laminar below Re ≈ 2000, turbulent above Re ≈ 4000
Mean velocity
V = Q/A, A = π·D²/4
Darcy–Weisbach
hf = f·(L/D)·V²/(2g)
Minor losses
hm = ΣK·V²/(2g)
Typical K values
entrance 0.5, exit 1.0, 90° bend ≈ 0.3
Pressure drop
Δp = ρ·g·hf
Two open reservoirs
Δz = (f·L/D + ΣK)·V²/(2g)
Free outlet
H = (1 + f·L/D + ΣK)·V²/(2g)
Open-channel flow (Manning)
Manning equation
V = (1/n)·R2/3·S1/2
Flow rate
Q = A·V
Hydraulic radius
R = A/P (P = wetted perimeter, free surface excluded)
Rectangle
A = b·y, P = b + 2y
Trapezoid (side slope z:1)
A = (b + z·y)·y, P = b + 2y·√(1 + z²)
Circular pipe, full or half full
R = D/4
Required slope
S = (n·Q/(A·R2/3))²
Pumps & pump power
Hydraulic power
Ph = ρ·g·Q·H = Q·Δp
Shaft power
Pshaft = Ph/ηpump
Electrical power
Pel = Pshaft/ηmotor
Pump head
H = Δz + Δp/(ρ·g) + hL
System losses
hL = (f·L/D + ΣK)·V²/(2g)
Time value of money
Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i
Method
Draw a timeline with every cash flow and its timing.
Match the rate to the period: a monthly rate for monthly payments.
Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
Check the sign and the order of magnitude of the answer.
NPV & IRR
Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)
Method
List all cash flows with their year; the investment at year 0 is negative.
Discount each cash flow: CFt/(1 + r)t.
Add them up to get the NPV. Positive means the project earns more than r.
For the IRR, find the rate that makes NPV zero by trial or interpolation.
Normal distribution
z-score
z = (x − μ)/σ
Below x
P(X < x) = Φ(z)
Above x
P(X > x) = 1 − Φ(z)
Between
Φ(z2) − Φ(z1)
Percentile
x = μ + z·σ
Method
Convert the value to a z-score: z = (x − μ)/σ.
Look up Φ(z), the area to the left of z.
For the area to the right use 1 − Φ(z); for an interval subtract the two left areas.
For a percentile, work backwards: find z for the area, then x = μ + z·σ.
2Practice problems
1.Beam support reactionsMedium
The beam has a pin at A and a roller at B, 4 m from A, and overhangs B to the free end C. Find the vertical reaction RA, taking upward as positive.
AB = 4 mAC = 5 mP1 = 45 kN at 1.5 mP2 = 60 kN at 5 m
RA = kN
2.Beam support reactionsHard
The simply supported beam has a pin at A and a roller at B. Find the vertical support reaction RB.
L = 6 mP = 15 kN at 5 mw = 8 kN/m from 3 to 4 m
RB = kN
3.Truss: method of jointsMedium
Use the method of joints to find the force FBC in member BC. Give tension as positive and compression as negative.
span = 8 mheight = 3 mB is 6 m from Avertical load = 45 kN
FBC = kN
4.Truss: method of jointsHard
Use the method of joints to find the force FBC in member BC. Give tension as positive and compression as negative.
span = 5 mheight = 4 mB is 3 m from Avertical load = 15 kNhorizontal load = 15 kN →
FBC = kN
5.Shear force & bending momentMedium
The marks A to G split the beam into six equal parts. At which mark is the bending moment largest in size, sagging or hogging? Click it in the diagram.
15 kN @ 6 m6 kN/m, 0–12 m
1A (x = 0 m)
2B (x = 2 m)
3C (x = 4 m)
4D (x = 6 m)
5E (x = 8 m)
6F (x = 10 m)
7G (x = 12 m)
6.Shear force & bending momentHard
The marks A to G split the beam into six equal parts. At which mark is the bending moment largest in size, sagging or hogging? Click it in the diagram.
