDEFG2 m2 m2 m2 m2 m2 m

The marks A to G split the beam into six equal parts. At which mark is the bending moment largest in size, sagging or hogging? Click it in the diagram.

60 kN @ 0 m30 kN @ 12 m35 kN @ 8 m
  1. 1A (x = 0 m)
  2. 2B (x = 2 m)
  3. 3C (x = 4 m)
  4. 4D (x = 6 m)
  5. 5E (x = 8 m)
  6. 6F (x = 10 m)
  7. 7G (x = 12 m)
7.Beam deflectionMedium
P = 2 kNABδ3.5 m1.5 m

A simply supported beam carries a point load P at a = 3.5 m from support A. Find the deflection δP under the load.

P = 2 kNa = 3.5 mL = 5 mE = 11 GPa (timber)I = 120 × 10⁶ mm⁴
δP = mm
8.Beam deflectionHard
w = 3 kN/mABδ4.5 m

A simply supported timber beam of rectangular section, 75 mm wide, carries a uniformly distributed load w over its whole span. Its midspan deflection may not exceed span/360. Find the smallest depth hreq of the section.

w = 3 kN/mL = 4.5 mE = 11 GPa (timber)b = 75 mm
hreq = mm
9.Column bucklingMedium
PL = 3 m25 × 50 mmcross-section

A column of length L made of aluminium is pinned at both ends. Using Euler’s formula, find its critical buckling load Pcr.

L = 3 mE = 70 GPa (aluminium)b × h = 25 × 50 mm
Pcr = kN
10.Column bucklingHard
PL = 2 md = 25 mmcross-section

A column of length L made of aluminium is pinned at both ends. Find its slenderness and the critical buckling stress σcr from Euler’s formula.

L = 2 mE = 70 GPa (aluminium)d = 25 mm
σcr = MPa
11.Centroid & second moment of areaMedium
200 mm200 mm140 mmØ30xIx​ = ?

A 200 mm × 200 mm plate has a circular hole of diameter 30 mm on its vertical centre line, with its centre 140 mm above the bottom. Find the second moment of area Ix about the horizontal axis through the centroid.

b = 200 mmh = 200 mmd = 30 mmhole centre: y = 140 mm
Ix = × 10⁶ mm⁴
12.Centroid & second moment of areaHard
150 mm150 mm90 mm80 × 50xIx​ = ?

A 150 mm × 150 mm plate has a rectangular cut-out 80 mm wide and 50 mm high, centred on the vertical centre line with its centre 90 mm above the bottom. Find the second moment of area Ix about the horizontal axis through the centroid.

b = 150 mmh = 150 mmcut-out: 80 × 50 mmhole centre: y = 90 mm
Ix = × 10⁶ mm⁴
13.Effective stress in soilMedium
sandγd​ = 15 kN/m³γsat​ = 20 kN/m³7 mwater tableXz = 7 m

For the soil profile shown, find the vertical effective stress σ′ at point X.

z = 7 mzw = 2 mγw = 9.81 kN/m³sand: γd = 15 kN/m³sand: γsat = 20 kN/m³
σ′ = kPa
14.Effective stress in soilHard
sandγd​ = 15 kN/m³γsat​ = 18.5 kN/m³4 mclayγsat​ = 17.5 kN/m³6 mwater tableXz = 7 m

For the soil profile shown, find the total vertical stress σ at point X.

z = 7 mzw = 3 mγw = 9.81 kN/m³sand: γd = 15 kN/m³sand: γsat = 18.5 kN/m³clay: γsat = 17.5 kN/m³
σ = kPa
15.Consolidation settlementMedium
Δσ = 25 kPasandclayCc​ = 0.4, Cr​ = 0.04e0​ = 0.7σ′0​ = 50 kPaσ′p​ = 120 kPa4 mwater table

A 4 m thick overconsolidated clay layer has Cc = 0.4, Cr = 0.04 and e₀ = 0.7. At its mid-depth the effective vertical stress is 50 kPa and the preconsolidation pressure is 120 kPa. A new building adds 25 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.

