FE Civil exam practice: cram pack

Formula sheets, the key method steps for every topic and 30 practice problems, with full solutions at the back.

New problemsBack to the course

In the print window, choose “Save as PDF” to keep a copy on your device.

1Formulas and methods

Beam support reactions

Equilibrium
ΣFx = 0, ΣFy = 0, ΣM = 0
Uniform load
resultant w·L at the middle of the load
Moment
M = F·d

Method

  1. Draw a free-body diagram and replace each support by its reactions.
  2. Replace every distributed load by a single force at its centroid.
  3. Take moments about one support to find the reaction at the other.
  4. Use ΣFy = 0 to find the remaining reaction, and check with a second moment equation.

Truss: method of joints

Method of joints
ΣFx = 0, ΣFy = 0 at each joint
Method of sections
ΣM = 0 about a cut point
Member force
positive = tension, negative = compression

Method

  1. Find the support reactions for the whole truss.
  2. Method of joints: start at a joint with at most two unknown member forces and use ΣFx = 0 and ΣFy = 0.
  3. Method of sections: cut through the member you need and take moments about a point where the other unknown members meet.
  4. Assume tension; a negative answer means compression.

Shear force & bending moment

Shear and moment
V = ΣF on one side, M = ΣF·d on one side
Bending stress
σ = M·y/I
Rectangle
I = bh³/12
Section modulus
W = I/ymax
Simply supported, uniform load
Mmax = wL²/8

Method

  1. Find the support reactions from equilibrium of the whole beam.
  2. Cut the beam at the section you need and keep one side.
  3. Shear force: sum of the vertical forces on that side. Bending moment: sum of their moments about the cut.
  4. For the maximum moment, find where the shear force is zero.

Beam deflection

Point load at midspan
δ = PL³/(48EI)
Uniform load, simply supported
δ = 5wL⁴/(384EI)
Cantilever, end load
δ = PL³/(3EI)
Cantilever, uniform load
δ = wL⁴/(8EI)
Superposition
δ = δ1 + δ2

Column buckling

Euler load
Pcr = π²EI/(KL)²
Effective length factor
K = 1 pinned–pinned, 0.5 fixed–fixed, 0.7 fixed–pinned, 2 fixed–free
Critical stress
σcr = Pcr/A
Slenderness
λ = KL/r, r = √(I/A)

Centroid & second moment of area

Centroid
ȳ = ΣAiyi/ΣAi
Rectangle
I = bh³/12
Parallel-axis theorem
I = Ic + A·d²
Composite section
I = Σ(Ic,i + Aidi²)

Effective stress in soil

Total stress
σ = Σγi·hi
Pore water pressure
u = γw·(z − zw)
Effective stress
σ′ = σ − u
Water
γw = 9.81 kN/m³

Consolidation settlement

Normally consolidated
S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0)
Final stress
σ′f = σ′0 + Δσ (at mid-depth of the layer)
Overconsolidated, σ′f ≤ σ′p
S = Cr·H/(1 + e0)·log₁₀(σ′f/σ′0)
Overconsolidated, σ′f > σ′p
S = H/(1 + e0)·[Cr·log₁₀(σ′p/σ′0) + Cc·log₁₀(σ′f/σ′p)]
Overconsolidation ratio
OCR = σ′p/σ′0
Time for consolidation
t = Tv·Hdr²/cv
Drainage path
Hdr = H/2 (double drainage), H (single drainage)
Time factors
U 50% → 0.197, 60% → 0.287, 70% → 0.403, 80% → 0.567, 90% → 0.848

Hydrostatic force

Pressure at depth
p = ρgh
Force on a vertical wall
F = ρg·hc·A
Centre of pressure
yp = yc + Ic/(ycA)
Rectangle
Ic = bH³/12

Pipe friction & head loss

Reynolds number
Re = V·D/ν = ρ·V·D/μ
Flow regime
laminar below Re ≈ 2000, turbulent above Re ≈ 4000
Mean velocity
V = Q/A, A = π·D²/4
Darcy–Weisbach
hf = f·(L/D)·V²/(2g)
Minor losses
hm = ΣK·V²/(2g)
Typical K values
entrance 0.5, exit 1.0, 90° bend ≈ 0.3
Pressure drop
Δp = ρ·g·hf
Two open reservoirs
Δz = (f·L/D + ΣK)·V²/(2g)
Free outlet
H = (1 + f·L/D + ΣK)·V²/(2g)

Open-channel flow (Manning)

Manning equation
V = (1/n)·R2/3·S1/2
Flow rate
Q = A·V
Hydraulic radius
R = A/P (P = wetted perimeter, free surface excluded)
Rectangle
A = b·y, P = b + 2y
Trapezoid (side slope z:1)
A = (b + z·y)·y, P = b + 2y·√(1 + z²)
Circular pipe, full or half full
R = D/4
Required slope
S = (n·Q/(A·R2/3))²

Pumps & pump power

Hydraulic power
Ph = ρ·g·Q·H = Q·Δp
Shaft power
Pshaft = Ph/ηpump
Electrical power
Pel = Pshaft/ηmotor
Pump head
H = Δz + Δp/(ρ·g) + hL
System losses
hL = (f·L/D + ΣK)·V²/(2g)

Time value of money

Future value
FV = PV·(1 + i)n
Present value
PV = FV/(1 + i)n
Several periods per year
i = r/m, N = m·n
Annuity, present value
PV = PMT·[1 − (1 + i)−n]/i
Annuity, future value
FV = PMT·[(1 + i)n − 1]/i

Method

  1. Draw a timeline with every cash flow and its timing.
  2. Match the rate to the period: a monthly rate for monthly payments.
  3. Use FV = PV·(1 + i)ⁿ for single amounts and the annuity formulas for equal payments.
  4. Check the sign and the order of magnitude of the answer.