50 kN @ 0 m60 kN @ 12 m45 kN @ 6 m12 kN/m, 2–8 m
1A (x = 0 m)
2B (x = 2 m)
3C (x = 4 m)
4D (x = 6 m)
5E (x = 8 m)
6F (x = 10 m)
7G (x = 12 m)
7.Beam deflectionMedium
A simply supported beam carries a uniformly distributed load w over its whole span. Find the maximum deflection δmax, at midspan.
w = 6 kN/mL = 4 mE = 200 GPa (steel)I = 12 × 10⁶ mm⁴
δmax = mm
8.Beam deflectionHard
A simply supported beam carries a uniformly distributed load w and a point load P at midspan. Using superposition, find the midspan deflection δmax.
P = 16 kNw = 12 kN/mL = 3 mE = 200 GPa (steel)I = 57 × 10⁶ mm⁴
δmax = mm
9.Column bucklingMedium
A column of length L made of steel is fixed at both ends. Using Euler’s formula, find its critical buckling load Pcr.
L = 6 mE = 200 GPa (steel)d = 80 mm
Pcr = kN
10.Column bucklingHard
A column of length L made of steel is pinned at both ends. Find its slenderness and the critical buckling stress σcr from Euler’s formula.
L = 2 mE = 200 GPa (steel)d = 50 mm
σcr = MPa
11.Centroid & second moment of areaMedium
A symmetric I-section has flanges 210 mm wide and 24 mm thick, an overall depth of 500 mm and a web 12 mm thick. Find its elastic section modulus Sx for bending about the horizontal centroidal axis x.
B = 210 mmH = 500 mmtf = 24 mmtw = 12 mm
Sx = × 10³ mm³
12.Centroid & second moment of areaHard
The T-section is used as a beam with the flange on top and carries a sagging bending moment of 30 kN·m. Find the bending stress σbottom at the bottom edge.
A 5 m thick overconsolidated clay layer has Cc = 0.5, Cr = 0.02 and e₀ = 1.05. At its mid-depth the effective vertical stress is 90 kPa and the preconsolidation pressure is 210 kPa. A new building adds 85 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.
In a laboratory oedometer test, a clay specimen 25 mm thick, drained at the top and bottom, reaches 50% consolidation in 15 min. In the field the same clay forms a layer 4.5 m thick. It lies on impervious rock, with sand above it, so water drains out only at the top. How many days t does the field layer take to reach 50% consolidation?
A vertical rectangular gate 3 m wide sits in the wall of a tank of water, with its top edge 0.5 m below the surface. Find the resultant hydrostatic force F on the gate.
A vertical rectangular gate 1.5 m wide sits in the wall of a tank of seawater, with its top edge 0.5 m below the surface. Find the resultant hydrostatic force F on the gate.
Water (ρ = 1000 kg/m³) flows at 2.4 m/s through a horizontal pipe, 200 m long, with an inside diameter of 100 mm. Use the Darcy friction factor f = 0.028 and g = 9.81 m/s². Find the pressure drop Δp over the pipe in kPa.
Two open reservoirs are joined by a pipe 200 m long with an inside diameter of 300 mm and a Darcy friction factor f = 0.025. The minor losses are a square-edged entrance (K = 0.5), 3 bends (K = 0.3 each), a valve (K = 2) and the exit into the lower reservoir (K = 1.0). Use g = 9.81 m/s². What difference in water level Δz between the reservoirs gives a flow rate of 200 L/s?
A rectangular grass-lined earth channel is 5.5 m wide. Water flows uniformly 2.3 m deep. Manning n = 0.03 and the bed slope is S = 0.0015. Find the flow rate Q in m³/s.
b = 5.5 my = 2.3 mn = 0.03S = 0.0015
Q = m³/s
22.Open-channel flow (Manning)Hard
A trapezoidal unfinished concrete channel with a bottom width of 2 m and side slopes of 3:1 (horizontal:vertical) must carry 8.5 m³/s in uniform flow at a depth of 1.2 m. Manning n = 0.014. Find the required bed slope S (in m/m).