H = 4 mCc = 0.4Cr = 0.04e0 = 0.7σ′0 = 50 kPaσ′p = 120 kPaΔσ = 25 kPa
S = mm
16.Consolidation settlementHard
sandclayH = 4.5 mcv​ = 4 m²/year4.5 msandwater table

A clay layer 4.5 m thick has a coefficient of consolidation cv = 4 m²/year. It lies between two sand layers, so water drains out at the top and the bottom. For 90% average consolidation the time factor is Tv = 0.848. How many years t does the layer take to reach 90% consolidation?

H = 4.5 mcv = 4 m²/yearU = 90%Tv = 0.848double drainage
t = years
17.Hydrostatic forceMedium
gated = 3 mH = 2.5 m

A vertical rectangular gate 2 m wide sits in the wall of a tank of water, with its top edge 3 m below the surface. Find the resultant hydrostatic force F on the gate.

d = 3 mH = 2.5 mb = 2 mρ = 1000 kg/m³g = 9.81 m/s²
F = kN
18.Hydrostatic forceHard
gated = 1 mH = 1.5 m

A vertical rectangular gate 1.5 m wide sits in the wall of a tank of glycerin, with its top edge 1 m below the surface. Find the resultant hydrostatic force F on the gate.

d = 1 mH = 1.5 mb = 1.5 mρ = 1260 kg/m³g = 9.81 m/s²
F = kN
19.Pipe friction & head lossMedium
V = 1.1 m/sD = 300 mmL = 100 mf = 0.022

Water flows at a mean velocity of 1.1 m/s through a pipe 100 m long with an inside diameter of 300 mm. Use the Darcy friction factor f = 0.022 and g = 9.81 m/s². Find the friction head loss hf.

V = 1.1 m/sL = 100 mD = 300 mmf = 0.022g = 9.81 m/s²
hf = m
20.Pipe friction & head lossHard
K = 2free outletH = ?L = 200 m, D = 150 mm, f = 0.0183× bend (K = 0.3)

A pipe 200 m long with an inside diameter of 150 mm (Darcy friction factor f = 0.018) runs from an open reservoir and discharges as a free jet into the air. The minor losses are a square-edged entrance (K = 0.5), 3 bends (K = 0.3 each) and a valve (K = 2). Use g = 9.81 m/s². How far H must the reservoir surface be above the pipe outlet for a flow rate of 25 L/s?

Q = 25 L/sL = 200 mD = 150 mmf = 0.018Kentrance = 0.5Kbend = 0.3 (×3)Kvalve = 2
H = m
21.Open-channel flow (Manning)Medium
b = 4 my = 0.9 m1.5 : 1n = 0.022, S = 0.002

A trapezoidal clean earth channel has a bottom width of 4 m and side slopes of 1.5:1 (horizontal:vertical). Water flows uniformly 0.9 m deep. Manning n = 0.022 and the bed slope is S = 0.002. Find the flow rate Q in m³/s.

b = 4 my = 0.9 mz = 1.5n = 0.022S = 0.002
Q = m³/s
22.Open-channel flow (Manning)Hard
b = 5 my = 0.8 m1 : 1n = 0.03, Q = 2.6 m³/s

A trapezoidal grass-lined earth channel with a bottom width of 5 m and side slopes of 1:1 (horizontal:vertical) must carry 2.6 m³/s in uniform flow at a depth of 0.8 m. Manning n = 0.03. Find the required bed slope S (in m/m).

Q = 2.6 m³/sb = 5 my = 0.8 mz = 1n = 0.03
S = m/m
23.Pumps & pump powerMedium
PQ = 15 L/sH = 66 m

A pump with an efficiency of 70% delivers 15 L/s of water (ρ = 1000 kg/m³) against a head of 66 m. Use g = 9.81 m/s². Find the shaft power Pshaft needed, in kW.