NPV & IRR

Net present value
NPV = −C0 + Σ CFt/(1 + r)t
Equal cash flows
NPV = −C0 + CF·[1 − (1 + r)−n]/r
Internal rate of return
the r at which NPV = 0
Decision
accept when NPV > 0 (or IRR > required return)

Method

  1. List all cash flows with their year; the investment at year 0 is negative.
  2. Discount each cash flow: CFt/(1 + r)t.
  3. Add them up to get the NPV. Positive means the project earns more than r.
  4. For the IRR, find the rate that makes NPV zero by trial or interpolation.

Normal distribution

z-score
z = (x − μ)/σ
Below x
P(X < x) = Φ(z)
Above x
P(X > x) = 1 − Φ(z)
Between
Φ(z2) − Φ(z1)
Percentile
x = μ + z·σ

Method

  1. Convert the value to a z-score: z = (x − μ)/σ.
  2. Look up Φ(z), the area to the left of z.
  3. For the area to the right use 1 − Φ(z); for an interval subtract the two left areas.
  4. For a percentile, work backwards: find z for the area, then x = μ + z·σ.

2Practice problems

1.Beam support reactionsMedium
w0​ = 4 kN/mP = 40 kNABRA​ = ?2 m3 m

The simply supported beam (pin at A, roller at B) carries a linearly varying load that rises from zero at A to 4 kN/m at B. A point load P also acts at 2 m from A. Find the vertical support reaction RA.

L = 5 mw0 = 4 kN/mP = 40 kN at 2 m
RA = kN
2.Beam support reactionsHard
w = 8 kN/mP = 50 kNABRA​RB​ = ?1 m4 m1 m

The simply supported beam has a pin at A and a roller at B. Find the vertical support reaction RB.

L = 6 mP = 50 kN at 5 mw = 8 kN/m from 1 to 6 m
RB = kN
3.Truss: method of jointsMedium
ABCDEFGH20 kN15 kN20 kN15 kN4 × 4 m3 m

Exactly one member of this truss carries no force under these loads. Which is the zero-force member? Click it in the diagram.

C: 20 kN ↓D: 15 kN ↓G: 20 kN ↓H: 15 kN ↓
  1. 1member AB
  2. 2member BC
  3. 3member CD
  4. 4member DE
  5. 5member FG
  6. 6member GH
  7. 7member AF
  8. 8member HE
  9. 9member BF
  10. 10member CG
  11. 11member DH
  12. 12member FC
  13. 13member HC
4.Truss: method of jointsHard
ABCDEFGH25 kN25 kN40 kN10 kN10 kN4 × 3 m4 m

Exactly one member of this truss carries no force under these loads. Which is the zero-force member? Click it in the diagram.

C: 25 kN ↓D: 25 kN ↓F: 40 kN ↓F: 10 kN →G: 10 kN ↓
  1. 1member AB
  2. 2member BC
  3. 3member CD
  4. 4member DE
  5. 5member FG
  6. 6member GH
  7. 7member AF
  8. 8member HE
  9. 9member BF
  10. 10member CG
  11. 11member DH
  12. 12member FC
  13. 13member HC
5.Shear force & bending momentMedium
5 kN/m45 kNABCDEFG2 m2 m2 m2 m2 m2 m

The marks A to G split the beam into six equal parts. At which mark is the bending moment largest in size, sagging or hogging? Click it in the diagram.

45 kN @ 8 m5 kN/m, 0–12 m
  1. 1A (x = 0 m)
  2. 2B (x = 2 m)
  3. 3C (x = 4 m)
  4. 4D (x = 6 m)
  5. 5E (x = 8 m)
  6. 6F (x = 10 m)
  7. 7G (x = 12 m)
6.Shear force & bending momentHard
w = 12 kN/mABC8 m2.5 m

The beam rests on a pin at A and a roller at B and overhangs B by 2.5 m to the free end C. A uniformly distributed load w acts over the whole length A–C. Find the bending moment MB at support B. Use sagging moments positive and upward shear on the left face positive.