Q = 8.5 m³/sb = 2 my = 1.2 mz = 3n = 0.014
S = m/m
23.Pumps & pump powerMedium
In a test, a pump delivers 40 L/s of water (ρ = 1000 kg/m³) against a head of 12 m while its shaft takes 7.8 kW. Use g = 9.81 m/s². Find the pump efficiency η in percent.
Q = 40 L/sH = 12 mPshaft = 7.8 kWg = 9.81 m/s²
η = %
24.Pumps & pump powerHard
A pump moves 40 L/s of water (ρ = 1000 kg/m³) from an open lower reservoir to an upper tank whose water surface is 12 m higher. The pipe is 400 m long with an inside diameter of 150 mm and a Darcy friction factor f = 0.015; the minor-loss coefficients add up to ΣK = 5 (entrance and exit included). Use g = 9.81 m/s². The pump efficiency is 82%. Find the shaft power Pshaft in kW.
You invest €1 000 at 7% per year with continuous compounding. Find the value FV after 2 years.
PV = €1 000r = 7%t = 2
FV = €
26.Time value of moneyHard
A loan of €20 000 is repaid with equal monthly payments over 3 years. The interest rate is 4.8% per year, compounded monthly. Find the monthly payment A.
P = €20 0004.8% / 12N = 36
A = €
27.NPV & IRRMedium
An investment of €45 000 gives these cash flows at the end of years 1 to 3: €15 000, €10 000, €18 000. The cost of capital is 10%. Find the net present value NPV.
A project costs €50 000 and returns €21 500, €37 000 at the end of years 1 to 2. Find its internal rate of return IRR in percent.
CF0 = −50 000CF1 = 21 500CF2 = 37 000
IRR = %
29.Normal distributionMedium
Drag z so that the shaded area between −z and z under the standard normal curve is 0.6265. Find z to two decimals.
A = 0.6265
z =
30.Normal distributionHard
The IQ scores are normally distributed with mean 100 points and standard deviation 15 points. Drag the cut-off so the shaded bottom 40% is to the left of it. Find the cut-off x.
μ = 100 pointsσ = 15 points40%
x = points
3Solutions
1.Beam support reactions
Answer: RA = 13.13 kN
Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Replace each distributed load by its resultant (its area) acting at the centroid of the load diagram, and take moments about a support to remove that support’s reaction from the equation.
Moments about A
Counter-clockwise positive.
ΣMA = 0: RB·4 = 45·1.5 + 60·5
RB = 367.5/4 = 91.88 kN
Vertical equilibrium
RA = 45 + 60 − 91.88 = 13.13 kN
Answer
RA = 13.13 kN
2.Beam support reactions
Answer: RB = 17.17 kN
Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Taking moments about one support removes that support’s reaction from the equation.
Free-body diagram
Replace the supports with reaction forces. A roller gives one vertical reaction; with only vertical loads the pin gives one vertical reaction too.
Equilibrium
Moments about A, counter-clockwise positive. Then vertical force balance.
UDL resultant: W = w·ℓ = 8·1 = 8 kN, acting at x̄ = 3.5 m
ΣMA = 0: RB·6 = 15·5 + 8·1·3.5
RB = 103/6 = 17.17 kN
ΣFy = 0: RA = 23 − 17.17 = 5.833 kN
Answer
RB = 17.17 kN
3.Truss: method of joints
Answer: FBC = −40.56 kN
Method of joints: every pin of a truss is in equilibrium, so ΣFx = 0 and ΣFy = 0 at each joint. Start at a joint with at most two unknown member forces. A negative result means the member is in compression.
Support reactions
Equilibrium of the whole truss. Moments about A, counter-clockwise positive.