Q = 15 L/sH = 66 mη = 70%g = 9.81 m/s²
Pshaft = kW
24.Pumps & pump powerHard
PQ = 75 L/sΔz = 19 mL = 100 m, D = 200 mm, f = 0.02, ΣK = 6

A pump moves 75 L/s of water (ρ = 1000 kg/m³) from an open lower reservoir to an upper tank whose water surface is 19 m higher. The pipe is 100 m long with an inside diameter of 200 mm and a Darcy friction factor f = 0.02; the minor-loss coefficients add up to ΣK = 6 (entrance and exit included). Use g = 9.81 m/s². Find the head H the pump must add.

Q = 75 L/sΔz = 19 mL = 100 mD = 200 mmf = 0.02ΣK = 6
H = m
25.Time value of moneyMedium
years0123PV = ?€20 000

You need €20 000 in 3 years. An account pays 4% per year, compounded quarterly. How much must you deposit today? Find the present value PV.

FV = €20 0004% / 4n = 3
PV = €
26.Time value of moneyHard
months01…72…240€200 000AB = ?A5.4% / 12

A mortgage of €200 000 is repaid with equal monthly payments over 20 years at 5.4% per year, compounded monthly. How much is still owed just after the payment at the end of year 6? Find the outstanding balance B.

P = €200 0005.4% / 12N = 240k = 72
B = €
27.NPV & IRRMedium
years0123−20 0005 0007 0005 000

An investment of €20 000 gives these cash flows at the end of years 1 to 3: €5 000, €7 000, €5 000. The cost of capital is 12%. Find the net present value NPV.

r = 12%CF0 = −20 000CF1 = 5 000CF2 = 7 000CF3 = 5 000
NPV = €
28.NPV & IRRHard
years0123−10 0003 0006 0005 000

A project costs €10 000 and returns €3 000, €6 000, €5 000 at the end of years 1 to 3. Cash flows can be reinvested at the cost of capital of 12%. Find the modified internal rate of return MIRR in percent.

r = 12%CF0 = −10 000CF1 = 3 000CF2 = 6 000CF3 = 5 000
MIRR = %
29.Normal distributionMedium
−3−2−10123zshaded area to the right of z = 0.9484

Drag z so that the shaded area under the standard normal curve, to the right of z, is 0.9484. Find z to two decimals.

A = 0.9484
z =
30.Normal distributionHard
10 g0X − Y?

The mass X of a product from line 1 and Y from line 2 are independent and normal: X has mean 500 g and standard deviation 8 g, Y has mean 490 g and standard deviation 6 g. Find the probability P that X is greater than Y. Round z to two decimals.

μX = 500 g, σX = 8 gμY = 490 g, σY = 6 g
P =

3Solutions

1.Beam support reactions

Answer: RA = 35 kN

Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Taking moments about one support removes that support’s reaction from the equation.

P1​ = 30 kNP2​ = 25 kNABRA​RB​1 m1 m2 m

Free-body diagram

Replace the supports with reaction forces. A roller gives one vertical reaction; with only vertical loads the pin gives one vertical reaction too.

Equilibrium

Moments about A, counter-clockwise positive. Then vertical force balance.

ΣMA = 0: RB·4 = 30·1 + 25·2
RB = 80/4 = 20 kN
ΣFy = 0: RA = 55 − 20 = 35 kN

Answer

RA = 35 kN
2.Beam support reactions

Answer: MA = 256.7 kN·m

Cantilever equilibrium: a fixed support can push up and also resist rotation, so it gives a vertical reaction RA and a reaction moment MA. ΣFy = 0 gives RA, and moments about the wall give MA = Σ(load × distance from the wall). A distributed load acts as its resultant at the centroid of the load diagram.