L = 10.5 mw = 12 kN/m from 0 to 10.5 msupports at x = 0 and x = 8 m
MB = kN·m
7.Beam deflectionMedium
w = 8 kN/mδL = 2 m

A simply supported beam carries a uniformly distributed load w over its whole span. Find the maximum deflection δmax, at midspan.

w = 8 kN/mL = 2 mE = 11 GPa (timber)I = 120 × 10⁶ mm⁴
δmax = mm
8.Beam deflectionHard
w = 12 kN/mδL = 4 m

A simply supported beam carries a uniformly distributed load w. Its deflection may not exceed span/360. Find the smallest second moment of area Ireq that meets this limit.

w = 12 kN/mL = 4 mE = 11 GPa (timber)
Ireq = × 10⁶ mm⁴
9.Column bucklingMedium
PL = 6 md = 60 mmcross-section

A column of length L made of steel is fixed at the base and free at the top. Using Euler’s formula, find its critical buckling load Pcr.

L = 6 mE = 200 GPa (steel)d = 60 mm
Pcr = kN
10.Column bucklingHard
PL = 5 md = 50 mmcross-section

A column of length L made of steel is fixed at the base and free at the top. Find its slenderness and the critical buckling stress σcr from Euler’s formula.

L = 5 mE = 200 GPa (steel)d = 50 mm
σcr = MPa
11.Centroid & second moment of areaMedium
1202016020xdimensions in mm

Find the second moment of area Ix of the T-section about the horizontal axis x through its centroid.

bf = 120 mmtf = 20 mmtw = 20 mmhw = 160 mm
Ix = × 10⁶ mm⁴
12.Centroid & second moment of areaHard
16022018260208xdimensions in mm

A welded I-section has a top flange 160 × 18 mm, a web 260 mm high and 8 mm thick, and a bottom flange 220 × 20 mm (width × thickness). Find its second moment of area Ix about the horizontal axis x through its centroid.

top flange: 160 × 18 mmweb: 8 × 260 mmbottom flange: 220 × 20 mm
Ix = × 10⁶ mm⁴
13.Effective stress in soilMedium
sandγd​ = 16 kN/m³γsat​ = 20 kN/m³10 mwater tableXz = 9 m

For the soil profile shown, find the total vertical stress σ at point X.

z = 9 mzw = 4 mγw = 9.81 kN/m³sand: γd = 16 kN/m³sand: γsat = 20 kN/m³
σ = kPa
14.Effective stress in soilHard
sandγd​ = 16.5 kN/m³γsat​ = 18.5 kN/m³5 mclayγsat​ = 17 kN/m³5 mwater tableXz = 7.5 m

For the soil profile shown, find the total vertical stress σ at point X.

z = 7.5 mzw = 2 mγw = 9.81 kN/m³sand: γd = 16.5 kN/m³sand: γsat = 18.5 kN/m³clay: γsat = 17 kN/m³
σ = kPa
15.Consolidation settlementMedium
Δσ = 120 kPasandclayCc​ = 0.5, Cr​ = 0.05e0​ = 0.9σ′0​ = 45 kPaσ′p​ = 85 kPa5 mwater table

A 5 m thick overconsolidated clay layer has Cc = 0.5, Cr = 0.05 and e₀ = 0.9. At its mid-depth the effective vertical stress is 45 kPa and the preconsolidation pressure is 85 kPa. A new building adds 120 kPa of vertical stress at mid-depth. Find the primary consolidation settlement S in mm.

H = 5 mCc = 0.5Cr = 0.05e0 = 0.9σ′0 = 45 kPaσ′p = 85 kPaΔσ = 120 kPa
S = mm
16.Consolidation settlementHard
sandclayH = 8.5 m8.5 msandwater table

In a laboratory oedometer test, a clay specimen 20 mm thick, drained at the top and bottom, reaches 50% consolidation in 15 min. In the field the same clay forms a layer 8.5 m thick. It lies between two sand layers, so water drains out at the top and the bottom. How many days t does the field layer take to reach 50% consolidation?

hlab = 20 mmtlab = 15 minH = 8.5 mfield: double drainage
t = days
17.Hydrostatic forceMedium
gated = 0.5 mH = 1 m

A vertical rectangular gate 3 m wide sits in the wall of a tank of water, with its top edge 0.5 m below the surface. Find the resultant hydrostatic force F on the gate.

d = 0.5 mH = 1 mb = 3 mρ = 1000 kg/m³g = 9.81 m/s²
F = kN
18.Hydrostatic forceHard
gated = 3 mH = 2.5 m

A vertical rectangular gate 3 m wide sits in the wall of a tank of seawater, with its top edge 3 m below the surface. Find the resultant hydrostatic force F on the gate.

d = 3 mH = 2.5 mb = 3 mρ = 1025 kg/m³g = 9.81 m/s²
F = kN
19.Pipe friction & head lossMedium
Q = 6 L/sD = 75 mmL = 1000 mf = 0.028

Water flows at 6 L/s through a pipe 1000 m long with an inside diameter of 75 mm. Use the Darcy friction factor f = 0.028 and g = 9.81 m/s². Find the friction head loss hf.