ΣMA = 0: Cy·8 = 45·6 → Cy = 33.75 kN
ΣFy = 0: Ay = 45 − 33.75 = 11.25 kN
Joint C
The roller gives only a vertical reaction, so joint C has just two unknown member forces. Assume both in tension.
sin γ = 3/3.606 = 0.8321, cos γ = 2/3.606 = 0.5547
Method of joints: every pin of a truss is in equilibrium, so ΣFx = 0 and ΣFy = 0 at each joint. Start at a joint with at most two unknown member forces. A negative result means the member is in compression.
Support reactions
Equilibrium of the whole truss. Moments about A, counter-clockwise positive.
ΣMA = 0: Cy·5 = 15·3 + 15·4 → Cy = 21 kN
ΣFy = 0: Ay = 15 − 21 = −6 kN
ΣFx = 0: Ax = −15 kN
Joint C
The roller gives only a vertical reaction, so joint C has just two unknown member forces. Assume both in tension.
sin γ = 4/4.472 = 0.8944, cos γ = 2/4.472 = 0.4472
Largest bending moment: M changes slope wherever the shear force changes, so its peaks sit where the shear force crosses zero: under a point load, inside a distributed load, or over a support of an overhang. At a fixed support of a cantilever the moment is largest at the wall. Compare the size of M at those places, sagging or hogging.
Support reactions
Take moments about one support, then use the vertical force balance.
R1 = 43.5 kN, R2 = 43.5 kN
Bending moment at every mark
Sum the moments of all forces on one side of the cut. Sagging is positive, hogging negative.
MA = 0, MB = 75, MC = 126, MD = 153 kN·m, ME = 126, MF = 75, MG = 0
Answer
Mark D: MD = 153 kN·m
6.Shear force & bending moment
Answer: E (x = 8 m)
Largest bending moment: M changes slope wherever the shear force changes, so its peaks sit where the shear force crosses zero: under a point load, inside a distributed load, or over a support of an overhang. At a fixed support of a cantilever the moment is largest at the wall. Compare the size of M at those places, sagging or hogging.
Support reactions
Take moments about one support, then use the vertical force balance.
R1 = 77.67 kN, R2 = 149.3 kN
Bending moment at every mark
Sum the moments of all forces on one side of the cut. Sagging is positive, hogging negative.
MA = 0, MB = −100, MC = −68.67, MD = −85.33, ME = −240 kN·m, MF = −120, MG = 0
Answer
Mark E: ME = −240 kN·m
7.Beam deflection
Answer: δmax = 8.333 mm
Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).
Consistent units
Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.
w = 6 N/mm, L = 4000 mm
EI = 2.4 × 10¹² N·mm²
Deflection
δmax = 5wL⁴/(384EI) = 5·6·4000⁴/(384·2.4 × 10¹²) = 8.333 mm
Answer
δmax = 8.333 mm
8.Beam deflection
Answer: δmax = 1.9 mm
Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).
Consistent units
Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.
P = 16000 N, w = 12 N/mm, L = 3000 mm, EI = 1.14 × 10¹³ N·mm²
Each load on its own
δP = PL³/(48EI) = 16000·3000³/(48·1.14 × 10¹³) = 0.7895 mm
δw = 5wL⁴/(384EI) = 5·12·3000⁴/(384·1.14 × 10¹³) = 1.11 mm
Add them
δmax = 0.7895 + 1.11 = 1.9 mm
Answer
δmax = 1.9 mm
9.Column buckling
Answer: Pcr = 441 kN
Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.
Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.
Smallest second moment of area
A round section has the same I about every axis.