Resultant of the triangular load

W = ½·10·8 = 40 kN
x̄ = L/3 = 2.667 m

Moment about the wall

MA = W·x̄ + P·a = 40·2.667 + 25·6 = 256.7 kN·m

Answer

MA = 256.7 kN·m
3.Truss: method of joints

Answer: member BF

Zero-force members: at a joint, the forces must balance in every direction. If a joint has no load and no support, and two of its three members are in line, then the balance across that line involves only the third member, so its force is zero. If only two members meet at an unloaded joint and they are not in line, both are zero.

Joint B

AB and BC lie on one straight line and the joint carries no load. Balancing forces across that line leaves only BF.

ΣF⊥ = 0 → FBF = 0

Check with the method of joints

Solving all joints gives these member forces (T = tension, C = compression).

AB: 20 kN (T), BC: 20 kN (T), CD: 25 kN (T), DE: 25 kN (T), FG: 40 kN (C), GH: 40 kN (C), AF: 28.28 kN (C), HE: 35.36 kN (C), BF: 0, CG: 10 kN (C), DH: 10 kN (T), FC: 28.28 kN (T), HC: 21.21 kN (T)

Answer

Zero-force member: BF
4.Truss: method of joints

Answer: member CG

Zero-force members: at a joint, the forces must balance in every direction. If a joint has no load and no support, and two of its three members are in line, then the balance across that line involves only the third member, so its force is zero. If only two members meet at an unloaded joint and they are not in line, both are zero.

Joint C

BC and CD lie on one straight line and the joint carries no load. Balancing forces across that line leaves only CG.

ΣF⊥ = 0 → FCG = 0

Check with the method of joints

Solving all joints gives these member forces (T = tension, C = compression).

AB: 5.625 kN (T), BC: 7.5 kN (T), CD: 7.5 kN (T), DE: 9.375 kN (T), FG: 20.63 kN (C), GH: 24.38 kN (C), AF: 34.38 kN (C), HE: 15.62 kN (C), BF: 12.5 kN (T), CG: 0, DH: 2.5 kN (C), BG: 3.125 kN (C), DG: 3.125 kN (T)

Answer

Zero-force member: CG
5.Shear force & bending moment

Answer: MA = −375 kN·m

Method of sections: cut the beam where you want the internal forces and keep one side. The shear force V balances the vertical forces on that side, and the bending moment M balances their moments about the cut.

Keep the free-end part

P: −60·5 = −300 kN·m
w: −6·5²/2 = −75 kN·m
MA = −300 − 75 = −375 kN·m

Answer

MA = −375 kN·m

Negative means hogging: tension on the top face.

6.Shear force & bending moment

Answer: B (x = 2 m)

Largest bending moment: M changes slope wherever the shear force changes, so its peaks sit where the shear force crosses zero: under a point load, inside a distributed load, or over a support of an overhang. At a fixed support of a cantilever the moment is largest at the wall. Compare the size of M at those places, sagging or hogging.

Support reactions

Take moments about one support, then use the vertical force balance.

R1 = 76.25 kN, R2 = 48.75 kN

Bending moment at every mark

Sum the moments of all forces on one side of the cut. Sagging is positive, hogging negative.

MA = 0, MB = −120 kN·m, MC = −87.5, MD = −55, ME = −22.5, MF = −60, MG = 0

Answer

Mark B: MB = −120 kN·m
7.Beam deflection

Answer: δP = 2.784 mm

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).

Consistent units

Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.

P = 2000 N, a = 3500 mm, b = 1500 mm, L = 5000 mm
EI = 1.32 × 10¹² N·mm²

Deflection under the load

δP = Pa²b²/(3EIL) = 2000·3500²·1500²/(3·1.32 × 10¹²·5000) = 2.784 mm

Answer

δP = 2.784 mm
8.Beam deflection

Answer: hreq = 265.1 mm

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).