Q = 6 L/sL = 1000 mD = 75 mmf = 0.028g = 9.81 m/s²
hf = m
20.Pipe friction & head lossHard
K = 10Δz = 8 mL = 300 m, D = 250 mm, f = 0.0223× bend (K = 0.3)

Two open reservoirs are joined by a pipe 300 m long with an inside diameter of 250 mm and a Darcy friction factor f = 0.022. The water surface of the upper reservoir is 8 m above that of the lower one. The minor losses are a square-edged entrance (K = 0.5), 3 bends (K = 0.3 each), a valve (K = 10) and the exit into the lower reservoir (K = 1.0). Use g = 9.81 m/s². Find the flow rate Q in L/s.

Δz = 8 mL = 300 mD = 250 mmf = 0.022Kentrance = 0.5Kbend = 0.3 (×3)Kvalve = 10Kexit = 1.0
Q = L/s
21.Open-channel flow (Manning)Medium
D = 750 mmn = 0.013, S = 0.0005

A concrete storm sewer with an inside diameter of 750 mm flows just full (as an open channel, not under pressure). Manning n = 0.013 and the slope is S = 0.0005. Find the flow rate Q in m³/s.

D = 750 mmn = 0.013S = 0.0005
Q = m³/s
22.Open-channel flow (Manning)Hard
b = 6 my = 0.5 mn = 0.03, Q = 3.6 m³/s

A rectangular grass-lined earth channel 6 m wide must carry 3.6 m³/s in uniform flow at a depth of 0.5 m. Manning n = 0.03. Find the required bed slope S (in m/m).

Q = 3.6 m³/sb = 6 my = 0.5 mn = 0.03
S = m/m
23.Pumps & pump powerMedium
PQ = 50 L/sH = 56 m

In a test, a pump delivers 50 L/s of water (ρ = 1000 kg/m³) against a head of 56 m while its shaft takes 38.2 kW. Use g = 9.81 m/s². Find the pump efficiency η in percent.

Q = 50 L/sH = 56 mPshaft = 38.2 kWg = 9.81 m/s²
η = %
24.Pumps & pump powerHard
400 kPa (gauge)PQ = 80 L/sΔz = 26 mL = 100 m, D = 200 mm, f = 0.015, ΣK = 8

A pump moves 80 L/s of water (ρ = 1000 kg/m³) from an open lower reservoir to an upper tank whose water surface is 26 m higher. The pipe is 100 m long with an inside diameter of 200 mm and a Darcy friction factor f = 0.015; the minor-loss coefficients add up to ΣK = 8 (entrance and exit included). Use g = 9.81 m/s². The upper tank is closed and the air above its water is at a gauge pressure of 400 kPa. Find the head H the pump must add.

Q = 80 L/sΔz = 26 mL = 100 mD = 200 mmf = 0.015ΣK = 8ptank = 400 kPa
H = m
25.Time value of moneyMedium
years012PV = ?€20 000

You need €20 000 in 2 years. An account pays 3.6% per year, compounded quarterly. How much must you deposit today? Find the present value PV.

FV = €20 0003.6% / 4n = 2
PV = €
26.Time value of moneyHard
months0123…204€150€150€150FV = ?

You save €150 at the end of every month for 17 years. The account pays 7.2% per year, compounded monthly. How much have you saved at the end? Find FV.

A = €1507.2% / 12N = 204
FV = €
27.NPV & IRRMedium
years01234567−80 00014 50014 50014 50014 50014 50014 50030 500

A machine costs €80 000 today. It generates €14 500 at the end of each year for 7 years and can then be sold for €16 000. The cost of capital is 12%. Find the net present value NPV.

C0 = €80 000CF = €14 500S = €16 000n = 7r = 12%
NPV = €
28.NPV & IRRHard
r (%)NPVABr* = ?0

Project A costs €40 000 and returns €23 000, €15 500, €9 500 at the end of years 1 to 3. Project B costs €45 000 and returns €13 000, €18 500, €24 000. Find the crossover rate r* at which both projects have the same NPV, in percent.

A: −40 000, 23 000, 15 500, 9 500B: −45 000, 13 000, 18 500, 24 000
r* = %
29.Normal distributionMedium
−3−2−10123zshaded area between −z and z = 0.9523

Drag z so that the shaded area between −z and z under the standard normal curve is 0.9523. Find z to two decimals.

A = 0.9523
z =
30.Normal distributionHard
235240245250255260265gbottom 15%

The bag weights are normally distributed with mean 250 g and standard deviation 5 g. Drag the cut-off so the shaded bottom 15% is to the left of it. Find the cut-off x.

μ = 250 gσ = 5 g15%
x = g

3Solutions

1.Beam support reactions

Answer: RA = 27.33 kN

Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Replace each distributed load by its resultant (its area) acting at the centroid of the load diagram, and take moments about a support to remove that support’s reaction from the equation.

Resultant of the triangular load

W = ½·4·5 = 10 kN
x̄ = 2L/3 = 3.333 m

Equilibrium

Moments about A, counter-clockwise positive. Then vertical force balance.

ΣMA = 0: RB·5 = 10·3.333 + 40·2
RB = 22.67 kN
RA = 50 − 22.67 = 27.33 kN

Answer

RA = 27.33 kN
2.Beam support reactions

Answer: RB = 65 kN

Static equilibrium: a body at rest has ΣFx = 0, ΣFy = 0 and ΣM = 0 about any point. Taking moments about one support removes that support’s reaction from the equation.

w = 8 kN/mP = 50 kNABRA​RB​1 m4 m1 m

Free-body diagram

Replace the supports with reaction forces. A roller gives one vertical reaction; with only vertical loads the pin gives one vertical reaction too.