I = πd⁴/64 = π·50⁴/64 = 306796 mm⁴
Radius of gyration and slenderness
A = 1963 mm²
r = √(I/A) = √(306796/1963) = 12.5 mm
KL = 1·2000 = 2000 mm
KL/r = 2000/12.5 = 160
Critical stress
σcr = π²E/(KL/r)² = π²·200000/160² = 77.11 MPa
Answer
σcr = 77.11 MPa
11.Centroid & second moment of area
Answer: Sx = 2655 × 10³ mm³
Second moment of area: for a rectangle about its own centroidal axis I = bh³/12, and about its base bh³/3 (parallel-axis theorem I = Ic + A·d²). A hole is handled by subtracting its I, as long as both parts share the same axis. The elastic section modulus is S = I/c, where c is the distance to the extreme fibre.
Outer rectangle minus the two side cut-outs
Both cut-outs together are (B − tw) wide and hw = H − 2tf high, and share the axis x.
Composite areas: split the section into rectangles. The centroid is the area-weighted average ȳ = ΣAᵢyᵢ/ΣAᵢ. The second moment of area about the centroidal axis adds each part’s own bh³/12 and its parallel-axis term A·d², where d is the distance from the part’s centroid to the overall centroid. Bending stress is σ = M·y/I.
Split into two rectangles
Measure every y from the bottom edge.
flange: Af = 180·30 = 5400 mm², yf = 280 + 30/2 = 295 mm
Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).
Total stress
Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.
σ = γd·zw + γsat·(z − zw) = 16·4 + 20·7 = 204 kPa
Answer
σ = 204 kPa
14.Effective stress in soil
Answer: u = 39.24 kPa
Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).
Pore water pressure
Water pressure grows with depth below the water table.
u = γw·(z − zw) = 9.81·4 = 39.24 kPa
Answer
u = 39.24 kPa
15.Consolidation settlement
Answer: S = 14.09 mm
Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.
Compare with the preconsolidation pressure
σ′f = 90 + 85 = 175 kPa ≤ 210 kPa
Settlement
The clay stays on its recompression line.
S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0) = 0.02·5/(1 + 1.05)·log₁₀(175/90) = 14.09 mm
Answer
S = 14.09 mm
16.Consolidation settlement
Answer: t = 1350 days
Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.
Drainage paths
Hdr,lab = 25/2 = 12.5 mm = 0.0125 m
Hdr,field = 4.5 m
Scale the time
t = Tv·Hdr²/cv with the same T_v and cv in the lab and the field.
tfield = 15·(4.5/0.0125)² = 1.944 × 10⁶ min
tfield = 1.944 × 10⁶/1440 = 1350 days
Answer
t = 1350 days
17.Hydrostatic force
Answer: F = 128.8 kN
Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.
Centroid depth and area
yc = d + H/2 = 0.5 + 2.5/2 = 1.75 m
A = H·b = 2.5·3 = 7.5 m²
Resultant force
F = ρ·g·yc·A = 1000·9.81·1.75·7.5 = 128.8 kN
Answer
F = 128.8 kN
18.Hydrostatic force
Answer: F = 45.25 kN
Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.
Centroid depth and area
yc = d + H/2 = 0.5 + 2/2 = 1.5 m
A = H·b = 2·1.5 = 3 m²
Resultant force
F = ρ·g·yc·A = 1025·9.81·1.5·3 = 45.25 kN
Answer
F = 45.25 kN
19.Pipe friction & head loss
Answer: Δp = 161.3 kPa
Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.
Head loss
hf = f·(L/D)·V²/(2g) = 0.028·(200/0.1)·2.4²/(2·9.81) = 16.44 m
Pressure drop
The pipe is horizontal and the velocity does not change, so the energy equation reduces to Δp = ρ·g·hf.
Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.
Velocity
V = Q/A = 0.2/0.07069 = 2.829 m/s
V²/(2g) = 0.408 m
Loss coefficients
f·L/D = 0.025·200/0.3 = 16.67
ΣK = 0.5 + 3·0.3 + 2 + 1.0 = 4.4
Total head loss
hf = 16.67·0.408 = 6.801 m
hm = 4.4·0.408 = 1.795 m
Δz = hf + hm = 8.596 m
Answer
Δz = 8.596 m
21.Open-channel flow (Manning)
Answer: Q = 18.98 m³/s
Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.