Consistent units

Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.

w = 3 N/mm, L = 4500 mm, E = 11000 N/mm²

Deflection limit

δallow = L/360 = 4500/360 = 12.5 mm

Required second moment of area

Ireq = 5wL⁴/(384·E·δallow) = 5·3·4500⁴/(384·11000·12.5) = 1.165 × 10⁸ mm⁴

Required depth

bh³/12 = Ireq → h = (12·1.165 × 10⁸/75)1/3 = 265.1 mm

Answer

hreq = 265.1 mm

In practice, choose the next standard depth above this value.

9.Column buckling

Answer: Pcr = 4.998 kN

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Smallest second moment of area

A rectangle buckles about its weak axis, using the smaller dimension cubed.

Imin = h·b³/12 = 50·25³/12 = 65104 mm⁴

Effective length

KL = 1·3000 = 3000 mm

Critical load

Pcr = π²EI/(KL)² = π²·70000·65104/3000² = 4998 N = 4.998 kN

Answer

Pcr = 4.998 kN
10.Column buckling

Answer: σcr = 6.747 MPa

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Smallest second moment of area

A round section has the same I about every axis.

I = πd⁴/64 = π·25⁴/64 = 19175 mm⁴

Radius of gyration and slenderness

A = 490.9 mm²
r = √(I/A) = √(19175/490.9) = 6.25 mm
KL = 1·2000 = 2000 mm
KL/r = 2000/6.25 = 320

Critical stress

σcr = π²E/(KL/r)² = π²·70000/320² = 6.747 MPa

Answer

σcr = 6.747 MPa
11.Centroid & second moment of area

Answer: Ix = 132.1 × 10⁶ mm⁴

Sections with holes: treat a hole as a negative area. The centroid is ȳ = (A₁y₁ − A₂y₂)/(A₁ − A₂), with A₁, y₁ for the full plate and A₂, y₂ for the hole. For the second moment of area about the centroidal axis, use the parallel-axis theorem for each part and subtract the hole: I = (Ic1 + A₁d₁²) − (Ic2 + A₂d₂²), where d is the distance from each part's own centroid to the axis through ȳ. A rectangle has Ic = bh³/12 and a circle Ic = πd⁴/64.

Centroid

ȳ = (40000·100 − 706.9·140)/(40000 − 706.9) = 99.28 mm

Full plate about ȳ

200·200³/12 + 40000·0.7196² = 133.4 × 10⁶ mm⁴

Hole about ȳ

π·30⁴/64 + 706.9·40.72² = 1.212 × 10⁶ mm⁴

Subtract

Ix = 132.1 × 10⁶ mm⁴

Answer

Ix = 132.1 × 10⁶ mm⁴
12.Centroid & second moment of area

Answer: Ix = 40.26 × 10⁶ mm⁴

Sections with holes: treat a hole as a negative area. The centroid is ȳ = (A₁y₁ − A₂y₂)/(A₁ − A₂), with A₁, y₁ for the full plate and A₂, y₂ for the hole. For the second moment of area about the centroidal axis, use the parallel-axis theorem for each part and subtract the hole: I = (Ic1 + A₁d₁²) − (Ic2 + A₂d₂²), where d is the distance from each part's own centroid to the axis through ȳ. A rectangle has Ic = bh³/12 and a circle Ic = πd⁴/64.

Centroid

ȳ = (22500·75 − 4000·90)/(22500 − 4000) = 71.76 mm

Full plate about ȳ

150·150³/12 + 22500·3.243² = 42.42 × 10⁶ mm⁴

Hole about ȳ

80·50³/12 + 4000·18.24² = 2.165 × 10⁶ mm⁴

Subtract

Ix = 40.26 × 10⁶ mm⁴

Answer

Ix = 40.26 × 10⁶ mm⁴
13.Effective stress in soil

Answer: σ′ = 80.95 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Total stress

Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.

σ = γd·zw + γsat·(z − zw) = 15·2 + 20·5 = 130 kPa

Pore water pressure

Water pressure grows with depth below the water table.

u = γw·(z − zw) = 9.81·5 = 49.05 kPa

Effective stress

σ′ = σ − u = 130 − 49.05 = 80.95 kPa

Answer

σ′ = 80.95 kPa
14.Effective stress in soil

Answer: σ = 116 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Total stress

Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.