Equilibrium

Moments about A, counter-clockwise positive. Then vertical force balance.

UDL resultant: W = w·ℓ = 8·5 = 40 kN, acting at x̄ = 3.5 m
ΣMA = 0: RB·6 = 50·5 + 8·5·3.5
RB = 390/6 = 65 kN
ΣFy = 0: RA = 90 − 65 = 25 kN

Answer

RB = 65 kN
3.Truss: method of joints

Answer: member BF

Zero-force members: at a joint, the forces must balance in every direction. If a joint has no load and no support, and two of its three members are in line, then the balance across that line involves only the third member, so its force is zero. If only two members meet at an unloaded joint and they are not in line, both are zero.

Joint B

AB and BC lie on one straight line and the joint carries no load. Balancing forces across that line leaves only BF.

ΣF⊥ = 0 → FBF = 0

Check with the method of joints

Solving all joints gives these member forces (T = tension, C = compression).

AB: 36.67 kN (T), BC: 36.67 kN (T), CD: 56.67 kN (T), DE: 56.67 kN (T), FG: 73.33 kN (C), GH: 73.33 kN (C), AF: 45.83 kN (C), HE: 70.83 kN (C), BF: 0, CG: 20 kN (C), DH: 15 kN (T), FC: 45.83 kN (T), HC: 20.83 kN (T)

Answer

Zero-force member: BF
4.Truss: method of joints

Answer: member BF

Zero-force members: at a joint, the forces must balance in every direction. If a joint has no load and no support, and two of its three members are in line, then the balance across that line involves only the third member, so its force is zero. If only two members meet at an unloaded joint and they are not in line, both are zero.

Joint B

AB and BC lie on one straight line and the joint carries no load. Balancing forces across that line leaves only BF.

ΣF⊥ = 0 → FBF = 0

Check with the method of joints

Solving all joints gives these member forces (T = tension, C = compression).

AB: 47.81 kN (T), BC: 47.81 kN (T), CD: 37.19 kN (T), DE: 37.19 kN (T), FG: 55.63 kN (C), GH: 55.63 kN (C), AF: 63.02 kN (C), HE: 61.98 kN (C), BF: 0, CG: 10 kN (C), DH: 25 kN (T), FC: 13.02 kN (T), HC: 30.73 kN (T)

Answer

Zero-force member: BF
5.Shear force & bending moment

Answer: E (x = 8 m)

Largest bending moment: M changes slope wherever the shear force changes, so its peaks sit where the shear force crosses zero: under a point load, inside a distributed load, or over a support of an overhang. At a fixed support of a cantilever the moment is largest at the wall. Compare the size of M at those places, sagging or hogging.

Support reactions

Take moments about one support, then use the vertical force balance.

R1 = 45 kN, R2 = 60 kN

Bending moment at every mark

Sum the moments of all forces on one side of the cut. Sagging is positive, hogging negative.

MA = 0, MB = 80, MC = 140, MD = 180, ME = 200 kN·m, MF = 110, MG = 0

Answer

Mark E: ME = 200 kN·m
6.Shear force & bending moment

Answer: MB = −37.5 kN·m

Method of sections: cut the beam where you want the internal forces and keep one side. The shear force V balances the vertical forces on that side, and the bending moment M balances their moments about the cut. Maximum moment: since dM/dx = V, the bending moment has its peak where the shear force passes through zero, either at a point load or inside a distributed load.

Support reactions

Equilibrium of the whole beam, including the load on the overhang.

UDL resultant: W = w·ℓ = 12·10.5 = 126 kN, acting at x̄ = 5.25 m
ΣMA = 0: RB·8 = 12·10.5·5.25
RB = 661.5/8 = 82.69 kN
ΣFy = 0: RA = 126 − 82.69 = 43.31 kN

Cut at B and keep the overhang

The load on the overhang, w·a, acts at a/2 from B and makes the beam hog over the support.

MB = −w·a²/2 = −12·2.5²/2 = −37.5 kN·m

Answer

MB = −37.5 kN·m
7.Beam deflection

Answer: δmax = 1.263 mm

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).

Consistent units

Work in N and mm: P in N, w in N/mm (kN/m = N/mm), L in mm, E in N/mm² (GPa × 1000), I in mm⁴.

w = 8 N/mm, L = 2000 mm
EI = 1.32 × 10¹² N·mm²

Deflection

δmax = 5wL⁴/(384EI) = 5·8·2000⁴/(384·1.32 × 10¹²) = 1.263 mm

Answer

δmax = 1.263 mm
8.Beam deflection

Answer: Ireq = 327.3 × 10⁶ mm⁴

Beam deflection: deflections come from integrating the curvature M/(EI) twice. Standard cases are tabulated, for example PL³/(3EI) for a cantilever with an end load and 5wL⁴/(384EI) for a simply supported beam under a full uniform load. Deflections from separate loads add (superposition).