Geometry
A = b·y = 5.5·2.3 = 12.65 m²
P = b + 2y = 5.5 + 2·2.3 = 10.1 m
R = A/P = 1.252 m
Velocity
V = (1/0.03)·1.2522/3·0.00151/2 = 1.5 m/s
Flow rate
Q = A·V = 12.65·1.5 = 18.98 m³/s
Answer
Q = 18.98 m³/s
22.Open-channel flow (Manning)
Answer: S = 0.0005038 m/m
Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.
Geometry
A = (b + z·y)·y = (2 + 3·1.2)·1.2 = 6.72 m²
P = b + 2y·√(1 + z²) = 2 + 2·1.2·√(1 + 3²) = 9.589 m
Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.
Hydraulic power
Ph = ρ·g·Q·H = 1000·9.81·0.04·12 = 4.709 kW
Efficiency
η = Ph/Pshaft = 4.709/7.8 = 60.37%
Answer
η = 60.37%
24.Pumps & pump power
Answer: Pshaft = 11.37 kW
Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Exponent
r·t = 0.07·2 = 0.14
e0.14 = 1.15
Future value
FV = 1 000·1.15 = €1 150.27
Answer
FV = €1 150.27
26.Time value of money
Answer: A = 597.6 €
Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.
Monthly rate and number of payments
i = 0.048/12 = 0.004
N = 12·3 = 36
Payment
The present value of N equal payments A is A·(1 − (1 + i)⁻ᴺ)/i. Set it equal to the loan and solve for A.
(1 + i)−N = 0.8661
A = 20 000·0.004/(1 − 0.8661) = €597.62
Answer
A = €597.62
27.NPV & IRR
Answer: NPV = −9576 €
Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.
Present value of each cash flow
CF0 = −45 000
CF1/(1 + 0.1)1 = 15 000/1.1 = 13 636.36
CF2/(1 + 0.1)2 = 10 000/1.21 = 8 264.46
CF3/(1 + 0.1)3 = 18 000/1.331 = 13 523.67
Add them up
NPV = €−9 575.51
Answer
NPV = €−9 575.51
NPV is negative, so the project earns less than the required return.
28.NPV & IRR
Answer: IRR = 10.17 %
Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.
Bracket the IRR
NPV falls as the rate rises, so the IRR lies between a rate with positive NPV and one with negative NPV.
NPV(10%) = 123.97
NPV(15%) = −3 327.03
Narrow down
Linear interpolation gives a first estimate; repeating it (or a calculator's IRR function) gives the exact rate.
From an area back to z: Φ(z) is the area to the left of z. For a left-tail area A, find z with Φ(z) = A in the table. A right-tail area A means Φ(z) = 1 − A. A central area A between −z and z leaves (1 − A)/2 in each tail, so Φ(z) = (1 + A)/2. For a value x, use x = μ + zσ.
Area to the left of z
Φ(z) = (1 + 0.6265)/2 = 0.8133
Read the z-table backwards
Find 0.8133 inside the table and read off z.
z = 0.89
Answer
z = 0.89
30.Normal distribution
Answer: x = 96.3 points
From an area back to z: Φ(z) is the area to the left of z. For a left-tail area A, find z with Φ(z) = A in the table. A right-tail area A means Φ(z) = 1 − A. A central area A between −z and z leaves (1 − A)/2 in each tail, so Φ(z) = (1 + A)/2. For a value x, use x = μ + zσ.
Area to the left
Φ(z) = 0.4
z from the table
z ≈ −0.25
Back to the original units
x = 100 − 0.25·15 = 96.3 points
Answer
x = 96.3 points
This is independent practice material. ExamProblems is not affiliated with or endorsed by the organisation that runs this exam, and the exam name is used only to describe the content. The FE exam is run by NCEES, which is not affiliated with ExamProblems and does not endorse it.