σ = γd·3 + γsat,sand·1 + γsat,clay·3
σ = 15·3 + 18.5·1 + 17.5·3 = 116 kPa

Answer

σ = 116 kPa
15.Consolidation settlement

Answer: S = 16.57 mm

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Compare with the preconsolidation pressure

σ′f = 50 + 25 = 75 kPa ≤ 120 kPa

Settlement

The clay stays on its recompression line.

S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0) = 0.04·4/(1 + 0.7)·log₁₀(75/50) = 16.57 mm

Answer

S = 16.57 mm
16.Consolidation settlement

Answer: t = 1.073 years

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Drainage path

Hdr = H/2 = 4.5/2 = 2.25 m

Time

t = Tv·Hdr²/cv = 0.848·2.25²/4 = 1.073 years

Answer

t = 1.073 years
17.Hydrostatic force

Answer: F = 208.5 kN

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 3 + 2.5/2 = 4.25 m
A = H·b = 2.5·2 = 5 m²
gated = 3 mH = 2.5 mF

Resultant force

F = ρ·g·yc·A = 1000·9.81·4.25·5 = 208.5 kN

Answer

F = 208.5 kN
18.Hydrostatic force

Answer: F = 48.67 kN

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 1 + 1.5/2 = 1.75 m
A = H·b = 1.5·1.5 = 2.25 m²
gated = 1 mH = 1.5 mF

Resultant force

F = ρ·g·yc·A = 1260·9.81·1.75·2.25 = 48.67 kN

Answer

F = 48.67 kN
19.Pipe friction & head loss

Answer: hf = 0.4523 m

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Velocity head

V²/(2g) = 1.1²/(2·9.81) = 0.06167 m

Darcy–Weisbach

hf = f·(L/D)·V²/(2g) = 0.022·(100/0.3)·1.1²/(2·9.81) = 0.4523 m

Answer

hf = 0.4523 m
20.Pipe friction & head loss

Answer: H = 2.897 m

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Velocity

V = Q/A = 0.025/0.01767 = 1.415 m/s
V²/(2g) = 0.102 m

Loss coefficients

f·L/D = 0.018·200/0.15 = 24
ΣK = 0.5 + 3·0.3 + 2 = 3.4

Energy equation

The outlet jet still carries its velocity head; it is not a loss but it has to be supplied.

H = (1 + 24 + 3.4)·0.102 = 2.897 m

Answer

H = 2.897 m
21.Open-channel flow (Manning)

Answer: Q = 7.454 m³/s

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Geometry

A = (b + z·y)·y = (4 + 1.5·0.9)·0.9 = 4.815 m²
P = b + 2y·√(1 + z²) = 4 + 2·0.9·√(1 + 1.5²) = 7.245 m
R = A/P = 0.6646 m

Velocity

V = (1/0.022)·0.66462/3·0.0021/2 = 1.548 m/s

Flow rate

Q = A·V = 4.815·1.548 = 7.454 m³/s

Answer

Q = 7.454 m³/s
22.Open-channel flow (Manning)

Answer: S = 0.0005136 m/m

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Geometry

A = (b + z·y)·y = (5 + 1·0.8)·0.8 = 4.64 m²
P = b + 2y·√(1 + z²) = 5 + 2·0.8·√(1 + 1²) = 7.263 m
R = A/P = 0.6389 m

Solve Manning for S

S1/2 = n·Q/(A·R2/3) = 0.03·2.6/(4.64·0.7418) = 0.02266
S = 0.02266² = 0.0005136

Answer

S = 0.0005136

That is a fall of 0.5136 m per kilometre.