Deflection limit

δallow = L/360 = 4000/360 = 11.11 mm

Required second moment of area

I = 5wL⁴/(384·E·δallow) = 5·12·4000⁴/(384·11000·11.11) = 3.273 × 10⁸ mm⁴
Ireq = 327.3 × 10⁶ mm⁴

Answer

Ireq = 327.3 × 10⁶ mm⁴
9.Column buckling

Answer: Pcr = 8.721 kN

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Smallest second moment of area

A round section has the same I about every axis.

I = πd⁴/64 = π·60⁴/64 = 636173 mm⁴

Effective length

KL = 2·6000 = 12000 mm

Critical load

Pcr = π²EI/(KL)² = π²·200000·636173/12000² = 8721 N = 8.721 kN

Answer

Pcr = 8.721 kN
10.Column buckling

Answer: σcr = 3.084 MPa

Euler buckling: a slender column becomes unstable at Pcr = π²EI/(KL)², where KL is the effective length: K = 1 for pinned–pinned, 2 for fixed–free, 0.7 for fixed–pinned and 0.5 for fixed–fixed. It buckles about the axis with the smallest I. The formula holds for slender columns, whose critical stress stays below the yield stress.

Smallest second moment of area

A round section has the same I about every axis.

I = πd⁴/64 = π·50⁴/64 = 306796 mm⁴

Radius of gyration and slenderness

A = 1963 mm²
r = √(I/A) = √(306796/1963) = 12.5 mm
KL = 2·5000 = 10000 mm
KL/r = 10000/12.5 = 800

Critical stress

σcr = π²E/(KL/r)² = π²·200000/800² = 3.084 MPa

Answer

σcr = 3.084 MPa
11.Centroid & second moment of area

Answer: Ix = 18.02 × 10⁶ mm⁴

Composite areas: split the section into rectangles. The centroid is the area-weighted average ȳ = ΣAᵢyᵢ/ΣAᵢ. The second moment of area about the centroidal axis adds each part’s own bh³/12 and its parallel-axis term A·d², where d is the distance from the part’s centroid to the overall centroid. Bending stress is σ = M·y/I.

Split into two rectangles

Measure every y from the bottom edge.

flange: Af = 120·20 = 2400 mm², yf = 160 + 20/2 = 170 mm
web: Aw = 20·160 = 3200 mm², yw = 160/2 = 80 mm

Centroid

ȳ = (Afyf + Awyw)/(Af + Aw) = (2400·170 + 3200·80)/5600 = 118.6 mm

Parallel-axis theorem

flange: 120·20³/12 + 2400·(170 − 118.6)² = 6.428 × 10⁶ mm⁴
web: 20·160³/12 + 3200·(80 − 118.6)² = 1.159 × 10⁷ mm⁴
Ix = 6.428 × 10⁶ + 1.159 × 10⁷ = 1.802 × 10⁷ mm⁴ = 18.02 × 10⁶ mm⁴

Answer

Ix = 18.02 × 10⁶ mm⁴
12.Centroid & second moment of area

Answer: Ix = 148.9 × 10⁶ mm⁴

Composite areas: split the section into rectangles. The centroid is the area-weighted average ȳ = ΣAᵢyᵢ/ΣAᵢ. The second moment of area about the centroidal axis adds each part’s own bh³/12 and its parallel-axis term A·d², where d is the distance from the part’s centroid to the overall centroid. Bending stress is σ = M·y/I.

Split into three rectangles

Measure every y from the bottom edge.

top flange: A = 2880 mm², y = 289 mm
web: A = 2080 mm², y = 150 mm
bottom flange: A = 4400 mm², y = 10 mm

Centroid

ȳ = (2880·289 + 2080·150 + 4400·10)/9360 = 127 mm

Parallel-axis theorem

top flange: 160·18³/12 + 2880·162² = 7.57 × 10⁷ mm⁴
web: 8·260³/12 + 2080·23.04² = 1.282 × 10⁷ mm⁴
bottom flange: 220·20³/12 + 4400·117² = 6.033 × 10⁷ mm⁴
Ix = 7.57 × 10⁷ + 1.282 × 10⁷ + 6.033 × 10⁷
Ix = 1.489 × 10⁸ mm⁴ = 148.9 × 10⁶ mm⁴

Answer

Ix = 148.9 × 10⁶ mm⁴
13.Effective stress in soil

Answer: σ = 164 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Total stress

Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.

σ = γd·zw + γsat·(z − zw) = 16·4 + 20·5 = 164 kPa

Answer

σ = 164 kPa
14.Effective stress in soil

Answer: σ = 131 kPa

Effective stress (Terzaghi): the soil skeleton carries σ′ = σ − u. The total stress σ is the weight of everything above the point, Σγ·h, using the dry unit weight above the water table and the saturated unit weight below it. Below the water table the pore water pressure is hydrostatic: u = γw·(depth below the water table).

Total stress

Add the weight of each soil band above X. Above the water table use the dry unit weight, below it the saturated one.