23.Pumps & pump power

Answer: Pshaft = 13.87 kW

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Hydraulic power

Ph = ρ·g·Q·H = 1000·9.81·0.015·66 = 9.712 kW

Shaft power

Pshaft = Ph/η = 9.712/0.7 = 13.87 kW

Answer

Pshaft = 13.87 kW
24.Pumps & pump power

Answer: H = 23.65 m

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Velocity

V = Q/A = 0.075/0.03142 = 2.387 m/s
V²/(2g) = 0.2905 m

Head losses

hL = (f·L/D + ΣK)·V²/(2g) = (10 + 6)·0.2905 = 4.648 m

Pump head

Both surfaces are open and practically at rest, so pressure and velocity terms drop out.

H = Δz + hL = 19 + 4.648 = 23.65 m

Answer

H = 23.65 m
25.Time value of money

Answer: PV = 17749 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Rate and number of periods

i = 0.04/4 = 0.01
N = 4·3 = 12

Present value

PV = FV/(1 + i)N = 20 000/1.127 = €17 748.98

Answer

PV = €17 748.98
26.Time value of money

Answer: B = 160606 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Monthly payment

i = 0.0045, N = 240
A = 200 000·0.0045/(1 − (1 + 0.0045)−240) = €1 364.50

Present value of the remaining payments

Whatever is still owed must be exactly paid off by the remaining payments.

N − k = 240 − 72 = 168
B = 1365·(1 − (1 + 0.0045)−168)/0.0045 = €160 605.72

Answer

B = €160 605.72
27.NPV & IRR

Answer: NPV = −6396 €

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Present value of each cash flow

CF0 = −20 000
CF1/(1 + 0.12)1 = 5 000/1.12 = 4 464.29
CF2/(1 + 0.12)2 = 7 000/1.254 = 5 580.36
CF3/(1 + 0.12)3 = 5 000/1.405 = 3 558.90

Add them up

NPV = €−6 396.46

Answer

NPV = €−6 396.46

NPV is negative, so the project earns less than the required return.

28.NPV & IRR

Answer: MIRR = 15.69 %

Modified IRR: compound every inflow forward to the end of the project at the reinvestment rate (usually the cost of capital) to get the terminal value TV. MIRR is the rate that turns the initial investment into TV: MIRR = (TV/C₀)^(1/n) − 1.

Terminal value of the inflows

3 000·1.122 = 3 763.20
6 000·1.121 = 6 720.00
5 000·1.120 = 5 000.00
TV = 15 483.20

MIRR

MIRR = (15 483.20/10 000)1/3 − 1 = 15.69%

Answer

MIRR = 15.69%
29.Normal distribution

Answer: z = −1.63

From an area back to z: Φ(z) is the area to the left of z. For a left-tail area A, find z with Φ(z) = A in the table. A right-tail area A means Φ(z) = 1 − A. A central area A between −z and z leaves (1 − A)/2 in each tail, so Φ(z) = (1 + A)/2. For a value x, use x = μ + zσ.

Area to the left of z

Φ(z) = 1 − 0.9484 = 0.0516

Read the z-table backwards

Find 0.0516 inside the table and read off z.

z = −1.63

Answer

z = −1.63
30.Normal distribution

Answer: P = 0.8413

Sums and differences of normal variables: if X and Y are independent and normal, X + Y and X − Y are normal too. Means add or subtract: E(X ± Y) = μX ± μY. Variances always add, also for a difference: Var(X ± Y) = σX² + σY², so σ = √(σX² + σY²). Standard deviations never add directly. The total of n independent items with the same distribution has mean n·μ and standard deviation σ·√n. Then standardise as usual: z = (x − mean)/σ and read Φ(z).

Distribution of the difference

μ = 500 − 490 = 10 g, σ = 10 g

Standardise

z = (0 − 10)/10 = −1

Probability

P = 1 − Φ(−1) = 0.8413

Answer

P = 0.8413

This is independent practice material. ExamProblems is not affiliated with or endorsed by the organisation that runs this exam, and the exam name is used only to describe the content. The FE exam is run by NCEES, which is not affiliated with ExamProblems and does not endorse it.