σ = γd·2 + γsat,sand·3 + γsat,clay·2.5
σ = 16.5·2 + 18.5·3 + 17·2.5 = 131 kPa

Answer

σ = 131 kPa
15.Consolidation settlement

Answer: S = 415.4 mm

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Compare with the preconsolidation pressure

σ′f = 45 + 120 = 165 kPa > 85 kPa

Settlement

Recompression up to σ′p, virgin compression beyond it.

S = 0.05·5/(1 + 0.9)·log₁₀(85/45) + 0.5·5/(1 + 0.9)·log₁₀(165/85)
S = 36.34 + 379 = 415.4 mm

Answer

S = 415.4 mm
16.Consolidation settlement

Answer: t = 1882 days

Primary consolidation of a clay layer of thickness H, using the effective stress at the middle of the layer: σ′f = σ′0 + Δσ. Normally consolidated clay: S = Cc·H/(1 + e0)·log₁₀(σ′f/σ′0). Overconsolidated clay recompresses along Cr up to the preconsolidation pressure σ′p and follows Cc only beyond it. Time: t = Tv·Hdr²/cv, where the drainage path Hdr is H/2 when water can leave at the top and bottom, and H when only one side drains.

Drainage paths

Hdr,lab = 20/2 = 10 mm = 0.01 m
Hdr,field = 8.5/2 = 4.25 m

Scale the time

t = Tv·Hdr²/cv with the same T_v and cv in the lab and the field.

tfield = 15·(4.25/0.01)² = 2.709 × 10⁶ min
tfield = 2.709 × 10⁶/1440 = 1882 days

Answer

t = 1882 days
17.Hydrostatic force

Answer: F = 29.43 kN

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 0.5 + 1/2 = 1 m
A = H·b = 1·3 = 3 m²
gated = 0.5 mH = 1 mF

Resultant force

F = ρ·g·yc·A = 1000·9.81·1·3 = 29.43 kN

Answer

F = 29.43 kN
18.Hydrostatic force

Answer: F = 320.5 kN

Hydrostatic force on a plane surface: F = ρ·g·yc·A. It acts at the centre of pressure, ycp = yc + Ic/(ycA), which always lies below the centroid.

Centroid depth and area

yc = d + H/2 = 3 + 2.5/2 = 4.25 m
A = H·b = 2.5·3 = 7.5 m²
gated = 3 mH = 2.5 mF

Resultant force

F = ρ·g·yc·A = 1025·9.81·4.25·7.5 = 320.5 kN

Answer

F = 320.5 kN
19.Pipe friction & head loss

Answer: hf = 35.1 m

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Mean velocity

A = π·0.075²/4 = 0.004418 m²
V = Q/A = 0.006/0.004418 = 1.358 m/s

Velocity head

V²/(2g) = 1.358²/(2·9.81) = 0.09401 m

Darcy–Weisbach

hf = f·(L/D)·V²/(2g) = 0.028·(1000/0.075)·1.358²/(2·9.81) = 35.1 m

Answer

hf = 35.1 m
20.Pipe friction & head loss

Answer: Q = 98.73 L/s

Pipe flow: the Reynolds number Re = V·D/ν = ρ·V·D/μ tells laminar flow (Re below about 2000) from turbulent flow (above about 4000). Friction along a pipe costs the Darcy–Weisbach head loss hf = f·(L/D)·V²/(2g). Fittings, valves, the entrance and the exit add minor losses hm = ΣK·V²/(2g). Between two open reservoir surfaces the energy equation gives Δz = hf + hm, with the exit loss K = 1 included.

Loss coefficients

f·L/D = 0.022·300/0.25 = 26.4
ΣK = 0.5 + 3·0.3 + 10 + 1.0 = 12.4

Energy equation

Both surfaces are open to the air and practically at rest, so all of Δz is lost in the pipe.

8 = (26.4 + 12.4)·V²/(2·9.81)
V = √(2·9.81·8/38.8) = 2.011 m/s

Flow rate

Q = V·π·D²/4 = 2.011·0.04909 = 0.09873 m³/s = 98.73 L/s

Answer

Q = 98.73 L/s
21.Open-channel flow (Manning)

Answer: Q = 0.2489 m³/s

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Geometry

A = 0.4418 m², R = D/4 = 0.1875 m

Velocity

V = (1/0.013)·0.18752/3·0.00051/2 = 0.5635 m/s

Flow rate

Q = A·V = 0.4418·0.5635 = 0.2489 m³/s

Answer

Q = 0.2489 m³/s
22.Open-channel flow (Manning)

Answer: S = 0.004011 m/m

Manning’s equation (SI): for uniform flow in an open channel V = (1/n)·R2/3·S1/2 and Q = A·V, with n the roughness coefficient, S the bed slope (m/m) and R = A/P the hydraulic radius: flow area divided by wetted perimeter. Only the boundary in contact with the water counts in P, not the free surface. Rectangle: A = b·y, P = b + 2y. Trapezoid with side slopes z:1 (horizontal:vertical): A = (b + z·y)·y, P = b + 2y·√(1 + z²). A circular pipe flowing full or half full has R = D/4.

Geometry

A = b·y = 6·0.5 = 3 m²
P = b + 2y = 6 + 2·0.5 = 7 m
R = A/P = 0.4286 m

Solve Manning for S

S1/2 = n·Q/(A·R2/3) = 0.03·3.6/(3·0.5684) = 0.06333
S = 0.06333² = 0.004011

Answer

S = 0.004011

That is a fall of 4.011 m per kilometre.

23.Pumps & pump power

Answer: η = 71.91 %

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Hydraulic power

Ph = ρ·g·Q·H = 1000·9.81·0.05·56 = 27.47 kW

Efficiency

η = Ph/Pshaft = 27.47/38.2 = 71.91%

Answer

η = 71.91%
24.Pumps & pump power

Answer: H = 71.9 m

Pump power: the power given to the water is the hydraulic power Ph = ρ·g·Q·H = Q·Δp. The shaft must deliver more because the pump loses some: Pshaft = Ph/ηpump, and the motor draws Pel = Pshaft/ηmotor. The pump head H follows from the energy equation: static lift + pressure head + all friction and minor losses.

Velocity

V = Q/A = 0.08/0.03142 = 2.546 m/s
V²/(2g) = 0.3305 m

Head losses

hL = (f·L/D + ΣK)·V²/(2g) = (7.5 + 8)·0.3305 = 5.123 m

Pressure head

p/(ρ·g) = 400000/(1000·9.81) = 40.77 m

Pump head

Both surfaces are practically at rest, so there is no velocity head term.

H = Δz + p/(ρ·g) + hL = 26 + 40.77 + 5.123 = 71.9 m

Answer

H = 71.9 m
25.Time value of money

Answer: PV = 18617 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Rate and number of periods

i = 0.036000000000000004/4 = 0.009
N = 4·2 = 8

Present value

PV = FV/(1 + i)N = 20 000/1.074 = €18 616.61

Answer

PV = €18 616.61
26.Time value of money

Answer: FV = 59709 €

Time value of money: money today is worth more than the same amount later, because it can earn interest. With interest rate i per period, an amount grows as FV = PV·(1 + i)n. A series of equal payments (an annuity) is valued by adding up each payment, which gives the annuity formulas.

Monthly rate and number of deposits

i = 0.07200000000000001/12 = 0.006
N = 12·17 = 204

Future value of the deposits

FV = A·((1 + i)N − 1)/i = 150·(3.388 − 1)/0.006 = €59 708.71

Answer

FV = €59 708.71

You paid in €30 600 yourself; the rest is interest.

27.NPV & IRR

Answer: NPV = −6588 €

Net present value: discount every cash flow back to today with the required rate of return r, then add them up: NPV = Σ CFₜ/(1 + r)ᵗ. A project with NPV > 0 earns more than r and adds value. The internal rate of return (IRR) is the rate at which NPV = 0.

Present value of the yearly cash flows

14 500·4.564 = 66 174.47

Present value of the salvage value

16 000/2.211 = 7 237.59

NPV

NPV = −80 000 + 66 174.47 + 7 237.59 = −€6 587.94

Answer

NPV = −€6 587.94
28.NPV & IRR

Answer: r* = 7.381 %

Crossover rate: the discount rate at which two projects have the same NPV. It is the IRR of the difference in their cash flows (B − A). Below it the project with the later, larger cash flows has the higher NPV; above it the other one wins.

Difference in cash flows

ΔCF0 = −45 000 − (−40 000) = −5 000
ΔCF1 = 13 000 − 23 000 = −10 000
ΔCF2 = 18 500 − 15 500 = 3 000
ΔCF3 = 24 000 − 9 500 = 14 500

IRR of the difference

NPVΔ(7%) = 110.84
NPVΔ(8%) = −176.68
r* = 7.381%

Answer

r* = 7.381%

Check: at 7.381% both NPVs are €2 534.27.

29.Normal distribution

Answer: z = 1.98

From an area back to z: Φ(z) is the area to the left of z. For a left-tail area A, find z with Φ(z) = A in the table. A right-tail area A means Φ(z) = 1 − A. A central area A between −z and z leaves (1 − A)/2 in each tail, so Φ(z) = (1 + A)/2. For a value x, use x = μ + zσ.

Area to the left of z

Φ(z) = (1 + 0.9523)/2 = 0.9761

Read the z-table backwards

Find 0.9761 inside the table and read off z.

z = 1.98

Answer

z = 1.98
30.Normal distribution

Answer: x = 244.8 g

From an area back to z: Φ(z) is the area to the left of z. For a left-tail area A, find z with Φ(z) = A in the table. A right-tail area A means Φ(z) = 1 − A. A central area A between −z and z leaves (1 − A)/2 in each tail, so Φ(z) = (1 + A)/2. For a value x, use x = μ + zσ.

Area to the left

Φ(z) = 0.15

z from the table

z ≈ −1.04

Back to the original units

x = 250 − 1.04·5 = 244.8 g

Answer

x = 244.8 g

This is independent practice material. ExamProblems is not affiliated with or endorsed by the organisation that runs this exam, and the exam name is used only to describe the content. The FE exam is run by NCEES, which is not affiliated with ExamProblems and does not endorse it.